Attachment_01_-_MASTER_SOW_-_150415.pdf
PDF 518 KB Posted
- Attached to
- Amphibious Combat Vehicle 1. 1 Federal contract opportunity
- Solicitation number
- M67854-15-R-0001
- Issued by
- United States Marine Corps
About this file
Attachment 01 - MASTER SOW - 150415
View the file
Other files for this federal contract opportunity
Show all 50
Amphibious Combat Vehicle 1. 1 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACV-SOW-03001
UNCLASSIFIED
Statement of Work (SOW)
For the Amphibious Combat Vehicle (ACV)
M67854-15-R-0001 Section J, Attachment 01
ACV-SOW-03001
Version 1.1
15 April 2015
DISTRIBUTION A: Approved for public release: distribution unlimited.
Revision Date Summary of Changes
1.0 19 Mar 2015 Initial release of the RFP
1.1 15 April 2015
Section 3.6.4.1.2 – “up to the beginning of Government organic supply support” was removed from the end of the 2nd sentence
This page blank
TABLE OF CONTENTS
ACV-SOW-03001 Unclassified
1 SCOPE
1.1 BACKGROUND
1.2 INTRODUCTION OF THE STATEMENT OF WORK
2 APPLICABLE DOCUMENTS
2.1 GOVERNMENT DOCUMENTS
2.1.1 SPECIFICATIONS, STANDARDS, AND HANDBOOKS
2.2 OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
2.2.1 REGULATIONS, FEDERAL ACQUISITION REGULATIONS, DEFENSE FEDERAL
ACQUISITION REGULATION SUPPLEMENTS, MANUALS, DIRECTIVES, INSTRUCTIONS, AND
FORMS 4
2.3 NON-GOVERNMENT DOCUMENTS
2.3.1 STANDARDS AND GUIDEBOOKS
2.4 AVAILABILITY OF DEPARTMENT OF DEFENSE DOCUMENTS
3 REQUIREMENTS
3.1 GENERAL REQUIREMENTS OVERVIEW
3.1.1 RESOURCE REQUIREMENTS
3.1.2 SECURITY
3.1.3 OPERATIONS SECURITY PLAN
3.1.4 PROGRAM PROTECTION IMPLEMENTATION PLAN
3.2 PROGRAM MANAGEMENT
3.2.1 ASSIGNMENT OF RESPONSIBILITY AND AUTHORITY
3.2.2 CONFERENCES, REVIEWS, AGENDAS, AND REPORTS
3.2.3 MONTHLY PROGRESS STATUS REPORTS
3.2.4 INTEGRATED MASTER PLANNING/INTEGRATED MASTER SCHEDULING/SCHEDULE
RISK ASSESSMENT
3.2.5 CONTRACTOR WORK BREAKDOWN STRUCTURE
3.2.6 RESERVED
3.2.7 RESERVED
3.2.8 COST ESTIMATING AND ANALYSIS
3.2.9 RESERVED
3.2.10 CONTRACTOR CONTROLLED LIFE CYCLE COST ESTIMATE
3.2.11 MATERIAL PRICING REPORT
3.2.12 TIME SERIES LOT SIZE PRICING DATA
3.2.13 FINANCIAL MANAGEMENT
3.3 SYSTEMS ENGINEERING
3.3.1 TECHNICAL REVIEWS
3.3.2 SYSTEMS ENGINEERING MANAGEMENT
3.3.3 QUALITY
3.3.4 REQUIREMENTS MANAGEMENT
3.3.5 INTERFACE CONTROL DIAGRAMS
3.3.6 DRAWINGS/MODELS
3.3.7 OPEN SYSTEMS
3.3.8 CONFIGURATION MANAGEMENT
3.3.9 VEHICLE CONFIGURATION DATA
3.3.10 CONFIGURATION AUDITS
3.3.11 CONFIGURATION CONTROL
3.3.12 CONTRACTOR VERIFICATION REPORT
3.3.13 TECHNOLOGY
3.3.14 ENVIRONMENTAL, SAFETY, AND OCCUPATIONAL HEALTH
3.3.15 SOFTWARE
3.3.16 CALIBRATION UPDATES
3.3.17 DATA
3.3.18 DIMINISHING MANUFACTURING SOURCES AND MATERIAL SHORTAGES
3.3.19 TECHNICAL PERFORMANCE MEASURES
3.3.20 BALLISTIC PROTECTION/SEAT TEST AND ANALYSIS
3.3.21 FORCE PROTECTION AND VULNERABILITY REDUCTION
3.3.22 GOVERNMENT MOBILITY MODELING AND SIMULATION
3.3.23 SEAWORTHINESS ANALYSIS
3.3.24 CORROSION PREVENTION AND CONTROL PLAN
3.3.25 THERMAL ANALYSIS REQUIREMENTS
3.3.26 LAUNCHING FROM AND EMBARKING TO AMPHIBIOUS SHIPS ANALYSIS
3.3.27 WATERTIGHT INTEGRITY ANALYSIS
3.3.28 HUMAN SYSTEMS INTEGRATION
3.3.29 WEIGHT CONTROL AND REPORTING
3.3.30 LOAD PLAN
3.3.31 RELIABILITY AND MAINTAINABILITY PROGRAM MANAGEMENT
3.3.32 FAILURE REPORTING, ANALYSIS, AND CORRECTIVE ACTION SYSTEM
3.3.33 FAILURE PREVENTION REVIEW BOARD
3.3.34 TECHICAL DATA PACKAGE
3.4 MANUFACTURING OF THE EMD/LRIP/FRP VEHICLES
3.4.1 MANUFACTURING PLAN
3.4.2 MANUFACTURING READINESS ASSESSMENT FOR EMD/LRIP/FRP
3.4.3 CRITICAL PROCESS
3.4.4 PROCESS FAILURE MODES AND EFFECTS ANALYSIS
3.4.5 VEHICLE ASSEMBLY AND GOVERNMENT-FURNISHED PROPERTY INTEGRATION 56
3.4.6 BREAK-IN OPERATIONS
3.4.7 CONTRACTOR ACCEPTANCE TEST
3.4.8 RESET LRIP INITIAL OPERATIONAL TEST AND EVALUATION VEHICLES
3.4.9 FIRST ARTICLE TESTING
3.4.10 PASS THROUGH OF COMMERCIAL WARRANTIES
3.5 TEST AND EVALUATION
3.5.1 MANAGEMENT AND SUPPORT
3.5.2 GOVERNMENT TEST AND EVALUATION ON EMD VEHICLES
3.5.3 GOVERNMENT TEST AND EVALUATION ON LRIP VEHICLES
3.5.4 TRANSPORTATION
3.6 LOGISTICS
3.6.1 LOGISTICS PROGRAM MANAGEMENT MEETINGS
3.6.2 LOGISTICS MANAGEMENT INFORMATION
3.6.3 SUPPORTABILITY ANALYSIS
3.6.4 SUPPLY SUPPORT
3.6.5 PACKAGING, HANDLING, STORAGE, AND TRANSPORTATION
3.6.6 TRAINING PRODUCTS AND SERVICES
3.6.7 TECHNICAL MANUALS
3.6.8 DEPOT LEVEL OVERHAUL/REBUILD PRODUCTS
3.6.9 PRODUCTION LINE SHUTDOWN
3.6.10 FIELD SERVICE REPRESENTATIVES
3.7 GOVERNMENT-FURNISHED INFORMATION/PROPERTY
3.7.1 GOVERNMENT-FURNISHED INFORMATION
3.7.2 GOVERNMENT-FURNISHED PROPERTY
3.7.3 GOVERNMENT PROPERTY MANAGEMENT
3.7.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY
3.7.5 GOVERNMENT PROPERTY BASELINE INVENTORY REPORT
3.7.6 GOVERNMENT PROPERTY STATUS REPORT
3.7.7 REPAIR AND FAILURE REPORT
3.7.8 CONTRACTOR ACQUIRED PROPERTY
3.7.9 MAINTENANCE OF GOVERNMENT-FURNISHED PROPERTY
3.7.10 GOVERNMENT-FURNISHED PROPERTY WITH WARRANTY
3.7.11 FINAL DISPOSITION OF GOVERNMENT-FURNISHED PROPERTY
3.8 DISPOSITION OF VEHICLES
3.8.1 DISPOSITION OF EMD LIVE FIRE VEHICLES
3.8.2 DISPOSITION OF NON-LRIP OPTION SELECTED CONTRACTOR EMD VEHICLES ... 93
3.8.3 DISPOSITION OF FUSL VEHICLES
3.9 CROSSWALK MATRIX
Section J, Attachment (1)
Statement of Work
ACV SOW 03001 Unclassified Page 1
1 SCOPE
This Statement of Work (SOW) describes the work scope associated with the Amphibious Combat Vehicle (ACV) Phase 1, Increment 1, Program hereafter referred to as the ACV Program. It includes all efforts associated with the Engineering and Manufacturing Development (EMD) vehicle production and testing, Low Rate Initial Production (LRIP) (Option, if exercised) Build, and Full Rate Production (FRP) (Option, if exercised) Build. It includes the associated Program Management, Systems Engineering (SE), Test and Evaluation (T&E), and Integrated Product Support planning requirements.
1.1 BACKGROUND
The ACV Program will continue to build upon the preparatory work of the Marine Personnel Carrier (MPC) Program efforts conducted from 2006 to 2013. In 2006, the Office of the Secretary of Defense (OSD) provided strategic planning guidance to the United States Marine Corps (USMC) to maintain a two (2) Marine Expeditionary Brigade (MEB) forcible entry capability and propose a mix of vehicles suitable for Irregular Warfare (IW) to provide a mobility portfolio that better balanced our maneuver/mobility capability for Major Contingency Operations and IW. In response, the USMC proposed a combination of a light vehicle and a medium vehicle designed for the threats seen in IW. Both maintain a capability to maneuver with formations while conducting Major Contingency Operations. A medium personnel carrier was assessed as necessary to provide the full protection required in a high Improvised Explosive Devices (IED) environment, and the multi-axle wheeled configuration was assessed as the most suitable platform for high cross country speed, combined with the ability to transit urban infrastructure in a non-threatening and non-destructive manner. The Marine Requirements Oversight Council (MROC) convened on 4 February 2008 for a decision brief on the MPC material solution and operational fielding placement, based on the MPC Analysis of Alternatives (AoA) dated December 2007. The Ground Combat Tactical Vehicle Strategy was finalized in August 2008, setting the fundamental MPC capacities (Acquisition Objectives), strategic lift envelope, protection, payload, and performance required of the MPC as a system.
After the Expeditionary Fighting Vehicle (EFV) Program cancellation in January 2011, a Systems Engineering Operational Planning Team (SE-OPT) convened to conduct engineering and cost analysis of EFV requirements to identify those parameters driving complexity in design, identify trade-space, and develop requirement generation options for an EFV replacement, called the ACV. The SE-OPT analyzed 11 system concepts against capabilities delivered, cost, and schedule of delivery. The SE-OPT fully developed four (4) of the system concepts with various capabilities and costs that represented a range of capability from Assault Amphibious Vehicle (AAV)-based system concepts to new developmental ACV-based system concepts. All four (4) system concepts were low water speed capable. The SE-OPT determined and recommended that the most affordable solution was to develop a modern low water speed capable AAV replacement.
Concurrently with the efforts of the SE-OPT, the Government awarded four (4) MPC Demonstrations and & Studies (D&S) Contracts on 6 August 2012 to better understand the capabilities of Non-Developmental Items (NDIs) to meet water performance, survivability, and human factors/stowage capacity requirements. The promising results of testing these demonstrator vehicles led to a re-invigorated ACV Program in late 2013 using the type of NDI vehicles tested during the D&S Contracts as a baseline. In January 2014, the MPC initiative was reprioritized and repurposed to be the material approach for the Phase 1 Program of the ACV. The MPC Program was then re-designated as the ACV Phase 1 Increment 1 (i.e., ACV 1.1) and an acquisition strategy was selected with a NDI Armored Personnel Carrier (APC).
ACV SOW 03001 Unclassified Page 2
In April 2014, the MROC approved the ACV Capability Development Document (CDD) which will be followed by a Joint Requirements Oversight Council (JROC) approval once the AoA is finalized, setting the stage for development of programmatic and contractual documentation. The Materiel Development Decision (MDD) was received on 4 June 2014 to formally initiate the ACV Program. The current requirement for the USMC is 12 infantry battalion lift equivalents via APCs. The ACV capability along with the AAV Survivability Upgrade will provide the USMC ten (10) infantry battalion lift equivalents through 2035. After which time, the future phase(s) of the ACV Program will provide for the entirety of the USMC armored lift capacity requirement.
1.2 INTRODUCTION OF THE STATEMENT OF WORK
The purpose of this contract is to procure NDI ACV Personnel (P) Vehicles from EMD to FRP (Option, if exercised). This EMD contract will include scope associated with the following: Design/Development;
Program Management Support; Tooling Development; Manufacturing ACVs; Logistics Management Information (LMI) Data development; Training Materials development; Technical Manual (TM) development; Pre-Milestone (MS) C Test Support; Corrective Action Mods.
This SOW will also include Options (if exercised) to manufacture LRIP and FRP Vehicles, after the down-select decision is completed by the Government. Tasking for these contracts will include: Post MS C Test Support; Design/Development; Program Management Support; Training Materials development;
TM development; Support Equipment development; Manufacturing ACVs; LMI Data; Test Support; Test and Initial Spares; Refurbishment of Test Vehicles, Field Service Representative (FSR) and Training Support for fielding.
2 APPLICABLE DOCUMENTS
The following documents form a part of this SOW to the extent specified herein. Unless otherwise noted, in the event of a conflict between the SOW and the references cited herein (except for related specification sheets) the text of this SOW takes precedence. All second tier and below references cited shall be considered as guidance only. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.
2.1 GOVERNMENT DOCUMENTS
2.1.1 SPECIFICATIONS, STANDARDS, AND HANDBOOKS
SPECIFICATIONS
DEPARTMENT OF DEFENSE
Military Performance Specification (MIL-PRF)- 32216A
Evaluation of Commercial-Off-The- Shelf (COTS) Manuals and Preparation of Supplemental Data1
12 Aug
Military Handbook (MIL-
HDBK)-29612A
Instructional Systems Development/Systems Approach to Training and Education
31 Aug
ACV SOW 03001 Unclassified Page 3
DEPARTMENT OF NAVY
ACV-SPE-02003 Amphibious Combat Vehicle Phase I, Increment 1 System Performance Specification
Draft
MIL-PREF-29612B Training Data Products Aug 2001
STANDARDS
Military Standard (MIL-
STD)-129R
Military Marking for Shipment and Storage
18 Feb 2014
MIL-STD-130-N,
Change 1
Identification Marking of United States (U.S.) Military Property
16 Nov 2012
MIL-STD-464C Electromagnetic Environmental Effects Requirements for Systems
1 Dec 2010
MIL-STD-882E System Safety 11 May 2012
MIL-STD-2073-1E,
Change 1
Standard Practice for Military Packaging
7 Jan 2011
MIL-STD-3018, Change 1 Parts Management 27 Oct 2011
MIL-STD-31000A Technical Data Packages 26 Feb 2013
MIL-STD-881C Work Breakdown Structures for Defense Materiel Items
03 Oct 2011
Federal Standard (FED-
STD)-313E
Material Safety Data, Transportation Data, and Disposal Data for Hazardous Materials Furnished to Government Activities
1 Jul 2014
GUIDEBOOKS
Department of Defense (DoD) Guide
Corrosion Prevention and Control Planning Guidebook (CPCPG), Spiral No. 4
4 Feb 2014
DoD Guide DoD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide
21 Oct 2005
DoD Guide Interim Risk Management Guide for DoD Acquisition, Seventh Edition
Dec 2014
ACV SOW 03001 Unclassified Page 4
(Interim Release)
DoD Guidance Technology Readiness Assessment (TRA) Guidance
April 2011
DoD MRL Deskbook Manufacturing Readiness Level (MRL) Deskbook, Version 2.2.1
Oct 2012
DEPARTMENT OF ARMY
U.S. Army Corps of Engineers Waterways Experiment Station
North Atlantic Treaty Organization (NATO) Reference Mobility Model, Edition II, (NRMMII) Version 2.8.2b
Dec 1992
Department of the Army Pamphlet (DA PAM) 73-1
Test and Evaluation in Support of Systems Acquisition
30 May
Navy Marine Corps
(NAVMC) 1553.1
Systems Approach To Training User's Guide, Short Title: SAT User Guide
27 Oct 2010
MIL-DTL-53072E Chemical Agent Resistant Coating (CARC) System Application Procedures and Quality Control Inspection
9 May 2013
HANDBOOKS
MIL-HDBK-61A Configuration Management Guidance 7 Feb 2001
2.2 OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
2.2.1 REGULATIONS, FEDERAL ACQUISITION REGULATIONS, DEFENSE FEDERAL
ACQUISITION REGULATION SUPPLEMENTS, MANUALS, DIRECTIVES,
INSTRUCTIONS, AND FORMS
REGULATIONS
DEPARTMENT OF ARMY
AR 73-1 Army Regulation Test and Evaluation Policy
1 Aug 2006
FEDERAL ACQUISITION REGULATIONS
ACV SOW 03001 Unclassified Page 5
Federal Acquisition Regulations (FAR) 2.101(b)
Definitions 13 Nov
FAR 52.245-1 Government Property June 2007
DEFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENTS
Defense Federal Acquisition Regulation Supplements (DFARS) 252.211-7003
Item Unique Identification Dec 2013
DFARS 252.227-7013 Rights in Technical Data— Noncommercial Items
Feb 2014
DFARS 252.227-7014 Rights in Noncommercial Computer Software and Noncommercial Computer Software Documentation
Feb 2014
DFARS 252.227-7017 Identification and Assertion of Use, Release, or Disclosure Restrictions
Jan 2011
DFARS 252.234-7003 Notice of Cost and Software Data Reporting System
Nov 2010
MANUALS
DoD 4000.25-2-M Military Standard Transaction Reporting and Accounting Procedures
13 June
DoD 5000.04-M-1
Cost and Software Data Reporting Manual
4 Nov 2011
DoD 5220.22-M National Industrial Security Program Operating Manual
28 Mar
Naval Sea Systems Command (NAVSEA)
S9310-AQ-SAF-010
U.S. Navy Lithium Battery Safety Program TM: Responsibilities and Procedures
15 Jul 2010
DEFENSE LOGISTICS AGENCY
DIRECTIVES
Defense Logistics Management (DLM) 4000.25-2-M
Military Standard Requisitioning and Issue Procedures
13 Jun 2012
ACV SOW 03001 Unclassified Page 6
Directive (DoDD) 8570.01
Information Assurance Training, Certification, and Workforce Management
15 Aug
INSTRUCTIONS
Instruction (DoDI) 5000.02 (Final)
Operation of the Defense Acquisition System
7 Jan 2015
DoDI 5200.39, Change 1 Critical Program Information Protection within DoD
28 Dec
DoDI 8320.04 Item Unique Identification (IUID) Standards for Tangible Personal Property
June 2008
DoDI 8510.01 Risk Management Framework for DoD Information Technology
12 Mar
DoDI 8520.2 Public Key Infrastructure and Public Key Enabling
24 May
DoDI 8582.01 Security of Unclassified DoD Information on Non-DoD Information Systems
6 Jun 2012
COMNAVSURFLANT/
COMNAVSURFPAC
INSTRUCTION 3340.3D
Marine Corps Order
(MCO) 1553.2B
Wet Well Operations Manual
Management Of Marine Corps Formal Schools and Training Detachments
9 Oct 2012
1 Apr 2011
MCO 3070.2A
The Marine Corps Operational Security (OPSEC) Program
2 Jul 2013
MCO 4790.25
Ground Equipment Management Program
12 Jan 2014
Office of the Chief of Naval Operations Instruction (OPNAVINST) 3000.12A
Operational Availability of Equipment’s and Weapon Systems
2 Sep 2003
OPNAVINST 3432.1A Operations Security 4 Aug 2011
ACV SOW 03001 Unclassified Page 7
FORMS
DD Form 250 Material Inspection and Receiving Report
Aug 2000
DD Form 254 Contract Security Classification Specification, Department of Defense
Dec 1999
DD Form 1423 Contract Data Requirements List
(CDRL)
Aug 1996
DD Form 1586 Contract Funds Status Report Aug 1996
DD Form 2734/1 Contract Performance Report, Format 1, Work Breakdown Structure
Apr 2005
DD Form 2734/2 Contract Performance Report, Format 2, Organizational Categories
Apr 2005
DD Form 2734/3 Contract Performance Report, Format 3, Baseline
Apr 2005
DD Form 2734/4 Contract Performance Report, Format 4, Staffing
Apr 2005
DD Form 2734/5 Contract Performance Report, Format 5, Explanations and Problem Analyses
Apr 2005
DD Form 2794 Cost and Software Data Reporting Plan
May 2011
GSA Optional Form
Optional Form (OF) 346 U.S. Government Motor Vehicle
Operators Identification Card
Nov 1985
2.3 NON-GOVERNMENT DOCUMENTS
2.3.1 STANDARDS AND GUIDEBOOKS
STANDARDS
SAE Government Electronics and Information Technology Association Standard (GEIA- STD)-0007, Rev B
Logistics Product Data 01 May 2013
American Society of Mechanical Engineers (ASME) Y14.24
Types and Application of Engineering Drawings
1 Jan 2012
ASME Y14.34 Associated Lists 1 Jan 2013
ACV SOW 03001 Unclassified Page 8
ASME Y14.35M Revision of Engineering Drawings and Associated Documents
8 Dec 1997
ASME Y14.41 Digital Product Definition Data Practices
14 May 2012
ASME Y14.5-2009 Geometric Dimensioning and Tolerancing
9 Feb 2009
ASME Y14.100 Engineering Drawing Practices 30 Jul 2013
American Society Testing Materials (ASTM)-D-3951
Standard Practice For Commercial Packaging
Institute of Electrical and Electronic Engineers (IEEE) 12207.2
Software Life Cycle Processes 1997
International Organization for Standardization (ISO) 9001:2008
Quality Management Systems- Requirements
National Aerospace Standard
(NAS) 411-1:2013
National Aerospace Standard:
Hazardous Materials Target List
30 Sep 2013
NAS 411, Rev 3 National Aerospace Standard:
Hazardous Materials Management Program
30 Sep 2013
National Institute of Standards and Technology Interagency Report (NISTIR) 7622
National Institute of Standards and Technology Interagency Report 7622, “Notional Supply Chain Risk Management Practices for Federal Information Systems: Piloting Supply Chain Risk Management for Federal Information Systems”
Oct 2012
National Institute of Standards and Technology (NIST) Special Publication 800-53A
Guide for Assessing the Security Controls in Federal Information Systems and Organizations
June 2010
SAE JA1011 Evaluation Criteria for Reliability- Centered Maintenance Processes
Aug 2009
GUIDEBOOKS
International Society of Weight Engineers, Inc.
Recommended Practice Number 5
Mass Properties Control System for Wheeled and Tracked Vehicles, Revision A
26 May
National Defense Industrial Association Guidebook
Engineering for System Assurance, Version 1.0
ACV SOW 03001 Unclassified Page 9
REPORTS
NISTIR 7622
Piloting Supply Chain Risk Management (SCRM) for Federal Information Systems, 16 Oct 2012
MANUALS
Automotive Industry Action Group (AIAG) Failure Mode and Effects Analyses (FMEA) Manual
4th Edition of Industry Standards 2008
2.4 AVAILABILITY OF DEPARTMENT OF DEFENSE DOCUMENTS
DoD Directives, Manuals, Instructions, and Publications are available online at http://www.dtic.mil/whs/directives/ or from the National Technical Information Services (NTIS), 5301 Shawnee Rd, Alexandria, VA 22312.
DoD FAR and DFARS are available online at http://farsite.hill.af.mil/.
DoD Forms are available online at http://www.dtic.mil/whs/directives/infomgt/forms/.
Department of Navy (DON) Issuances (e.g., Office of the Chief of Naval Operations (OPNAV) Instructions) are available online at http://doni.daps.dla.mil/allinstructions.aspx.
General Services Administration (GSA) OF are available by ordering from http://www.gsa.gov/portal/forms/download/116942
Military Specifications, Military Standards, Military Handbooks, and Data Item Descriptions (DIDs) are available online at http://quicksearch.dla.mil/ or from the Standardization Document Order Desk, 700 Robbins Avenue, Building 4D, Philadelphia, PA 19111-5094.
If a DoD document cannot be acquired, they may be provided by the Government upon the Contractor’s request.
3 REQUIREMENTS
This SOW encompasses the EMD and the Production and Deployment (PD) Phases of the ACV Acquisition Program. The ACV performance requirements are fully described in Section J, Attachment 02, ACV System Performance Specification ACV-SPE-02003. Vehicle quantities are detailed in Section B - Supplies or Services and Prices of the Request for Proposal (RFP).
Contract Line Item Number (CLIN) 0001 – For EMD Design and Development, the Contractor shall provide the following efforts:
Vehicle Design/Development
Procurement of Vehicle Tooling
Program Management
Armor and Seat Coupons
Development of Software
ACV SOW 03001 Unclassified Page 10
Management of Government Furnished Property (GFP)
CLIN 0002 – The Contractor shall manufacture and deliver 13 ACV-P EMD Vehicles.
CLIN 0003 –Delivery incentive for EMD vehicles, see Section H; H.5 Delivery Incentive.
CLIN 0004 – The Contractor shall prepare and deliver EMD, LRIP and FRP Contract Data Requirements List (CDRLs) in accordance with Exhibit A, DD-1423s.
CLIN 0005 (Option) – The Contractor shall manufacture and deliver 3 ACV-P EMD Vehicles.
CLIN 1001 (Option) – The Contractor shall continue to Design and Develop EMD vehicles, and provide the following efforts:
Program Management
Producibility
Engineering Planning
Management of GFP
CLIN 1002 (Option) – The Contractor shall provide EMD Test Support that shall include the following efforts:
Pre-MS C Test Support
Test Spares
Vehicle Transportation
Conduct of training for testing
FSRs
CLIN 1003 (Option) – The Contractor shall provide corrective action modifications to the EMD vehicles in support of system Reliability Growth Testing (RGT). These corrective action modifications are in response to safety and reliability failures discovered during system developmental testing. The corrective action modifications will be implemented during the planned Corrective Action Periods.
CLIN 1004 (Option) – The Contractor shall provide the following efforts for Logistics Management:
Develop and deliver LMI data
Develop and deliver Technical Manuals
Develop and deliver Training Material
Preservation, Packaging, and Storage Plan for Unique Production Tooling
CLIN 1005 (Option) – The Contractor shall provide Studies for Advanced Capability Improvements in accordance with Attachment 26. This will include design and installation of key objective-level performance improvements to EMD vehicles. A contract modification will be awarded prior to any efforts being executed by the Contractor.
CLIN 1006 (Option) – The non-selectee Contractor shall follow the instructions identified in SOW paragraph 3.8.2 for disposition of the Contractor EMD vehicles.
ACV SOW 03001 Unclassified Page 11
CLIN 1007 (Option) – The Contractor shall provide Post down-select efforts for EMD Design and Development to include the following:
Program Management Management of GFP
CLIN 1008 (Option) – The Contractor shall provide post down-select efforts for EMD Test Support to include the following efforts:
Conduct and Support Post-MS C Test
Support IOT&E Testing
Vehicle Transportation
Test Spares
FSRs
For the PD phase the following CLINs shall apply:
CLIN 2001 (Option) will include two (2) sub-CLINs for the LRIP (Lot 1) Vehicles. They are:
CLIN 2001AA (Option) – The Contractor shall manufacture and deliver four (4) ACV-P Full-Up System-Level (FUSL) vehicles.
CLIN 2001AB (Option) – The Contractor shall manufacture and deliver 26 ACV-P Production vehicles.
CLIN 2002 (Option) will include two (2) sub-CLINs for other production related Costs for LRIP (Lot 1).
They are:
CLIN 2002AA (Option) – The Contractor shall provide the following development funded efforts:
Test Support Test Spares Vehicle Transportation Logistics Demonstration First Article Testing Corrective Action Modifications Conduct of Training for Testing
CLIN 2002AB (Option) – The Contractor shall provide the following procurement funded efforts:
Program Management Procurement of Vehicle Tooling Acceptance Testing FSRs
CLIN 2003 (Option) will include two (2) sub-CLINs for Fielding and Support Costs for LRIP (Lot 1).
They are:
CLIN 2003AA (Option) – The Contractor shall provide the following development funded efforts:
Develop logistics products (LMI data, training materials, TMs)
ACV SOW 03001 Unclassified Page 12
CLIN 2003AB (Option) – The Contractor shall provide the following procurement funded efforts:
Procure data products (LMI data, training materials, TMs) Procure support equipment Procure initial spares Fielding support Unique Production Tooling Preservation, Packaging, and Storage
CLIN 2004 (Option) – The Contractor shall reset LRIP operational test and evaluation vehicles identified in SOW paragraph 3.4.8.
CLIN 3001 (Option) – The Contractor shall manufacture and deliver 30 ACV-P vehicles for LRIP (Lot 2).
CLIN 3002 (Option) – The Contractor shall provide the following production related efforts for LRIP (Lot 2):
Program Management Procurement of Vehicle Tooling
Vehicle Transportation
CLIN 3003 (Option) – The Contractor shall provide the following fielding and support efforts for LRIP (Lot 2):
Procure data products (LMI data, training materials, TMs) Procure support equipment Procure initial spares Fielding support
CLIN 4001 (Option) – The Contractor shall manufacture and deliver 30 ACV-P vehicles for FRP (Lot 1).
CLIN 4002 (Option) – The Contractor shall provide the following production related efforts for FRP (Lot 1):
Program Management Procurement of Vehicle Tooling
CLIN 4003 (Option) – The Contractor shall provide the following fielding and support efforts for FRP (Lot 1):
Procure data products (LMI data, training materials, TMs) Procure support equipment Procure initial spares Fielding support
ACV SOW 03001 Unclassified Page 13
CLIN 4004 (Option) – The Contractor shall develop and deliver depot data and support products necessary for depot stand-up.
CLIN 5001 (Option) – The Contractor shall manufacture and deliver 80 ACV-P vehicles for FRP (Lot 2).
CLIN 5002 (Option) – The Contractor shall provide the following production related efforts for FRP (Lot 2):
Program Management Procurement of Vehicle Tooling
CLIN 5003 (Option) – The Contractor shall provide the following fielding and support efforts for FRP (Lot 2):
Procure data products (LMI data, training materials, TMs) Procure support equipment Procure initial spares Fielding support
CLIN 6001 (Option) – The Contractor shall manufacture and deliver 38 ACV-P vehicles for FRP (Lot 3).
CLIN 6002 (Option) – The Contractor shall provide the following production related efforts for FRP (Lot 3):
Program Management Procurement of Vehicle Tooling
CLIN 6003 (Option) – The Contractor shall provide the following fielding and support efforts for FRP (Lot 3):
Procure data products (LMI data, training materials, TMs) Procure support equipment Procure initial spares Fielding support
CLIN 6004 (Option) – The Contractor shall provide production line shut-down efforts:
Production Line Shut-Down
CLIN 6005 (Option) – Technical Data Package
ACV SOW 03001 Unclassified Page 14
3.1 GENERAL REQUIREMENTS OVERVIEW
3.1.1 RESOURCE REQUIREMENTS
The Contractor shall provide all necessary personnel, resources and facilities to execute the requirements, and provide deliverables within the identified schedules. The Contractor shall ensure that video teleconference and telephone bridges are available at the Contractor’s facility for the entire contract period of performance. All personnel attending demonstration events at the test sites shall speak fluent English, and submit visit requests to applicable test agencies.
3.1.2 SECURITY
The Contractor shall safeguard controlled unclassified information and administrative data and classified program information and material at all levels of classification through all stages of the contract associated with the ACV from unauthorized access or disclosure in accordance with DoDI 8582.01, "Security of Unclassified DoD Information on Non-DoD Information Systems."
The Contractor shall comply with the security requirements imparted by the Contract Security Classification (DD Form 254), per Section J, Attachment 23, and the National Industrial Security Program Operating Manual (NISPOM), DoD 5220.22-M (current version). Additional information can be found in the National Industrial Security Program Library on the Defense Security Service web site:
http://www.dss.mil/isp/fac_clear/download_nispom.html.
3.1.3 OPERATIONS SECURITY PLAN
The Contractor shall develop an OPSEC plan. The OPSEC plan shall:
1) Describe the OPSEC environment to include identification of critical information, the OPSEC threat, and vulnerabilities an adversary might exploit to acquire critical information,
2) Document the OPSEC risk analysis,
3) Identify proposed and actual OPSEC measures,
4) Define and assign specific OPSEC responsibilities and tie the OPSEC Plan to the contractor's corporate OPSEC Program, and
5) Serve as a repository of the OPSEC history of the contract. Additional guidance can be found in the OPNAVINST 3432.1A, "Operations Security" and MCO 3070.2A "The Marine Corps OPSEC Program".
The Contractor shall prepare and deliver the Contractor's OPSEC Plan in accordance with CDRL A001.
3.1.4 PROGRAM PROTECTION IMPLEMENTATION PLAN
The Contractor shall provide a Program Protection Implementation Plan (PPIP) that includes a criticality analysis, vulnerability assessment, risk assessment, and countermeasure selection and implementation, with assumptions, rationale, and results. For each Level I and Level II component with the following Protection Failure Criticality Levels, Table (1), the Contractor shall identify the associated logic-bearing hardware, software, and firmware that implements critical functions or introduces vulnerability to the associated components (designated as critical components).
ACV SOW 03001 Unclassified Page 15
Level Description
Level I: Total Mission Failure Function/component failure is a failure that results in total compromise of mission capability
Level II:
Significant/Unacceptable Degradation
Function/component failure is a failure that results in unacceptable compromise of mission capability or significant mission degradation
Level III: Partial/Acceptable Function/component failure is a failure that results in partial compromise of mission capability or partial mission degradation
Level IV: Negligible Function/component failure is a failure that results in little or no compromise of mission capability
Table (1) Protection Failure Criticality Levels
The Contractor shall demonstrate visibility into its supply chain for critical components, understanding of the risks to that supply chain, and shall implement or provide plans for implementation of risk mitigation efforts to counter those risks.
The Contractor shall plan for and implement countermeasures which mitigate foreign intelligence, technology exploitation, supply chain and battlefield threats, and system vulnerabilities that result in the catastrophic (Level I) and critical (Level II) protection failures, including:
1) Application of supply chain risk management key practices, applied as appropriate to the development of the system. Supply chain risk management key practices are found in the National Institute of Standards and Technology Interagency Report 7622, Piloting SCRM for Federal Information Systems, and the National Defense Industrial Association Guidebook, Engineering for System Assurance, both publicly available.
2) Identification and recording of the relevant cost, schedule, and performance information used to choose between alternates as a part of the selection of critical components. The Contractor shall define associated program protection risks with the selected critical component(s) and work with the Government to develop mutually-agreeable risk management plans.
3) Implementation of processes to control access by foreign nationals to program information, including system design information, DoD-unique technology, and software or hardware used to integrate commercial technology.
4) Establishment and maintenance of a Counterfeit Electronic Part Detection and Avoidance System. The processes and practices employed to ensure that genuine hardware, software and logic elements will be employed in the solution. The Contractor shall ensure flow down requirements necessary for the Contractor’s Counterfeit Electronic Part Detection and Avoidance System are levied upon subcontractors.
5) Implementation of processes for safeguarding unclassified controlled technical information in the development environment.
The Contractor shall develop a set of secure design and coding practices to be followed for implementation of Level I and II critical components. Top 10 Secure Coding Practices (https://www.securecoding.cert.org/confluence/display/seccode/Top+10+Secure+Coding+Practices) and the Common Weakness Enumeration (CWE)/SysAdmin, Audit, Network, Security (SANS) top 25 most dangerous software errors (http://cwe.mitre.org/top25/index.html) may be used as guidance.
The Contractor’s PPIP shall address the following areas:
Section 2: Identifying what to protect
ACV SOW 03001 Unclassified Page 16
Section 4: Vulnerabilities Section 5: Countermeasures Section 7: Program Protection Risks Section 8: Managing and Implementing Program Protection Plan (PPP) Section 9: Process for Management and Implementation of PPP Section 10: Process for Monitoring and Reporting Compromises Appendix C: Criticality Analysis
The Contractor shall prepare and deliver the Contractor’s PPIP in accordance with CDRL A002. The Government will provide a Contracting Office letter to the Contractor validating that the Critical Program Information/Critical Technology (CPI/CT) is properly identified for the program.
3.1.4.1 PROGRAM PROTECTION REVIEW MEETINGS
The Contractor shall host three (3) Program Protection Review Meetings in accordance with the Section J, Attachment 03, Meeting List. Each of the three (3) meetings shall include:
The Contractor’s CPI Assessment identifying CPI or CT (defined by DoDI 5200.39, July 16, 2008 Incl Change 1 Dec 28, 2010, CPI Protection within the DoD)
A classified session for the Contractor’s Anti-Tamper Plan and status of the Anti-Tamper Solution’s implementation
For planning purposes, each meeting will be a one (1) day event.
3.1.4.2 CYBERSECURITY
The Contractor shall designate an Information Systems Security Manager (ISSM) who shall meet the training and certification requirements as defined in DoDD 8570.01, “Information Assurance Training, Certification, and Workforce Management,” dated 15 Aug 2004.
The Contractor shall ensure that Contractor Information Assurance Workforce (IAW) personnel comply with Contractor IAW certification standards and security background investigation requirements, as defined in the DoDD 8570.01.
The Contractor shall ensure that Contractor IAW personnel comply with the identification, tracking and assignment reporting requirements, as defined in the DoDD 8570.01. Contractor IAW personnel shall meet the same standards for IAW certification, system access, management, training and reporting requirements as Government IAW personnel, as defined in DoDD 8570.01.
The Contractor shall comply with and provide Cybersecurity/Information Assurance (IA) supporting activities and functions for the requirements, processes, reporting activities, reviews, certification and accreditation, security design, and assessment activities as defined in the DoDI 8510.01, “Risk Management Framework (RMF) for DoD Information Technology (IT),” dated 12 Mar 2014.
The Contractor shall ensure that ACV IA designated contract deliverables and activities are in compliance with DoDI 8510.01.
ACV SOW 03001 Unclassified Page 17
The Contractor shall ensure that deliverables comply with applicable U.S. Government and DoD Cybersecurity/IA, Directives, Regulations, and Standards that are applicable to the ACV Program’s Security Classification Level (SCL).
The Contractor shall provide a Cybersecurity/IA status at each of the identified Program Management Reviews (PMRs) per Section J, Attachment 03, Meeting List. The Government may require the Contractor to provide quarterly Cybersecurity/IA program status reports at the PMR to ensure Cybersecurity/IA is fully integrated and compliant with:
1) Federal Information Security Management Act of 2002, Title III-Information Security
2) NIST Special Publication 800-53A Guide for Assessing the Security Controls in Federal Information Systems and Organizations
3) DoDI 8510.01- Risk Management Framework for DOD IT, dated 12 Mar 2014
4) Interim DoDI 5000.02 – Operation of the Defense Acquisition System, dated 25
November 2013
5) The ACV Program’s designated SCL implementation requirements as defined by
DoDI 8510.01
6) The Government’s Integrated Master Schedule (IMS)
The Contractor ISSM shall ensure the ACV design is reviewed for Cybersecurity/IA and Anti-Tamper Compliance at the Preliminary Design Review (PDR)/Critical Design Review (CDR), Vehicle Acceptance Review (VAR), and the Production Readiness Review/System Verification Review
(PRR/SVR).
The Contractor shall provide support to the Government to successfully achieve an Authority to Operate (ATO) as defined in DoDI 8510.01.
The Contractor shall deliver the Cybersecurity/IA Assessment in accordance with CDRL A003.
3.1.4.3 ANTI-TAMPER PLAN
The Contractor’s Anti-Tamper Plan shall provide countermeasures to protect CPI and Critical Technologies in accordance with DoDI-5200.39, “Critical Program Information with DoD, Change 1,” dated 28 Dec 2010 to address the following:
1) Deter countermeasure development that would decrease U.S. warfighting capabilities
2) Prevent the unauthorized or out of baseline augmentation or change of capabilities in
Direct Commercial Sales (DCS), Foreign Military Sales (FMS), and International Cooperative Development Programs
3) Prevent unauthorized technology changes on CPI or any released capability
4) Protect U.S. critical design knowledge and manufacturing processes from unauthorized transfer
5) Protect U.S. investment in weapon system capabilities, and avoid additional unplanned investment to regain the U.S. advantage
The Contractor’s Anti-Tamper countermeasures shall be verified by Contractor testing to include any prototypes. The Contractor shall deliver the detailed Anti-Tamper solution as an Anti-Tamper Plan submission in accordance with CDRL A004 and the ACV Security Classification Guide, Section J, Attachment 25, and shall incorporate the solutions into the ACV design.
ACV SOW 03001 Unclassified Page 18
3.2 PROGRAM MANAGEMENT
The Contractor shall provide a qualified Program Manager (PM) that shall be responsible for the accomplishment of all tasks in this SOW. The Contractor’s PM shall plan, organize, manage, schedule, implement, control, analyze, and report on all elements of the SOW. The Contractor’s PM shall have resources and authority to efficiently and effectively execute tasks necessary to complete the requirements. The Contractor’s PM shall be prepared to present and discuss the status of contract activities, requirements, and issues with the Program Manager Advanced Amphibious Assault (PM AAA) ACV Product Manager (PdM), the Contracting Officer, and the Contracting Officer Representative
(COR).
The Contractor shall execute the program with established, defined, and repeatable organizational processes, procedures, and policies unless otherwise directed within this SOW or other Government regulations, policies, and/or direction.
The Contractor shall deliver all Unclassified/Classified CDRLs in accordance with each DD Form 1423 and the CDRL Submission Instructions, per Section J, Attachment 04.
3.2.1 ASSIGNMENT OF RESPONSIBILITY AND AUTHORITY
The Contractor shall identify clear lines of authority, within their organization, of the personnel who shall be responsible for conducting all activities delineated in this SOW. Those individuals shall be responsible for determining and controlling the resources necessary to satisfy each element of this SOW.
3.2.2 CONFERENCES, REVIEWS, AGENDAS, AND REPORTS
The Contractor shall plan, host, attend, coordinate, provide administrative support and conduct meetings, formal reviews and events, conferences, and audits (hereinafter called "reviews") in conjunction with the Government. The reviews shall be conducted at the Contractor’s or Government’s facilities, as indicated in Section J, Attachment 03, Meeting List. The reviews shall be included in the IMS, and multiple reviews may be held concurrently with the Government’s approval. In addition, the Contractor shall be available to participate in Government – Contractor internet conferencing (Web Meetings) using Government approved systems such as Defense Connect Online (DCO) conferencing tool.
Prior to each review, the Contractor shall prepare agendas for Government approval, unless waived by the Government, in accordance with CDRL A006. The Contractor shall deliver Conference Reports following each review, in accordance with CDRL A008. Action item documentation, assignment of responsibility for completion and due dates will be determined by the Government Chairperson prior to adjournment of all reviews. A summary of all action items, responsible parties, and completion dates shall be included with the meeting minutes.
3.2.2.1 POST-AWARD AND CONTRACT OPTION POST-AWARD CONFERENCES
3.2.2.1.1 POST-AWARD CONFERENCE
The Post-Award Conference (PAC) is the first meeting of key Contractor and Government personnel.
This PAC is to achieve a clear and mutual understanding of all contract requirements between the
ACV SOW 03001 Unclassified Page 19
Government and the Contractor, and identify and resolve potential problems to ensure successful contract performance. The PAC shall be conducted within 20 calendar days after contract award, per Section J, Attachment 03, Meeting List. The PAC shall include Contractor representatives, the cognizant Contract Administration Office and the Contracting Officer. The Contracting Officer, or designated representative, initiating the conference, will designate or act as the chairperson. The Contractor shall participate with the Government to draft an agenda for the PAC, prior to the meeting.
3.2.2.1.2 CONTRACT OPTION POST-AWARD CONFERENCE
A contract Option PAC shall be held within 20 calendar days after exercise of the LRIP and FRP CLINs (Options, if exercised) per Section J, Attachment 03, Meeting List. The attendees shall include the Contractor, contracting representative, Government Contracting Officer, management, and technical personnel from both the Government and the Contractor. The Contractor shall participate with the Government to arrange a schedule and agenda for the PAC prior to the meeting.
3.2.2.2 RESERVED
3.2.2.3 PROGRAM MANAGEMENT REVIEWS
The Contractor shall participate in PMRs during EMD, LRIP (Option, if exercised) and FRP (Option, if exercised) to assess program cost, schedule, performance, process implementation, risk, and status related to the execution of the ACV Program per Section J, Attachment 03, Meeting List. The PMRs may be held in conjunction with other reviews and conferences for efficiency. The Contractor shall summarize the following items and any others that the Government identifies within 30 days of each of the PMRs:
1) Work completed (inclusive of meeting action items)
2) Work planned for upcoming quarter
3) Contract tasks not completed
4) Significant accomplishments
5) Problems or delays
6) Corrective actions
7) Schedule updates and Critical Path Analysis
8) Other program or personnel changes
9) Risk Management Status (Cybersecurity and Safety included)
10) Configuration Management
11) IMS review with critical path and supporting metrics
12) Schedule Risk Assessment (SRA) review with supporting metrics
13) Contractor Cost Data Reporting (CCDR) with most recent cost estimates
14) Status Report for each Integrated Product Team (IPT) or Team
15) Project Metric Status (including Average Unit Manufacturing Cost (AUMC))
16) Technical Performance Measures (TPMs)
3.2.3 MONTHLY PROGRESS STATUS REPORTS
The Contractor shall deliver a Monthly Progress Status Report for the EMD CLINs, and the LRIP (Option, if exercised) and FRP (Option, if exercised) CLINs in accordance with CDRL A009.
3.2.4 INTEGRATED MASTER PLANNING/INTEGRATED MASTER
SCHEDULING/SCHEDULE RISK ASSESSMENT
ACV SOW 03001 Unclassified Page 20
3.2.4.1 CONTRACT INTEGRATED MASTER PLAN
The Contractor shall develop and deliver a Contract Integrated Master Plan (IMP) in accordance with the Integrated Program Management Report (IPMR), CDRL A010. The Contract IMP shall be traceable to the Government Program IMP, provided in Section J, Attachment 05, Program IMP, and shall include all accomplishments and criteria necessary to achieve each identified Program IMP event. The Contractor shall maintain the IMP throughout the period of performance and if changes occur, obtain written Government approval. The Contract IMP shall be statused by the Contractor to the third level of the Government Work Breakdown Structure (WBS). The IMP shall comply with the “DoD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide.” If the Contract IMP requires additional IMP accomplishment criteria to be added to the Program IMP, the Contractor can request a change to the Program IMP. The Government will use an established internal process to evaluate the proposed change prior to approval. The Contractor shall liaison with the COR to facilitate the integration of all Contract IMP events, accomplishments, and criteria into the ACV Program IMP.
3.2.4.2 CONTRACT INTEGRATED MASTER SCHEDULE
The Contractor shall decompose the Contract IMP into a time-based IMS showing the detailed tasks required to accomplish the work effort contained in the Contract IMP. The Contractor shall develop and deliver the Contract IMS in accordance with IPMR, CDRL A010. The Contractor shall liaison with the COR to facilitate the integration of key Contract IMS milestones and tasks into the Program IMS. The Contractor shall develop task definitions that include task durations and dependencies with other Contract IMS Tasks. The Contractor shall maintain the Contract IMS and the Government will ensure key Contract IMS milestones and tasks are fully integrated into the Program IMS. The Contractor shall deliver an IMS Narrative Report and Analysis to reflect changes in the Contract IMS, in accordance with IPMR, CDRL A010. In addition, the Contractor shall perform system critical path and near-critical path analyses to the closest major acquisition MS (e.g., MS C) and to each key system-level technical review (e.g., PDR/CDR, VAR). The Contractor shall deliver the results of the analyses and Corrective Action Plans in the IMS Narrative Report and Analysis to resolve those efforts negatively impacting the critical path, in accordance with the IMPR, CDRL A010.
The Contract IMS shall meet the below listed requirements:
1) Define all tasks required to execute the Government-approved Contract IMP. Define all internal and external schedule dependencies necessary to execute the Contract
IMS.
2) Incorporate material order, material delivery, fabrication, assembly, and test for vehicle production and delivery into the IMS (e.g., EMD CLINs, LRIP (Option, if exercised) CLINs, and FRP (Option, if exercised) CLINs).
3) Include Contractor tasks required to accomplish each IMP event and relevant subcontractor scheduled milestones necessary for the achievement of each Contract IMS event.
4) Include all CDRL deliveries and events as defined by the IMP.
5) Be vertically traceable to the Contract IMP, the Contract Work Breakdown Structure
(CWBS), and the Contract SOW and horizontally traceable to all dependent project tasks, identifying the relationships and constraints between project tasks.
ACV SOW 03001 Unclassified Page 21
3.2.4.3 SCHEDULE RISK ASSESSMENT
A probabilistic SRA shall be developed and delivered in accordance with IPMR CDRL A010. The SRA will provide the Government with an understanding of the potential schedule impacts associated with existing or emerging program risks. These analyses shall compute the probability of completing key milestones, events, and tasks/activities by specific dates. The Contractor shall report optimistic, pessimistic, and most likely remaining durations and rationale for the values in accordance with the Contract IMS for each task/activity on the following paths: critical path to contract completion, critical path to the next Major MS (e.g. MS C), and the next three (3) near-critical paths to the next Major MS.
Global weighting values and rationale shall also be provided by the Contractor. In addition, the Contractor technical team members shall be asked to provide pessimistic, most likely, and optimistic durations for moderate to high risk activities identified in the Program Risk Database (generally identified through a risk cube) that are associated with IMS tasks.
3.2.5 CONTRACTOR WORK BREAKDOWN STRUCTURE
The Contractor shall refine the WBS Index and Dictionary developed by the Government at an appropriate level to make the resulting structure program specific, and to facilitate effective Program Management; in accordance with MIL-STD-881C, Work Breakdown Structures for Defense Materiel Items. The Contractor shall establish the CWBS definition at a level necessary to identify work progress and enable effective management, regardless of the CWBS level reported per Section J, Attachment 06, Cost and Software Data Reporting (CSDR) Plan, for program oversight. The Contractor shall be responsible for periodic updates and maintenance of the CWBS at the level below the required reporting level established per Section J, Attachment 06, CSDR Plan, according to the provisions set forth in the CWBS.