HSFE80-17-R-0005 Section F
VERSION ACB AUGUST
18NOVEMBER 14, 2017
F-1
SECTION F - DELIVERIES OR PERFORMANCE
F.6
Deliverables and Required Reports Table Area
Required Report
/ Deliverable Delivery Date Delivery
Recipient Description Template
Provided by FEMA
Reference
F-2
13 MHU Installation - Report
Manufactured Home or HUD Specification Home (MH)/Park Model (PM) is Ready for Utilities (i.e., electric, water, sewer, etc.) within three (3) calendar days of work order issuance.
MH/PM is available for Ready for Occupancy (RFO) inspection within one
(1) calendar day after the unit is energized.
Travel Trailer is available for RFO inspection within two (2) calendar days of work order issuance.
The contractor shall identify and apply for all permits that are required for MHU installation within 1 business day, unless a deviation is approved by the COR.The Contractor must have all appropriate permits and licenses within three (3) calendar days of work order issuance.
If an MHU Reinstall is necessary, the Contractor shall remove and replace an MHU at the same site within two (2) calendar days of work order issuance.
COR
MHU installation shall be requested by FEMA specifically based on the needs of the disaster. FEMA will validate the deliverable either through the exchange of the Installation Summary Report, Individual Installation Report, Ready for Occupancy Checklist, and / or visual validation of the installation of the MHU.
N/A N/A
F-3
MHU
Deactivation Report
Manufactured Home or HUD Specification Home (MH)/Park Model (PM) shall be removed from the installation site within three (3) calendar days of work order issuance.
Travel Trailer shall be removed from the installation site within two (2) calendar days of work order issuance.
Work must be completed within 3 days (2 days for TTs) of receipt of all required permits if applicable, or within 3 days of work order issuance (2 days for TTs) if no permits are required.The Contractor must have all appropriate permits and licenses within three (3) calendar days of work order issuance.
In the case of an emergency MHU deactivation, the unit shall be removed from the site, made ready for transport, and transported back to a designated staging area within one (1) calendar day of the emergency deactivation work order issuance.
Variable
The deactivation of an MHU shall be requested by FEMA specifically based on the needs of the disaster. FEMA will validate the deliverable either through the exchange of FEMA Form 90-13, the MHU Deactivation Checklist, Deactivation
Summary Report, Individual Deactivation Report, and / or visual validation of the deactivation of the MHU.
N/A N/A
Difficult Single Unit Installation Site Safety and
Health Plan
Due prior to commencing work on a difficult unit installation.10 days after award to commencing work on a difficult unit installation.
COR
A Site Safety and Health Plan that is specific to a difficult individual construction project and is in compliance with applicable sections of the USACE Manual. Manual linked identified in Section C.
N/A No
END OF SECTION F