GAINES GE-T101-GE-T101.pdf
PDF 198 KB Posted
- Attached to
- 2025 E-Rate Network Cabling Additions
- Solicitation number
- RFP-SCC-250000001194-3
- Issued by
- Genesee County, Michigan
About this file
This is a structured cabling design drawing for Gaines Elementary School in the Swartz Creek Community Schools district, created by Convergent Technology Partners. The floor plan details the installation of Category 6A UTP cabling throughout the school building, including wall and ceiling UTP locations, telecom cabinets, and telecom bus-bars. The design specifies standard installation requirements including surface-mounted single-gang back boxes with white two-port faceplates, wall locations centered below whiteboards at standard height, and concealed raceway for below-ceiling cable runs.
The technical specifications require all UTP cable to meet ANSI/TIA Category 6A standards, with white 8P/8C (RJ45) jacks for termination. Service loops must be long enough to reach the farthest location in associated rooms and securely fastened to the structure. The drawing indicates several telecom cabinet locations that require grounding, with bus block locations to be determined using best practices during installation. The design was authored by DLF and EGH, with design dates of 12/17/2024 and 1/23/2025.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 1
1 1
1 1
1 1
1 1
1 1
1 11 11 11 1
1 1
1 1
TG
B
TGB
SYMBOL LEGEND
UTP LOCATION, QTY AS
NOTED
CEILING UTP LOCATION,
QTY AS NOTED
TELECOM CABINET
TELECOM BUS-BAR
REPLACE CABINETR
GENERAL NOTES
1. ALL UTP CABLE SHALL BE ANSI/TIA
CATEGORY 6A. PLACE WALL
LOCATIONS IN A SURFACE MOUNTED
SINGLE-GANG BACK BOX WITH A
WHITE TWO PORT FACEPLATE.
2. THE UNUSED TOP PORT OF THE
FACEPLATE IS TO BE FILLED WITH A
BLANK KEYSTONE JACK INSERT.
3. PLACE WALL LOCATIONS CENTERED
BELOW WHITEBOARD AT STANDARD
HEIGHT.
4. LOCATIONS WITHOUT WHITEBOARDS,
CENTER THE INSTALLATION ON THE
WALL AT STANDARD HEIGHT.
5. ALL CABLE BELOW CEILING SHALL BE
CONCEALED IN RACEWAY PROVIDED
BY CONTRACTOR.
6. PROVIDE CEILING LOCATION WITH
SERVICE LOOP LONG ENOUGH TO
REACH THE FARTHEST LOCATION IN
THE ASSOCIATED ROOM. SECURELY
FASTEN SERVICE LOOP TO
STRUCTURE.
7. TERMINATE ALL CATEGORY 6A
CABLES ON WHITE 8P/8C (RJ45) JACKS.
8. LOCATION OF BUS BLOCKS ARE
ESTIMATED, USE BEST PRACTICES
FOR INSTALLATION LOCATION.
9. FOR ESTIMATES ASSUME ALL
CABINETS NEED GROUNDING.
C O N V E R G E N T 6197 Miller Road Suite 4 Swartz Creek, MI 48473
Phone: 810.720.3820 www.ctpartners.net
T E C H N O L O G Y P A R T N E R S
TECHNOLOGY DESIGN I CONSULTING I PLANNING
1/23/2025 DESIGN DLF
12/17/2024 DESIGN EGH
DATE ISSUE AUTHOR
SWARTZ CREEK
COMMUNITY SCHOOLS
STRUCTURED CABLING
GAINES ELEMENTARY
SCHOOL
GE-T101
T101
NTS
GAINES FLOOR PLAN
| Sheets and Views |
| GE-T101 |
File details come from the government source that posted it. Updated .