Atch 13 AF Form 3065 ProgRpt.xls

XLS spreadsheet 45 KB Posted

Attached to
NELLIS AFB SABER Federal contract opportunity
Solicitation number
FA4861-11-R-A300
Issued by
Department of the Air Force Air Combat Command

About this file

NELLIS AFB SABER

View the file

Other files for this federal contract opportunity

Other files attached to NELLIS AFB SABER, newest first.
File Type Posted
Atch 32a Bldg. 10566 Utility Layout.pdf PDF
Amend 2 Nellis SABER.pdf PDF
Nellis SABER RFP Conformed.pdf PDF
Atch 32a Bldg10566 Utility Layout.pdf PDF
Atch 33 Performance Information Form.pdf PDF
Atch 25 SOO Demo Project Bldg 10566.pdf PDF
Nellis SF30 Amendment.pdf PDF
Atch 26 Floor Plan Layout B10566.pdf PDF
Nellis SABER Questions FINAL 8 Aug 11.pdf PDF
Nellis PPQ Question and Answer 1.docx DOCX document
Atch 24 Past Performance Questionnaire.pdf PDF
Atch 28 Bonding Information Request.pdf PDF
Atch 27 Nellis Financial Information Request.pdf PDF
Atch 16 AF Form 103 Dig Outage and Location Request.pdf PDF
Atch 15 AF Form 1477 Inspection Record.pdf PDF
Atch 12 AF Form 3000 Material Approval Submittal.pdf PDF
Atch 11 AF Form 3064 Progress Schedule.pdf PDF
Atch 8 38EIGHTB33-01 Comm Infor 1st 400 Ft.doc DOC document
Atch 28 Bonding Information Request.pdf PDF
Atch 7 UFC 3-580-01.pdf PDF
Atch 9 ETL 93-5 Fire Protect.pdf PDF
Atch 3 Comm Standards dtd May 2010.pdf PDF
Atch 2 NAFB Design Stds.pdf PDF
Atch 5 Tech Spec SCIF May 5 2011.pdf PDF
Atch 17 ID Warranty.Guarantee Items.doc DOC document
Atch 19 UFC 1-300-08 How To DD1354.pdf PDF
Atch 4 ETL —
Atch 26 Floor Plan Layout B10566.pdf PDF
Atch 23 NV100004.docx DOCX document
Atch 29 Map of Nellis to Bldg. 588.docx DOCX document
Atch 12 AF Form 3000.xfdl XFDL file
Atch 14 Range Pass NAFB 0-74.doc DOC document
Atch 31 Client Authorization Letter dtd 15 Feb 10.doc DOC document
Atch 18 Sample of DD1354.pdf PDF
Atch 15 AF FORM 1477.xfdl XFDL file
Atch 24 Past Performance Questionnaire.pdf PDF
Atch 22 NV100022.docx DOCX document
Atch 10 AF Form 66.doc DOC document
Atch 11 AF Form 3064.xfdl XFDL file
Atch 20 AF Form 3052 Cost Estimate Breakdown.xls XLS spreadsheet
NELLIS SABER RFP.pdf PDF
Atch 30 Consent Letter dtd 15 Feb 10.doc DOC document
Atch 27 Financial Information Request NELLIS.pdf PDF
Atch 6 ACC Arch Interior Design Stand.pdf PDF
Atch 25 SOO Demo Project B10566.doc DOC document
Atch 21 NV100064.docx DOCX document
Atch 16 AF Form 103.xfdl XFDL file
Atch 1 NELLIS SABER Rev 12 23 June 2011--JBP.docx DOCX document
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W01

FA4861-11-R-A300/ Attachment #13
CONTRACT PROGRESS REPORT
0
CONTRACTORADDRESS
00
0
0
REPORT NO.PERIOD COVEREDPROJECT NO.COMPLETION DATE
FROMTO0OriginalChange OrderTotalCONTRACT NO.031-Dec-99
131 Dec 9931 Dec 99$0.00$0.00$0.000
LINE NO.OriginalChange OrderTotal% of Total JobContractor %

Completed This Period Contractor % Completed Cumulative CE % Completed This Period CE % Completed Cumulative

00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
00$0.00$0.00$0.000.00%0.00%0.00%0.00%0.00%
SUBTOTAL:$0.00$0.00$0.00100.00%0.00%0.00%0.00%0.00%
REMARKS: (If CE/Inspector agrees to percentages submitted by the contractor, CE percentage columns do not have to be completed. Complete only when a difference occurs.)
WORK IN PROGRESS.SCHEDULED %
0.00%
At the Contracting Officer’s discretion and according to the payments clause of the contract, the information provided may be used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications
SUBMITTED BY CONTRACTOR
TYPE OR PRINT NAME AND TITLESIGNATUREDATE
SUBMITTED BY OR FOR CIVIL ENGINEERING APPROVED DISAPPROVED
TYPE OR PRINT NAME AND TITLESIGNATUREDATE
REVIEWED BY OR FOR CONTRACTING OFFICER APPROVED DISAPPROVED
TYPE OR PRINT NAME AND TITLESIGNATUREDATE
AF Form 3065U.S. Government Printing Office: