Atch 25 SOO Demo Project B10566.doc

DOC document 67 KB Posted

Attached to
NELLIS AFB SABER Federal contract opportunity
Solicitation number
FA4861-11-R-A300
Issued by
Department of the Air Force Air Combat Command

About this file

NELLIS AFB SABER

View the file

Other files for this federal contract opportunity

Other files attached to NELLIS AFB SABER, newest first.
File Type Posted
Amend 2 Nellis SABER.pdf PDF
Atch 32a Bldg. 10566 Utility Layout.pdf PDF
Atch 25 SOO Demo Project Bldg 10566.pdf PDF
Atch 32a Bldg10566 Utility Layout.pdf PDF
Atch 33 Performance Information Form.pdf PDF
Nellis SF30 Amendment.pdf PDF
Atch 26 Floor Plan Layout B10566.pdf PDF
Nellis SABER RFP Conformed.pdf PDF
Nellis SABER Questions FINAL 8 Aug 11.pdf PDF
Nellis PPQ Question and Answer 1.docx DOCX document
Atch 24 Past Performance Questionnaire.pdf PDF
Atch 27 Nellis Financial Information Request.pdf PDF
Atch 28 Bonding Information Request.pdf PDF
Atch 12 AF Form 3000 Material Approval Submittal.pdf PDF
Atch 15 AF Form 1477 Inspection Record.pdf PDF
Atch 11 AF Form 3064 Progress Schedule.pdf PDF
Atch 16 AF Form 103 Dig Outage and Location Request.pdf PDF
Atch 12 AF Form 3000.xfdl XFDL file
Atch 14 Range Pass NAFB 0-74.doc DOC document
Atch 31 Client Authorization Letter dtd 15 Feb 10.doc DOC document
Atch 13 AF Form 3065 ProgRpt.xls XLS spreadsheet
Atch 18 Sample of DD1354.pdf PDF
Atch 15 AF FORM 1477.xfdl XFDL file
Atch 24 Past Performance Questionnaire.pdf PDF
Atch 22 NV100022.docx DOCX document
Atch 10 AF Form 66.doc DOC document
Atch 11 AF Form 3064.xfdl XFDL file
Atch 2 NAFB Design Stds.pdf PDF
Atch 5 Tech Spec SCIF May 5 2011.pdf PDF
Atch 17 ID Warranty.Guarantee Items.doc DOC document
Atch 19 UFC 1-300-08 How To DD1354.pdf PDF
Atch 4 ETL —
Atch 26 Floor Plan Layout B10566.pdf PDF
Atch 23 NV100004.docx DOCX document
Atch 29 Map of Nellis to Bldg. 588.docx DOCX document
Atch 20 AF Form 3052 Cost Estimate Breakdown.xls XLS spreadsheet
NELLIS SABER RFP.pdf PDF
Atch 30 Consent Letter dtd 15 Feb 10.doc DOC document
Atch 27 Financial Information Request NELLIS.pdf PDF
Atch 6 ACC Arch Interior Design Stand.pdf PDF
Atch 21 NV100064.docx DOCX document
Atch 16 AF Form 103.xfdl XFDL file
Atch 1 NELLIS SABER Rev 12 23 June 2011--JBP.docx DOCX document
Atch 8 38EIGHTB33-01 Comm Infor 1st 400 Ft.doc DOC document
Atch 28 Bonding Information Request.pdf PDF
Atch 7 UFC 3-580-01.pdf PDF
Atch 9 ETL 93-5 Fire Protect.pdf PDF
Atch 3 Comm Standards dtd May 2010.pdf PDF
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA4861-11-R-A-300

Attachment #25

NELLIS SABER IDIQ

STATEMENT OF OBJECTIVES

FOR

Repair Interior for Restrooms and Eyewash

Bldg. 10566

RKMF 11-0160

NELLIS AIR FORCE BASE, NEVADA

21 June 2011

OFFICE OF THE BASE CIVIL ENGINEER

NELLIS AIR FORCE BASE, NEVADA

STATEMENT OF OBJECTIVES

1. SCOPE: Contractor shall furnish all design, labor, equipment, material, transportation, administration, supervision and all else necessary to perform all operations in connection with successfully completing this project RKMF 11-0160, Repair Interior for Restrooms & Eyewash, Bldg. 10566 at FORMDROPDOWN . When complete, the project shall be as shown below (either in the attached sketch or work description). Include in the submittal, reference to the specifications that apply to this project and identification of material items required to be submitted to the government for approval (use AF Form 66), both will be incorporated in the construction project.

2. LOCATION: The project site is located at FORMDROPDOWN . The Main base is located approximately FORMDROPDOWN miles north of downtown Las Vegas on Highway US 93 (Las Vegas Blvd.). NAFB consists of three main areas: the Main Base, Area II and Area III.

3. CODES: All design and construction must be in compliance with the International Building Code (UBC-2006) (or most recent edition), Department of Defense Unified Facilities Criteria Standards (UFC), all Public Laws, Executive Orders, Code of Federal Regulations, Department of Defense Instructions, (DODI), Department of Defense Directives, NAFB Design Compatibility Guidelines, Clark County, State of Nevada and Federal standards, codes and laws or other higher authority documents as applicable.

4. DRAWING STANDARDS: All drawings submitted shall be prepared in accordance with the applicable provisions of the Architectural/Engineering/Construction (A/E/C) Computer-Aided Design and Drafting (CADD) standard. All drawings shall comply with the specifications in Attachment #1 for Simplified Acquisition of Base Engineering Requirements (SABER) dated 20 June 2011. Contractor shall maintain one set of drawings on site and record all changes and any hidden or subsurface data discovered during construction. Construction drawings shall be submitted to government with Red Line Marks.

5. ENVIRONMENTAL PROTECTION: All work and contractor operations shall comply with the requirements imposed by all applicable Federal, State, local and NAFB laws, regulations, codes and permits (including NAFB Management Plan12) concerning environmental protection. Test for Asbestos Containing Material (ACM) and Lead Base Paint (LBP) in the area of construction. Provide test report of findings to government.

DESCRIPTION OF WORK: The work to be accomplished includes but is not limited to the following description: Construct new men’s and women’s restroom with double showers complete. Provide and install (1) mop utility sink plumbed and (1) eye wash station plumbed. Each restroom will have an audio/visual and heat detector fire alarm system that will be incorporated with the existing alarm system.

GENERAL CONDITIONS

· The Contractor shall furnish the toilet facilities during the execution of the delivery order.

· The Government shall furnish electrical power and water but no toilet facility is available in the building during the execution of the delivery order.

· Contractor will provide project site and/or material storage security if necessary.

· Contractor will include estimated cost for construction fencing if necessary.

· Contractor shall furnish 35% Construction Plans /drawings to begin construction.

· Contractor shall furnish Preliminary As-Builts Drawings for review and approval before submitting Final As-builts for review and approval.

EXISTING CONDITIONS WORK

Provide the necessary rubbish handling, disposal, etc for all project materials.

DIVISION 02 SITEWORK

02.01 Install all utilities, (Power, Potable Water and Sewer) from point of origin to building 10566.

DIVISION 03 CONCRETE

03.01 Provide necessary concrete filled bollards on driveway side and paint four (4) safety (black and yellow) striped bollards

DIVISION 05 METALS WORK

05.01 Fur all walls the restrooms with 3 5/8”, 20 GA, metal studs, 16” OC, drywall, tape, texture and paint. (Color to be selected by the Government)

DIVISION 07 THERMAL AND MOISTURE PROTECTION WORK

07.01 Provide and install R-19 insulation behind on all furred walls.

DIVISION 08

OPENING WORK

08.01 Men’s and Women’s restroom doors shall be ADA compliant 3070, 1 3/4” solid core oak with standard lock set.

08.02 Install push/pull hardware and indicator deadbolt lock on both restroom doors.

08.03 All locksets shall be compatible with base standards 7-pin, interchangeable cores FALCON/BEST cores and hardware.

DIVISION 09 FINISHES WORK

09.01 Install new ½” gypsum green board walls behind all wet areas in the men’s and women’s restroom.

09.02 Provide and install new VCT flooring in the men’s and women’s Restroom. Samples are to be provided by the Contractor. Color to be selected by the Government.

09.03 Provide and install new 6” x 6” wall tile 4-feet from floor base in the men’s and women’s restroom. Tile colors samples are to be provided by the Contractor. Color will be chosen by the Government.

09.04 Provide and install new 2’x 2’ tegular white suspended ceiling grid and tiles at 8’ high in the men’s and women’s restroom.

09.05 Provide and install mud, tape and texture to all new wall surfaces.

09.06 Provide all new painted wall surfaces. One layer of primer and (2) layers of finish coat in the men’s and women’s restroom. Color to be approved by Government.

09.07 Provide and install solid surface counter tops with seamless sinks and back splash in the restrooms. Color to be selected by the Government.

DIVISION 10

SPECIALTIES WORK

10.01 Provide and install standard stainless steel bathroom accessories to include toilet tissue dispensers, paper towel/waste receptacles, soap dispensers, seat protector dispenser, ADA grab bars and vanity glass mirrors, and sanitary napkin dispenser in the men’s and women’s restroom.

10.02 Test for Asbestos Containing Material (ACM) and Lead Base Paint (LBP) in the area of construction. Provide report of findings. Asbestos and Lead abatement is assumed to be present for this scope of work

DIVISION 15 HVAC

15.01 Provide and install all the necessary supply and return-diffusers, registers, grills etc for the men’s and women’s restroom

15.02 Tie into existing HVAC to provide restrooms with heating and cooling.

15.03 Provide exhaust vents in each restroom venting to the outside of the building.

DIVISION 16 ELECTRICAL

16.01 Install exit and emergency light fixtures in the (2) restrooms.

16.02 Provide and install T-8 fluorescent lighting for the men’s and women’s restroom.

16.03 Provide and install new receptacles, face plates, switches, etc. in the men’s and women’s restroom.

DIVISION 17 PLUMBING

17.01 Provide and install (2) sinks with wall mounted, laminated countertops, (1) ADA toilet/partition, (2) shower stalls in the women’s restroom

17.02 Provide and install (2) sinks with wall mounted, laminated countertops, (1) ADA toilet/ partition, (1) urinal and (2) shower stalls in the men’s restroom.

17.03 Provide and install (1) mop sink.

17.04 Provide and install (1) eye wash station.

17.05 Provide and install an ADA compliant water fountain in the alcove outside the restrooms.

DIVISION 21

FIRE SUPPRESSION WORK

021.01. Provide and install audio / visual and heat detector sensors within the portable offices. System to be tied into the existing fire alarm system.

21.02 Provide new LED exit lights above exit doors of the men’s and women’s restroom.

21.03 Provide new battery emergency lights inside the men’s and women’s restroom.

021.04 Design for fire alarm system within the restrooms shall be reviewed and signed by a

Level IV NICET registered in the State of Nevada. The system must be install by a

Certified installer.

021.05 Provide a set of Construction Drawings; Preliminary As-Built drawings and Final As-

Built drawings, of the fire alarm system going into the modular offices. Provide preliminary as-builts for the Nellis AFB Fire Department and to 99 Cons within 10 calendar days of the system acceptance inspection conducted by the Nellis AFB Fire

Inspector.

21.06 Provide (1) fire extinguisher cabinet to be attached to the wall outside the restrooms.

END OF STATEMENT OF OBJECTIVES