Attch _52 _MACC_Contracting_Questions_and_Answers.pdf

PDF 41 KB Posted

Attached to
Multiple Award Construction Contract, Shaw AFB, SC FY13 Federal contract opportunity
Solicitation number
FA4803-13-R-0005
Issued by
Department of the Air Force Air Combat Command

About this file

Attch. 52 MACC Contracting Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract, Shaw AFB, SC FY13, newest first.
File Type Posted
Attch._51 _MACC_Technical_Questions_and_Answers.pdf PDF
Attch._50 _B912_Revised_SOW_Oct_18_2013.pdf PDF
Amendment_8.pdf PDF
Attch._47 _PAST_AND_PRESENT_PERFORMANCE_QUESTIONNAIRE_UPDATE.pdf PDF
Attch_43 _AutoCAD_2.dwg DWG drawing
Attch_42 _AutoCAD_1.dwg DWG drawing
Attch_46 _912_FLOOR_PLAN.dwg DWG drawing
Attch_48 _MACC_Technical_Questions_and_Answers.pdf PDF
Attch_49 _MACC_Contracting_Questions_and_Answers.pdf PDF
Attch_41 _B912_Revised_SOW_Sept_25_2013.pdf PDF
Attch_44 _AutoCAD_3.dwg DWG drawing
Amendment_7 _MACC.pdf PDF
Amendment_6.pdf PDF
Atch_38 _tech_Qs.pdf PDF
Atch_40 _MACC_Site_Visit_2_10_September_2013_Sign-in.pdf PDF
Atch_39 _Contracting_Qs.pdf PDF
Atc_37 _B912_Revised_SOW_Sept_20_2013.pdf PDF
Atc_31_Floor_Plan_Title_Block_Template.dwt —
Atc_36_B912_Revised_SOW_Aug_29_2013.pdf PDF
Atc_28_Electrical2.pdf PDF
Atc_32_ShawDrawingCoverSheet.dwg DWG drawing
Atc_35_Contracting_Questions.pdf PDF
Atc_27_Electrical1.pdf PDF
Atc_33_Chapel_area_survey_(2).pdf PDF
Atc_34_Technical_Questions_and_Answers.pdf PDF
Atc_30_Electrical4.pdf PDF
Attch_25-MACC_Meeting_Minutes.pdf PDF
Attch_19-_Technical_Q A.pdf PDF
Attch_23-MACC_Project_Chapel_Survey.dat —
Attch_18-Contracting_Q A.pdf PDF
Attch_24-Water_Flow_Test_Map.pdf PDF
Attch_21-Chapel_Utility_area.pdf PDF
Attch_20-Chapel_Contours.pdf PDF
Attch_22-Chapel_Utility_with_all_area_markings.pdf PDF
Attachment_16 _Questions_ _Answers_set__2.pdf PDF
MACC_amendment__3.pdf PDF
Attachment_14_Blank_Cost_Estimate.xls XLS spreadsheet
Attachment_15 _Base_Map_to_pre-bid_site.pdf PDF
Amendment_2 _MACC.pdf PDF
Attch_13_MACC_Technical_Questions.pdf PDF
amendment_1 _MACC.pdf PDF
Attachment_5-SpecSection01000.pdf PDF
Attachment_2_MACC_Provisions_Feb_26_2013.pdf PDF
Attachment_3-_Shaw_AFB_Design_Standards.pdf PDF
Attachment_8_WD_SC130043_Highway.pdf PDF
Attachment_12_Security_Requirements.pdf PDF
Attachment_7_WD__SC130037_Bldg.pdf PDF
FA4803-13-R-0005_FY_13_MACC_Solicitation.pdf PDF
Attachment_6_WD_SC130011_Dredging.pdf PDF
Attachment_11-_Sample_Project.pdf PDF
Show all 50

Multiple Award Construction Contract, Shaw AFB, SC FY13 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Information provided via answers to these questions in this amendment shall not qualify the terms and conditions of the solicitations and specifications. Terms of the solicitation and specifications remain unchanged unless specifically amended in the solicitation. Any disparity between the answers to the questions and the changes to the terms of the solicitation and specifications of the solicitation will go in favor of the actual solicitation, not answers to questions. If an amendment is issued, normal procedures relating to the acknowledgement and receipt of solicitation amendments shall apply.

1. Contractor XYZ would like to request a copy of the ACC Interior Design Guide latest edition. We need this document in order to prepare our required color board in the Shaw AFB MACC Proposal.

Please instruct me on how to attain the ACC Interior Design Guide latest edition.

The ACC Interior Design guide has been incorporated into the Shaw ID2 handbook (attachment 26) which is included in the solicitation, also further design requirement can be located in UFC 3-120-10

2. We are bidding on this project and in the process of obtaining Bid Bond but I’m wondering if this is required for the sample project. Also, I didn’t see a liquidated damages amount. Can you clarify if these are needed?

See question 55 amendment # 5, Yes bid bonds will be required IAW FAR 28.101.

See question 35 amendment #2, There are no LD’s for the sample project as this is for evaluation purposes only. The determination to include LD’s will be made post award per individual task order as appropriate.

3. Due to the furlough of the entire NC SBA office, our required Joint Venture submittal may be incomplete if the SBA has not reviewed and returned to us at the time of proposal due date, Nov. 15, 2013.

How will Shaw contracting treat this requirement?

The Government shutdown is not a consideration for extending the proposal due date.

3. Am 7, attachment 48 states: 2. Per Amendment #5 revised Proposal Instructions - 3. PART III - PAST PERFORMANCE INFORMATION - Limited to no more than 10 pages, excluding past performance questionnaires. Question: Would the government please consider changing the 10 page limitation to only be applicable to the requested Item (a) Performance Survey Information; thereby allowing sufficient spacing to address the other requested information in additional Items (b), (c), and (d) of PART III? Government Answer: No the limitation will not be changed. The 10 page limitation is sufficient to address requirements of (b), (c), and (d).

Question: Q. Per Amendment #5 revised Proposal Instructions - 3. PART III - PAST PERFORMANCE INFORMATION - Limited to no more than 10 pages, excluding past performance questionnaires. Item D requires a letter of consent from major subcontractors be included in the response. A letter would take up an entire page, can Item D not be part of the overall 10 pages for Part III?

The consent letter will not count against Part III page limitation.

4. Item C. Specific Instructions/3. Part III Past performance Info, states ..the government will evaluate the quality and extent of "offeror's" performance deemed relevant

Question: Please clarify for Part III, Past Performance Information/past performance surveys are requested only on the offeror/JVs. Should any portion of the 10 projects be provided from "major subcontractors" such as a major/ key design firm that is a subcontractor to the offeror?

See Section L “ Instructions to Offerors” of the solicitation.

5. It is indicated in the Solicitation to mail all bid submission documents to: 20 CONS/LGCAB, ATTN:

JOSEPH NEMEDY/ DO NOT OPEN - RFP FA4803-13-R-0005, 321 Cullen Street (Bldg 216), SHAW AFB, SC 29152. Will hand deliveries be acceptable? If so, to what address should they be delivered?

Yes, Same as above. Note: No escort(s) will be provide for hand deliveries.

6. To go to silver design concept/cost, we are to start fresh and coordinate all parties to comply with this requirement. We strongly feel that we need additional time, is additional time to be granted?

No time extension is to be granted, reference technical question 7 from attachment

7. The Government has verbally stated in the first site visit that the lowest cost per square foot will be one of the deciding factors for award. This is not mentioned in the solicitation. Also, there is not currently an area to give a cost per square foot value in section B of the Solicitation. The Government has stated in the solicitation a review of "Best Value" and "LPTA". Per LPTA, as we understand, the Government will chose the lowest price for the new addition, then review for technical acceptability and then move on to the higher priced proposals during the government review. IS THIS A CORRECT ASSUMPTION?

See Section M001- Source Selection paragraph f.

Furthermore, please advise if the government will be..

8. ISSUING A NEW ADDENDUM THAT GIVES BIDDING CONTRACTORS THE OPTION TO

FURNISH A COST PER SQUARE FOOT VALUE?

No addendum will be issued. Provide proposal pricing information IAW Section M of the solicitation.

9. OR IF THE BIDDING CONTRACTORS SHOULD ASSUME GIVING THE LOWEST PRICE AS

POSSIBLE TO MEET THE INTENT OF THE DESIGN STANDARDS PER A TRUE LPTA (LOWEST

PRICE TECHNICALLY ACCEPTABLE) REVIEW AS STATED ON PAGE 6 OF 17 OF ATTACHMENT

2?

This reference is General MACC provisions “ Bid/Proposal Evaluation Criteria” is for individual Task orders after Contract award of MACC. Please reference the solicitation Section(s) L and M for specific evaluation criteria.

10. OR SHOULD THE BIDDING CONTRACTORS ASSUME THAT THE GOVERNMENT WILL

REVIEW ALL BIDDING CONTRACTORS PROPOSALS BASED UPON THE "BEST VALUE" METHOD

AS STATED ON PAGE 4 OF 17 OF ATTACHMENT 2 ?

This reference is General MACC provisions “Definitions” not evaluation criteria. Please reference the solicitation Section(s) L and M for specific evaluation criteria.

11. It appears that Attachment 47 - Present & Past Performance Questionnaire Update - is missing from Amendment 7. Will you be posting that as part of Amendment 8?

The past performance questionnaire update will be posted with amendment # 8

Information provided via answers to these questions in this amendment shall not qualify the terms and conditions of the solicitations and specifications. Terms of the solicitation and specifications remain unchanged unless specifically amended in the solicitation. Any disparity between the answers to the questions and the changes to the terms of the solicitation and specifications of the solicitation will go in favor of the actual solicitation, not answers to questions. If an amendment is issued, normal procedures relating to the acknowledgement and receipt of solicitation amendments shall apply.