MATERIAL APPROVAL SUBMITTAL
(See Instructions on Reverse)
Form Approved OMB No 9000-0062
Expires May 31, 2005
Public reporting burden for this collection of information is estimated to average 20 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the Department of Defense, Washington Headquarters Services, Directorate for Information Operations and
Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project OMB No 9000-0062, Washington DC 20503. Please DO NOT RETURN your form to either of these addresses. Send your completed form to: SAF/AQCP, 1060 Air Force Pentagon, Washington DC
TO: (Contracting Officer) FROM: (Contractor) DATE
CONTRACT NUMBER SUBMISSION NUMBER SUBMITTAL
PREVIOUS SUBMISSION NUMBER PROJECT NUMBER
TO BE COMPLETED BY CONTRACTOR FOR GOVERNMENT USE ONLY
ITEM
NO.
SPECIFICATION SECTION/
PARA NO./DRAWING NO.
DESCRIPTION OF MATERIAL
(Include Type, Model Number, Catalog Number, Mfg., etc.)
AP-
PROVED
DISAP-
PROVED
SEE
REVERSE
INITIAL
BY COMPLETING THIS FORM, THE UNDERSIGNED CONTRACTOR CERTIFIES THAT
THE MATERIAL COMPLIES WITH ALL SPECIFICATIONS OF SUBJECT CONTRACT.
DATE (YYYYMMDD) TYPE OR PRINT NAME AND GRADE SIGNATURE
FOR GOVERNMENT USE ONLY
TO: (Base Civil Engineering Officer)
For Evaluation and Action RNLT ________________ OR SOONER
DATE (YYYYMMDD) TYPE OR PRINT NAME AND GRADE SIGNATURE
TO: (AF Contracting Office)
RECOMMEND APPROVAL DISAPPROVAL AS INDICATED ABOVE AND SUBJECT TO ANY APPLICABLE COMMENTS ON THE REVERSE
DATE (YYYYMMDD) TYPE OR PRINT NAME AND GRADE SIGNATURE
TO: (Contractor)
APPROVED
DISAPROVED AS INDICATED ABOVE AND SUBJECT TO ANY APPLICABLE COMMENTS ON THE REVERSE SIDE. REQUEST
RESUBMITTAL ON DISAPPROVED ITEMS WITHIN ____ DAYS OF DATE SHOWN BELOW.
DATE (YYYYMMDD) TYPE OR PRINT NAME AND GRADE SIGNATURE
AF IMT 3000, 20030901, V1 PREVIOUS EDITION IS OBSOLETE.
New Resubmittal
COMMENTS
(Number to correspond with applicable Item Number on reverse)
INSTRUCTIONS TO CONTRACTORS
1. The term "material" is defined as articles, supplies, raw materials, equipment, parts, components, and end items that are to be incorporated into the work required by the contract.
2. This form is to be used by contractors for submitting Shop Drawings, Equipment Data, Manufacturer's Literature and Certificates and samples of Materials to the Government for approval in accordance with the provisions of this contract. Unless otherwise specified, it is to be prepared in 4 copies, signed, and provided to the contracting officer with appropriate attachments.
3. Item(s) to be approved will be clearly tabbed or identified. Data pertaining to item(s) to be approved will be clearly identified or tabbed, particularly where documents are voluminous, in order to properly evaluate the materials or articles to be incorporated in the work. Each attachment will be numbered to correspond with the item number shown on the face of this form.
4. Requests submitted shall be numbered consecutively, by contract, in the space entitled "Submission No.". This number, in addition to the Contract No., will be used to identify each Material Approval Submittal. Resubmissions will be indicated in the appropriate block and the insertion of previous submission number and data in addition to a new submission number. A single submission should be used for all work of a section of the specifications, but in NO instance should the submission include work for more than one (1) contract. Submittals requiring priority handling will be submitted by separate submittal using the form and so marked across the face of the form.
5. This Material Approval Submittal is not valid unless it is signed by the contracting officer. This approval is required as called for by the contracting officer under the terms of this contract.
AF IMT 3000, 20030901, V1 (REVERSE)
~T
GEOTEC LABS
A DIVISION OF ENPROTEC I HIBBS & TODD. INC
402 CEDAR
P 0 BOX3097
FAX 325 690 9127
ABILENE TX 79604-3097
TEL 325 696 5563
wwwe-htcom
COMPRESSION TEST REPORT
BILL TO: FARR BUILDERS LLC
3401 S GEVERS ST # 1
SAN ANTONIO, TX 78210
REPORT NO:
DATE POURED:
PROJECT: REPAIR MAINTENANCE SHOP- BUILDING 8040 TECHNICIAN:
TIME POURED:
CONCRETE TEMP:
AIR CONTENT:
SAMPLE MARK
DF-1
DF-2
DF-3
DF-4
REMARKS:
3:10 p 66° 3.0
Hold
MIX: 70M23509
PLACEMENT: grade beams I footings
SLUMP IN INCHES: 3%
WATER ADDED TO TRUCK 10 gallons
ACCUMULATED YARDS: 9.5
DATE
TESTED
03-26-18
04-11-18
04-11-18
Hold
TOTAL
LOAD- LBS
54,000
A 51989-18
03-14-18
JOSH ALVAREZ
TRUCK NO:
TICKET NO:
WEATHER:
3380160 70°
COMPRESSIVE
STRENGTH - PSI
4,300
COMPRESSIVE STRENGTHS DETERMINED IN ACCORDANCE WITH A.S.T.M. C39. CROSS SECTIONAL AREA, DIAMETER AND LENGTH ARE STANDARD UNLESS OTHERWISE NOTED.
PORTIONS OF THE INFORMATION CONTAINED IN THIS REPORT HAVE BEEN FURNISHED BY OTHERS CYLINDERS CURED IN LABORATORY IN ACCORDANCE WITH A.S.T.M. C31 UNLESS
OTHERWISE NOTED. IN COMPLIANCE WITH A.S,T.M. C138 C143 C172 C173 C231 C1064 C617 C1231.
REPORT DISTRIBUTION I GEOTEC LABS
e-mail group C.M .'f"~{;?sCOTI YUNGBLUT, P.E
Results shown on this report are for the exclusive use or the client for whom they were obtained and apply only to the samples tested and/or inspected They are not intended to be indicative of the qualities of apparently identical products The use of our name must receive prior approval
Firm Registration No 1151 PG Firm Registration No 501 03
RPLS Firm Nos 10011900 & 10007300
| AF Form 3000 Submittal #38 Concrete Break Test Results |
| FARR - BLD. 8040 CONCRETE 51989 03-14 |
| TO Contracting Officer: Capt. Hillary Ince |
| FROM Contractor: FARR Builders LLC |
S. Gevers, San Antonio, TX 78210
| DATE: 29 Mar. 2018 | |
| CONTRACT NUMBER: FA4661-15-D-0001 | |
| SUBMISSION NUMBER: 38 | |
| PREVIOUS SUBMISSION NUMBER: 37 | |
| PROJECT NUMBER: FNWZ 12-0053 | |
| ITEM NORow1: 1 | |
| SPECIFICATION SECTION PARA NODRAWING NORow1: Per Sow | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow1: Concrete Test Results | |
| INITIALRow1: PR | |
| ITEM NORow2: | |
| SPECIFICATION SECTION PARA NODRAWING NORow2: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow2: | |
| INITIALRow2: | |
| ITEM NORow3: | |
| SPECIFICATION SECTION PARA NODRAWING NORow3: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow3: | |
| INITIALRow3: | |
| ITEM NORow4: | |
| SPECIFICATION SECTION PARA NODRAWING NORow4: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow4: | |
| INITIALRow4: | |
| ITEM NORow5: | |
| SPECIFICATION SECTION PARA NODRAWING NORow5: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow5: | |
| INITIALRow5: | |
| ITEM NORow6: | |
| SPECIFICATION SECTION PARA NODRAWING NORow6: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow6: | |
| INITIALRow6: | |
| ITEM NORow7: | |
| SPECIFICATION SECTION PARA NODRAWING NORow7: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow7: | |
| INITIALRow7: | |
| ITEM NORow8: | |
| SPECIFICATION SECTION PARA NODRAWING NORow8: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow8: | |
| INITIALRow8: | |
| ITEM NORow9: | |
| SPECIFICATION SECTION PARA NODRAWING NORow9: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow9: | |
| INITIALRow9: | |
| ITEM NORow10: | |
| SPECIFICATION SECTION PARA NODRAWING NORow10: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow10: | |
| INITIALRow10: | |
| ITEM NORow11: | |
| SPECIFICATION SECTION PARA NODRAWING NORow11: | |
| DESCRIPTION OF MATERIAL Include Type Model Number Catalog Number Mfg etcRow11: | |
| INITIALRow11: | |
| DATE YYYYMMDD: 2018-03-29 | |
| TYPE OR PRINT NAME AND GRADE: Wayne Owens, PS | |
| TO Base Civil Engineering Officer: 502 CE | |
| RNLT: | |
| DATE YYYYMMDD_2: 20180409 | |
| TYPE OR PRINT NAME AND GRADE_2: A1C Yeongsoo Jeon | |
| TO AF Contracting Office: 7 CONS | |
| DATE YYYYMMDD_3: 20180406 | |
| TYPE OR PRINT NAME AND GRADE_3: Patrick Rolan | |
| TO Contractor: FARR Builders LLC. | |
| DATE YYYYMMDD_4: 20180409 | |
| TYPE OR PRINT NAME AND GRADE_4: 1st Lt Teresa Elsbree | |
| 2018-04-09T13:48:37-0500 | |
| JEON.YEONGSOO.1538040130 |
| 2018-04-06T14:53:21-0500 | |
| ROLAN.PATRICK.M.1515150249 |
| 2018-04-09T17:05:18-0500 | |
| ELSBREE.TERESA.JEANETTE.1395813010 |
| Text5: |
| Check Box6: Yes |
| Check Box7: Off |
| Check Box8: Off |
| Check Box9: Off |
| Check Box10: Off |
| Check Box11: Off |
| Check Box12: Off |
| Check Box13: Off |
| Check Box14: Off |
| Check Box15: Off |
| Check Box16: Off |
| Check Box17: Off |
| Check Box18: Off |
| Check Box19: Off |
| Check Box20: Off |
| Check Box21: Off |
| Check Box22: Off |
| Check Box23: Off |
| Check Box24: Off |
| Check Box25: Off |
| Check Box26: Off |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Check Box31: Off |
| Check Box32: Off |
| Check Box33: Off |
| Check Box34: Off |
| Check Box35: Off |
| Check Box36: Off |
| Check Box37: Off |
| Check Box38: Off |
| Check Box3: Yes |
| Check Box50: Off |
| Check Box4: Yes |
| Check Box5: Off |
| Check Box39: Yes |
| Check Box40: Off |
| COMMENTS Number to correspond with applicable Item Number on reverseRow1: |