This is a Synopsis for Anticipated Orders issued by the 60th Contracting Squadron at Travis Air Force Base on February 5, 2026, announcing two upcoming contract opportunities under Pool 1. The document outlines anticipated federal construction and facility renovation projects for the base.

The first anticipated order concerns the B878 Split System Replacement Phase 2, located at Building 878 on Travis AFB, with an estimated magnitude between $25,000 and $100,000. The contractor must provide complete labor, equipment, tools, materials, and supervision to remove and replace an existing 4-ton Carrier air conditioning system (condenser and evaporator/furnace) with a new DX split heat pump system on the roof, including associated ductwork replacement, integration with existing dampers, connection to the Energy Management and Control System (EMCS) ports, and relocation of existing ductwork from the attic. All work must comply with Federal, State, and Local Code requirements, including the International Mechanical Code, International Plumbing Code, International Energy Conservation Code, National Electrical Code, ASHRAE standards, OSHA, NFPA, and Unified Facilities Criteria. The contractor must also ensure BACnet/ASHRAE-135 protocol compliance for seamless integration with the existing Johnson Controls Metasys server per UFC 3-410-02.

The second anticipated order is for a Storefront Door Package affecting multiple buildings across Travis AFB (Buildings 155, 179, 380, 383, 549, 615, 660, and 8993), with an estimated magnitude between $100,000 and $250,000. The contractor must resolve door-related issues while coordinating with building occupants and facility managers to minimize mission interruption, providing 14 days' advance notice of any shutdowns. Work must comply with Federal, State, and Local Code requirements, including the National Standard Plumbing Code, National Electrical Code, ASHRAE standards, OSHA, NFPA, and UFC codes. For both opportunities, the Contracting Officer is to be determined, and the Point of Contact is 2nd Lt Phillip Manwaring at phillips.manwaring@us.af.mil or DSN 424-7769.

View the file

Other files

File Type Posted
SYNOPSIS FOR ANTICIPATED ORDERS_July 2026 (2).pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS_Pool 1_July 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDER_Pool 1_4 May 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDER_Pool 1_22 Apr 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS Pool 2 21 April 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDER_Pool 1_21 Apr 2026.pdf PDF
Attachment 6 - Instructions for BOA Application_Amend 3.pdf PDF
Consolidated RFI Responses_3.17.26.xlsx XLSX spreadsheet
Attachment 7 - Application Evaluation Procedures_Amend 3.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS (B380A 383) (002).pdf PDF
SYNOPSIS FOR ANTICIPATED POOL 1 ORDER -Building 859 Flooring Paint Windows.pdf PDF
Attachment 7 - Application Evaluation Procedures_Amend 2.pdf PDF
Attachment 6 - Instructions for BOA Application_Amend 2.pdf PDF
Consolidated RFI Responses.xlsx XLSX spreadsheet
SYNOPSIS FOR ANTICIPATED ORDERS (B381 - B4) 18 FEB 2026.docx DOCX document
SYNOPSIS FOR ANTICIPATED ORDERS Pool 2 28 January 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 22 JAN 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 7 Jan 26.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 31 Dec 2025.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 31 Dec 2025.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 15 Dec 2025.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 6 - Instructions for BOA Application.docx DOCX document
Attachment 7 - Application Evaluation Procedures.docx DOCX document
SYNOPSIS FOR ANTICIPATED ORDERS.pdf PDF
Synopsis for Anticipated Orders - 22 May.pdf PDF
Synopsis for Anticipated Orders.pdf PDF
Consolidated RFI Responses.xlsx XLSX spreadsheet
Attachment 4 - Application.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 1 - Travis Specification.zip ZIP file
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 2 - Model Agreement.pdf PDF
Attachment 4 - Application.pdf PDF
Attachment 3 - Request for Information.xlsx XLSX spreadsheet
Attachment 5 - SF330.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SYNOPSIS FOR ANTICIPATED ORDERS Pool 1

60th Civil Engineering Squadron & 60th Contracting Squadron

Travis AFB

5 February 2026

SYNOPSIS FOR ANTICIPATED ORDERS

05 Feb 2026

Contracting Office: 60 CONS 350 Hangar Ave B549 Travis AFB, CA 94535

Subject: B878 Split System Replacement Ph2

Location: B878, Travis AFB

Magnitude Range: Between $25,000 and $100,000

Subject: The contractor shall provide all labor, equipment, tools, material, supervision, and any other items necessary to properly remove and replace the existing 4-ton Carrier air conditioning (condenser, evaporator/furnace) system and install a new DX split heat pump system on roof, including associated ductwork replacement, integration with existing dampers, connection to the Energy Management and Control System (EMCS) ports, and the relocation of existing ductwork for the separate split unit currently located in the attic. The contractor shall comply with Federal, State, and Local Code requirements, as well as the IMC (International Mechanical Code), IPC (International Plumbing Code), IECC (International Energy Conservation Code), NEC (National Electrical Code), ASHRAE (American Society of Heating, Refrigerating and Air-Conditioning Engineers) standards, and Occupational Safety and Health Administration (OSHA), National Fire Protection Agency (NFPA), and Unified Facilities Criteria (UFC) codes and standards.

Compliance with BACnet/ASHRAE-135 protocols and standards to provide seamless integration with the existing EMCS Johnson Controls Metasys server and to maximize data interoperability in accordance with UFC 3-410-02 and in alignment with industry best practices is also required.

Contracting Officer: TBD

Point of Contact: 2nd Lt Phillip Manwaring (Email: phillip.manwaring@us.af.mil, DSN:424- 7769)

SYNOPSIS FOR ANTICIPATED ORDERS

05 Feb 2026

Contracting Office: 60 CONS 350 Hangar Ave B549 Travis AFB, CA 94535

Subject: Storefront Door Package

Location: Various Buildings on Travis AFB

Magnitude Range: Between $100,000 and $250,000.

Subject: The contractor shall provide all labor, equipment, tools, material, supervision, and any other items necessary to resolve door-related issues for buildings 155, 179, 380, 383, 549, 615, 660, and 8993. The contractor shall coordinate with the building occupants through the facility manager to ensure there will be minimum interruptions to their daily mission. The contractor shall ensure the facility manager is notified of shut down fourteen (14) days in advance. Any work not specifically covered by the specifications shall comply with Federal, State, and Local Code requirements, as well as the NSPC (National Standard Plumbing Code), NEC (National Electrical Code), ASHRE, Heating Ventilation Air Conditioning standards, and Occupational Safety and Health Administration (OSHA), National Fire Protection Agency (NFPA), and Unified Facilities Criteria (UFC) codes and standards.

Contracting Officer: TBD

Point of Contact: 2nd Lt Phillip Manwaring (Email: phillip.manwaring@us.af.mil, DSN:424- 7769)

File details come from the government source that posted it. Updated .