This document contains application instructions for a Basic Ordering Agreement (BOA) for construction services at Travis Air Force Base, California. The solicitation is divided into two pools: Pool 1 for Minor Construction and Pool 2 for Major Construction. Applications are open for submission anytime through 15 May 2030 at 14:30 PST. All applicants must maintain an active System for Award Management (SAM) registration at SAM.gov at the time of submission and submit a single PDF application using Attachment 4. Questions and applications for Pool 1 should be directed to Lt Phillip Manwaring (phillip.manwaring@us.af.mil) or Ms. Christina Johnson (christina.johnson.32@us.af.mil), while Pool 2 inquiries should go to Mr. Brandon Spratt (brandon.spratt.2@us.af.mil).

Both pools require submission of identical core documents: a cover letter using the provided template (failure to use the template results in automatic rejection), a past performance questionnaire highlighting three multi-disciplinary construction projects completed within the past three years for the Department of Defense or other federal agencies (or notation of "No relevant past experience" if unavailable), and a bonding capability letter from the applicant's surety demonstrating maximum bonding capability per order. Pool 2 has an additional requirement: applicants for the Design Build Construction Pool must complete and submit the SF-330 Architect-Engineer Qualifications form (Attachment 7), with a separate Section E for each discipline including Architect, Civil, Mechanical, and Electrical specialties.

View the file

Other files

File Type Posted
SYNOPSIS FOR ANTICIPATED ORDERS_July 2026 (2).pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS_Pool 1_July 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDER_Pool 1_4 May 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDER_Pool 1_22 Apr 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS Pool 2 21 April 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDER_Pool 1_21 Apr 2026.pdf PDF
Consolidated RFI Responses_3.17.26.xlsx XLSX spreadsheet
Attachment 7 - Application Evaluation Procedures_Amend 3.pdf PDF
SYNOPSIS FOR ANTICIPATED POOL 1 ORDER -Building 859 Flooring Paint Windows.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS (B380A 383) (002).pdf PDF
Attachment 6 - Instructions for BOA Application_Amend 2.pdf PDF
Consolidated RFI Responses.xlsx XLSX spreadsheet
Attachment 7 - Application Evaluation Procedures_Amend 2.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS (B381 - B4) 18 FEB 2026.docx DOCX document
SYNOPSIS FOR ANTICIPATED ORDERS_Pool 1_5 Feb 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS Pool 2 28 January 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 22 JAN 2026.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 7 Jan 26.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 31 Dec 2025.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 31 Dec 2025.pdf PDF
SYNOPSIS FOR ANTICIPATED ORDERS 15 Dec 2025.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 6 - Instructions for BOA Application.docx DOCX document
Attachment 7 - Application Evaluation Procedures.docx DOCX document
SYNOPSIS FOR ANTICIPATED ORDERS.pdf PDF
Synopsis for Anticipated Orders - 22 May.pdf PDF
Synopsis for Anticipated Orders.pdf PDF
Consolidated RFI Responses.xlsx XLSX spreadsheet
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 4 - Application.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 1 - Travis Specification.zip ZIP file
Attachment 3 - Request for Information.xlsx XLSX spreadsheet
Attachment 5 - SF330.pdf PDF
Attachment 6 - Instructions for BOA Application.pdf PDF
Attachment 2 - Model Agreement.pdf PDF
Attachment 4 - Application.pdf PDF
Attachment 7 - Application Evaluation Procedures.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. General

1.1. These instructions cover the preparation of an application for the basic ordering agreement (BOA) at Travis AFB, CA. Questions and applications for Pool 1 shall be submitted to Lt Phillip Manwaring at phillip.manwaring@us.af.mil and Ms. Christina Johnson at christina.johnson.32@us.af.mil. Questions and applications for Pool 2 shall be submitted to Mr.

Brandon Spratt at brandon.spratt.2@us.af.mil. Applications for Pool 1: Minor Construction and Pool 2: Major Construction are open and may be submitted anytime between now and 15 May 2030.

2. Application Preparation

2.1. The applicant will utilize Attachment 4 - Application for the submission of all required documents. A completed application will cover the requirements for submission in para. 2.3. Pool 1:

Minor Construction Application Preparation. Failure to use the application form or submitting incomplete applications may result in rejection. The first step to applying is to have a System for Award Management (SAM) registration at SAM.gov. A company must have an active registration at the time of the submission in SAM.gov to be considered for a Construction BOA. All requirements will be submitted as a singular PDF in line with Attachment 4 - Application. A completed application will cover the requirements for submission in para. 2.4. Pool 2: Major Construction Application Preparation, as well as the submission of SF 330 in accordance with para. 2.4.4.

2.2. The application process for Pool 1: Minor Construction and Pool 2: Major Construction will close on 15 May 2030 14:30 PST. Submissions past this time and date will be ineligible for the award of an agreement.

2.3. Pool 1: Minor Construction Application Preparation

2.3.1. Cover Letter. The cover letter will be filled out to the best of the contractor’s ability. Cover letter template in Attachment 4 - Application shall be used. Failure to use the appropriate cover letter will result in automatic rejection.

2.3.2. Past Performance. The contractor will be required to submit a past performance questionnaire (PPQ) highlighting three (3) multi-disciplinary construction requirements the offeror has completed in the past three (3) years with the DoD or other federal agencies. PPQs shall be completed by the applicable agency and included in the application as required. If applicants do not have the minimum past performance required annotate “No relevant past experience”.

2.3.3. Bonding Capability. Applicants must provide bonding capabilities in the form of a letter from the applicant’s surety. The letter should demonstrate the contractors maximum bonding capability, per order.

mailto:phillip.manwaring@us.af.mil mailto:christina.johnson.32@us.af.mil mailto:brandon.spratt.2@us.af.mil

2.4. Pool 2: Major Construction Application Preparation

2.4.1. Cover Letter. The cover letter will be filled out to the best of the contractor’s ability. Cover letter template in Attachment 4 - Application shall be used. Failure to use the appropriate cover letter will result in automatic rejection.

2.4.2. Past Performance. The contractor will be required to submit a past performance questionnaire (PPQ) highlighting three (3) multi-disciplinary construction requirements the offeror has completed in the past three (3) years with the DoD or other federal agencies. PPQs shall be completed by the applicable agency and included in the application as required.

2.4.3. Bonding Capability. Applicants must provide bonding capabilities in the form of a letter from the applicant’s surety. The letter should demonstrate the contractors maximum bonding capability, per order.

2.4.4. SF 330 Architect/Engineering Capabilities. If you are applying for the Design Build Construction Pool, Complete the SF-330, Architect-Engineer Qualifications form (Attachment 7) and include it with your application. Section E is the key for this form in that there must be a separate Section E for each of the disciplines, (Architect, Civil, Mechanical, & Electrical).

1. General
2. Application Preparation
2.3. Pool 1: Minor Construction Application Preparation
2.4. Pool 2: Major Construction Application Preparation