CN-370000-CN214-T37CO2.pdf

PDF 5 MB Posted

Attached to
Master Agreement FL|CN214|9ee31443e44a9c909ef0ca196a4906cb
Contract number
CN214
Issued by
Florida

About this file

This is a Task Assignment Change Order Form (Change Order No. 02) issued by the Florida Department of Environmental Protection (FDEP) for contract CN214 involving the Florida Caverns State Park New Campground and Mountain Bike Trail project. The consultant is George & Associates Consulting Engineers, Inc., with project representation by Brian Miller, PE. The FDEP Contract Manager is Ralph Perkins. The change order was executed on May 19, 2023, with approvals from FDEP budget, project management, and contract authority representatives, as well as the consultant.

This deductive change order modifies cultural resource services work as requested by the Department of State Division of Historic Resources (DHR). Subtask 2b (Case Study Report), originally valued at $5,579.00, is being removed and replaced with Subtask 2d (Archaeological Impacts Summary), valued at $3,254.00. The net reduction to the overall contract is $2,325.00, bringing the total task amount from $82,361.97 to $80,036.97. The change involves removing work on a case study report that would have documented project alternatives and mitigation measures, and substituting it with an archaeological impacts summary letter report describing previously identified archaeological sites within the mountain bike trail footprint and recommending alignment modifications to avoid site impacts. Payment is contingent upon FDEP approval of deliverables for each subtask. The project execution date remains December 2, 2021, with the task end date extended to June 30, 2024.

View the file

Other files

File Type Posted
CN-370000-CN214-A1.pdf PDF
CN-370000-CN214-CMC1.pdf PDF
CN-370000-CN214-CMC3.pdf PDF
CN-370000-CN214-T12.pdf PDF
CN-370000-CN214-T15CO1.pdf PDF
CN-370000-CN214-T17.pdf PDF
CN-370000-CN214-T1CO2.pdf PDF
CN-370000-CN214-T2.pdf PDF
CN-370000-CN214-T21.pdf PDF
CN-370000-CN214-T24.pdf PDF
CN-370000-CN214-T30.pdf PDF
CN-370000-CN214-T30CO2.pdf PDF
CN-370000-CN214-T33.pdf PDF
CN-370000-CN214-T34.pdf PDF
CN-370000-CN214-T34CO1.pdf PDF
CN-370000-CN214-T35.pdf PDF
CN-370000-CN214-T37CO4.pdf PDF
CN-370000-CN214-T3CO1.pdf PDF
CN-370000-CN214-T40CO2.pdf PDF
CN-370000-CN214-T43CO1.pdf PDF
CN-370000-CN214-T46.pdf PDF
CN-370000-CN214-T49.pdf PDF
CN-370000-CN214-T4CO1.pdf PDF
CN-370000-CN214-T6.pdf PDF
CN-370000-CN214-T9.pdf PDF
CN-370000-CN214-TA23.pdf PDF
CN-370000-CN214.pdf PDF
PC-370000-CN214.pdf PDF
CN-370000-CN214-T10.pdf PDF
CN-370000-CN214-T15.pdf PDF
CN-370000-CN214-T15CO2.pdf PDF
CN-370000-CN214-T15CO3.pdf PDF
CN-370000-CN214-T19CO2.pdf PDF
CN-370000-CN214-T27.pdf PDF
CN-370000-CN214-T30CO1.pdf PDF
CN-370000-CN214-T30CO4.pdf PDF
CN-370000-CN214-T32.pdf PDF
CN-370000-CN214-T36CO1.pdf PDF
CN-370000-CN214-T36CO2.pdf PDF
CN-370000-CN214-T37.pdf PDF
CN-370000-CN214-T37CO3.pdf PDF
CN-370000-CN214-T38CO1.pdf PDF
CN-370000-CN214-T39CO1.pdf PDF
CN-370000-CN214-T40.pdf PDF
CN-370000-CN214-T40CO1.pdf PDF
CN-370000-CN214-T41CO1.pdf PDF
CN-370000-CN214-T43.pdf PDF
CN-370000-CN214-T43CO3.pdf PDF
CN-370000-CN214-T44.pdf PDF
CN-370000-CN214-T45.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN214 37 02 61351C

Florida Caverns State Park New Campground

George & Associates Consulting Engineers

Brian Miller, PE 850-521-0344 bmiller@gaceng.net

Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov

Deductive revision to align with Cultural Resource Services requested by the Department of State Division of Historic Resources (DHR) per the attached proposal dated May 19, 2023.

$ 1,070.00 $ 71,782.97 $ 72,852.97 $ 1,070.00 $ 81,291.97 $ 82,361.97

$ 0.00 -$ 2,325.00 -$ 2,325.00 $ 1,070.00 $ 78,966.97 $ 80,036.97

12/2/2021

6/30/2023

6/30/2024 n/a

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.05.19 15:42:23 -04'00'

Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.05.22 08:12:17 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.05.22 13:26:41 -04'00'

Brian Miller, PE Brian Miller Digitally signed by Brian Miller Date: 2023.05.23 08:45:37 -04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.05.26 12:51:40 -04'00'

61351C 37501000025 080039/22 423001 U3200 131500 QK -$ 2,325.00

-$ 2,325.00

1967 COMMONWEALTH LANE, SUITE 200 - TALLAHASSEE, FLORIDA 32303

PHONE 850-521-0344 - FAX 850-521-0345

www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION

May 19, 2023

Theresa Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399

RE: CN214 TA37, CO#2 (Revised): Florida Caverns State Park � New Campground + Mountain Bike Trail

For your review, George & Associates, Consulting Engineers, Inc. has prepared a revised fee proposal deductive change order for work related to the proposed cultural resource services for the Florida Caverns State Park � New Campground + Mountain Bike Trail. Previous tasks to be removed/voided are the case study report, Subtask 2b. Subtask 2d will take its place. Change Order #2 can be considered a deductive change order. These items will be required to comply with Florida State Laws regarding the preservation of cultural resources.

Sincerely, Brian Miller, P.E.

George & Associates, Consulting Engineers, Inc.

Florida Caverns State Park New Campground & Mountain Bike Trail

CN214 TA37 CO#2

Subtask 2b: Case Study Report Description: PaleoWest will prepare a Case Study Report, should it be identified as required documentation following the DHR coordination. The purpose of the Case Study Report is to:

1) Summarize efforts to develop project alternatives or modifications to the undertaking that could avoid, minimize, or mitigate adverse effects;

2) Evaluate the effects of the preferred alternative on historic properties;

3) Document public and agency coordination efforts to date; and

4) Propose potential mitigation measures to resolve adverse effects.

Deliverable:

Case Study Report, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost Subtask 2b: Case Study Report

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

George & Associates Project Manager $129.00 6 $774.00

PaleoWest Principal in Charge $135.00 33 $4,455.00 PaleoWest GIS Specialist $65.00 4 $260.00 PaleoWest Administrative Assistant $60.00 1.5 $90.00

Fixed Price Total Cost: $5,579.00 Total for Subtask 2B: $5,579.00

Subtask 2d: Archaeological Impacts Summary Description: As requested by DHR, PaleoWest will prepare a summary of the archaeological impacts of the proposed mountain bike trail. The summary will describe the archaeological sites that have been previously identified within the proposed trail footprint and recommend measures to avoid impacts to the sites via the revised mountain bike trail alignment.

Archaeological Impacts Summary letter report, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost Subtask 2d: Archaeological Impacts Summary

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

George & Associates Project Manager $129.00 6 $774.00

PaleoWest Principal in Charge $135.00 16 $2,160.00

PaleoWest GIS Specialist $65.00 4 $260.00

PaleoWest Administrative Assistant $60.00 1 $60.00

Fixed Price Total Cost: $3,254.00 Total for Subtask 2d: $3,254.00

Summary of Fees:

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 2b: Case Study Report ($5,579.00) Subtask 2d: Archaeological Impacts Summary $3,254.00

Reduction to the Overall Total Cost: $2,325.00

Overall Total Cost (Subtasks 2a, 2c & 2d): $7,184.00

Project Schedule:

Activity Duration (calendar days)

Dates

Subtask 2b: Case Study Report 40* Upon DHR

Coordination

Subtask 2d: Archaeological Impacts Summary 21* Upon execution

* Assumes agency responsiveness (DHR). Includes review and comment phase by BDC between draft and final document. 10 days are required to complete final document starting from time of draft comments received.

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

-($2325.00)Deductive fee change