This document is Section F (Deliveries or Performance) from RFP #368624 for a SLAC Job Order Contract, establishing the period of performance for construction job order services at SLAC National Accelerator Laboratory, operated by Stanford University for the U.S. Department of Energy.

The contract structure includes one base period and four option periods, each lasting 12 months. Line 01 represents the base period, commencing upon fully executed award and extending for 12 months post-award. Lines 02 through 05 represent optional renewal periods (Options 1-4), each scheduled to begin upon completion of the preceding period and extend for an additional 12 months, contingent upon SLAC's exercise of the options. All four option periods are currently marked as "NOT EXERCISED." Each line item covers construction job orders performed in accordance with the subcontract terms and conditions outlined in Section C Statement of Work. The document does not specify pricing terms, set-asides, or detailed service requirements, as those elements are addressed in other sections of the RFP.

View the file

Other files

File Type Posted
B2_DRAFT_03.2_Section_C_Construction_Task_Catalog_INCORPORATED_BY_REFERENCE.pdf PDF
B2_DRAFT_03.7_Section_C_Appendix F_SLAC_Landscape_Vegetation_Planting_Guidance.pdf PDF
B2_DRAFT_03.9_Section_C_Appendix H_SLAC_Drawing_Deliverables.pdf PDF
B2_DRAFT_08.3_Sec_J_SF1413_exp_05-2027.pdf PDF
B2_DRAFT_08.4_Subcontractor_Safety_Qualification_Form.pdf PDF
B2_DRAFT_10.2_Section_L_Attachment_B_(Bid_Form).pdf PDF
B2_DRAFT_03.1_Section_C_Statement_of_Work_JOC.pdf PDF
B2_DRAFT_03.3_Section_C_Appendix_B_SLAC_Electrical_Design_Standards.pdf PDF
B2_DRAFT_03.4_Section_C_AppendixC_SLAC_Design_Procedures_Sewer_Services.pdf PDF
B2_DRAFT_03.5_Section_C_Appendix_D_SLAC_Design_Procedures_Water_Services.pdf PDF
B2_DRAFT_03.6_Section_C_Appendix E_SLAC_Space_Standards.pdf PDF
B2_DRAFT_03.11_Section_C_Appendix J_DOE-STD-1066-2023.pdf PDF
B2_DRAFT_08.1_Sec_J_DBA_WD_CA20260018_09172026_Mod_08.pdf PDF
B2_DRAFT_08.2_Sec_J_Subcontractor_IIPP_Form.pdf PDF
B2_DRAFT_08.6_Final_Inspection_Report.pdf PDF
B2_DRAFT_01_RFP_Section_A_(Subcontract_Form).pdf PDF
B2_DRAFT_03.0_RFP_Section_C_SOW_Cover_JOC.pdf PDF
B2_DRAFT_03.10_Section_C_Appendix_I_INCORPORATED_BY_REFERENCE.pdf PDF
B2_DRAFT_05.0_RFP_Section_G_(General_TsCs).pdf PDF
B2_DRAFT_05.2_SLAC_General_Ts_Cs_Supplemental_Rider_Aug2026.pdf PDF
B2_DRAFT_07_RFP_Section_H_(Special_Terms_Conditions).pdf PDF
B2_DRAFT_08.0_RFP_Section_J_Cover.pdf PDF
B2_DRAFT_08.5_NTP_Submittal_Checklist.pdf PDF
B2_DRAFT_09.0_RFP_Section_K_(Rep_and_Certs_Cover).pdf PDF
B2_DRAFT_09.1_RFP_Section_K_Reps_and_Certs_Supplement_08.25.22.pdf PDF
B2_DRAFT_10.0_RFP_Section_L_(Instructions_to_Offerors).pdf PDF
B2_DRAFT_10.1_Section_L_Attachment_A_(Past_Performance).pdf PDF
B2_DRAFT_10.3_Section_L_Attachment_C_(Q&A_Log).pdf PDF
B2_DRAFT_00_RFP_Cover_Letter_JOC.pdf PDF
B2_DRAFT_02_RFP_Section_B_(Supplies or Services and Price_Costs).pdf PDF
B2_DRAFT_03.8_Section_C_Appendix G_SLAC_Seismic_Design_Specifications.pdf PDF
B2_DRAFT_05.1_Fixed_Price_Construction_March2024.pdf PDF
B2_DRAFT_08.7_Final_Release.pdf PDF
B2_DRAFT_11_RFP_Section_M_(Evaluation_Factors).pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLAC NATIONAL ACCELERATOR LABORATORY • 2575 SAND HILL ROAD • MENLO PARK • CALIFORNIA • 94025 • USA

Operated by Stanford University for the U.S. Department of Energy

SECTION F (REV. 06/04/12) SLAC-SCM-GEN-032 PAGE 1 OF 1

SUPPLY CHAIN MANAGEMENT

Section F – Deliveries or Performance

RFP # 368624 SLAC Job Order Contract

Period of Performance

Line Description From To

Per each Construction Job Order, in accordance with the terms and conditions of this Subcontract and Section C Statement of Work, for a Base Period of 12 months

Fully Executed Award 12 Months Post Award

OPTION 1 Job Order in accordance with the terms and conditions of this agreement

– 12 months after completion of Item 01

NOT EXCERCISED

End of Period of Performance of Line 01

12 Months Post from the beginning of Line 01

Period of Performance

OPTION 2 Job Order in accordance with the terms and conditions of this agreement

– 12 months after completion of Item 02

NOT EXCERCISED

End of Period of Performance of Line 01

12 Months Post from the beginning of Line 02

Period of Performance

OPTION 3 Job Order in accordance with the terms and conditions of this agreement

– 12 months after completion of Item 03

NOT EXCERCISED

End of Period of Performance of Line 01

12 Months Post from the beginning of Line 03

Period of Performance

OPTION 4 Job Order in accordance with the terms and conditions of this agreement – 12 months after completion of Item 04

NOT EXCERCISED

End of Period of Performance of Line 01

12 Months Post from the beginning of Line 04

Period of Performance