Attachment D is a Construction Experience Project Data Sheet template for federal contract opportunity 36C26125R0008, designed to capture detailed information about an offeror's previous construction projects. The form requires contractors to provide comprehensive project details including contract type, award dates, project scope, customer information, and a detailed description demonstrating project relevance to the current solicitation requirements.

The template is structured to collect critical information across nine sections, including contractor identification, contract specifics, project type (new construction, renovation, or repair), project description, and percentage of self-performed work. Contractors are instructed to submit between three and five projects within the solicitation's project description parameters, with space to explain the firm's role, project characteristics, and meaningful involvement in the proposed contract. This form serves as a key evaluation tool for assessing a contractor's experience and qualifications for the federal contract opportunity.

View the file

Other files

File Type Posted
36C26125R0008 0005.docx DOCX document
Attach Amend 0005 RFI BID Responses.pdf PDF
ATTCH 5 - 38_AE152_FINISH FLOOR PLAN -TEMPORARY BUILDINGS.pdf PDF
ATTACH 3 GeoTech Report 02.02.21.pdf PDF
Attach 1 Amend 0004 SPS - Pre-Bid RFI Responses.pdf PDF
36C26125R0008 0004.docx DOCX document
ATTACH 6 No. 81 - CS106.pdf PDF
ATTACH 4 SECTION 27 51 16 PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS.pdf PDF
Attach 2 - 23 09 23 Direct-Digital Control System for HVAC.pdf PDF
ATTACH 7 - Construction Experience Project Data Sheet.rtf RTF text file
1795.07 - Basement Div. 12 Specifications.pdf PDF
36C26125R0008 0003.docx DOCX document
SIte Visit 12 June 2025 Sign in Roster.pdf PDF
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION DEVIATION.docx DOCX document
36C26125R0008 0002.docx DOCX document
Temporary SPS_640-23-108_Bid Document Specifications.pdf PDF
DRAWINGS - TEMPORARY SPS_Part2.pdf PDF
DRAWINGS - BASEMENT SPS_Part3.pdf PDF
DRAWINGS - TEMPORARY SPS_Part5.pdf PDF
DRAWINGS - BASEMENT SPS_Part5.pdf PDF
36C26125R0008 0001.docx DOCX document
DRAWINGS - TEMPORARY SPS_Part4.pdf PDF
DRAWINGS - TEMPORARY SPS_Part1.pdf PDF
DRAWINGS - BASEMENT SPS_Part6.pdf PDF
DRAWINGS - BASEMENT SPS_Part4.pdf PDF
Basement_640-23-108_Bid Document Specifications.pdf PDF
DRAWINGS - TEMPORARY SPS_Part3.pdf PDF
DRAWINGS - BASEMENT SPS_Part2.pdf PDF
DRAWINGS - BASEMENT SPS_Part1.pdf PDF
ATTACHMENT AA SPS - Specifications.pdf PDF
ATTACH CC PART 1.pdf PDF
ATTACH CC PART 2.pdf PDF
ATTACH BB DRAWINGS PART 1.pdf PDF
ATTACH BB DRAWINGS Part 2.pdf PDF
ATTACH DD SPS SWING SPACE.pdf PDF
36C26125R0008.docx DOCX document
ATTACHMENT AA SPS - Specifications.pdf PDF
Attachment G - Supplemental Price Breakdown.xlsx XLSX spreadsheet
Attachment F - Client Authorization Letter.docx DOCX document
Attachment C - Key Personnel Evaluation.docx DOCX document
ATTACH DD SPS - Swing Space Drawings.pdf PDF
ATTACH CC SPS - Drawings_Part2.pdf PDF
ATTACH BB - SPS - Drawings_Part1.pdf PDF
Attachment A - Request for Information.docx DOCX document
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION.docx DOCX document
Attachment H Wage Determination CA20250018 Dtd 3.21.25.pdf PDF
Attachment E - Past Performance Questionnaire.docx DOCX document
Attachment B - EMR Sheet.docx DOCX document
36C26125R0008.docx DOCX document
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT D

CONSTRUCTION EXPERIENCE PROJECT DATA SHEET – OFFEROR

This form is to be completed by the Offeror. Submit (one per project) in order to provide supporting project information for Factor 2, Experience. Only projects that are within the project description parameters of the solicitation will be considered relevant. Submit no less than three (3) and no more than (5) projects.

Project No. (check one): - 1 - 2 - 3 - 4 - 5 Contractor:

1. Offeror Name:

Firm who performed the work:

Performed this work as: Prime Contractor Subcontractor Joint Venture Other (explain):

If subcontractor, name of prime: Phone #:

If the firm who performed this project differs from the Offeror proposing on this contract, identify the firm’s relationship to the Offeror:

Joint Venture Partner Partner Subcontractor Parent Company

Subsidiary Satellite Office Predecessor Company Other:

Explain how this firm will have meaningful involvement in the performance of the contract:

Construction Contract:

2. Contract/Project No.: Delivery/Task Order Number:

Title:

Location:

3. Award Date (mm/dd/yy): Award Amount: $

Completion Date (mm/dd/yy): Final Price: $

This is the: total project subcontract price

4. Type of Contract: Design-Build. If D-B, design firm was:

(check one) Design-Bid-Build

Customer:

5. Name:

Point of Contact Name/Title:

POC Phone Number: POC Email Address:

Project Description:

6. Type of Work (check all that apply): New Construction Renovation Repair

7. Provide a detailed description of the project and the relevancy to the project requirements of this RFP:

36C26125R0008

8. If project is design-build, provide a detailed description of the design effort:

9. Percentage of work your firm self-performed (see definition): % Provide a detailed description of the work your firm self-performed on this project.

Note: Form may be expanded.

Exhibit “B” – PPQ, Page 1 of 4 (Rev 12/11)

EXHIBIT “B”

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO NAVFAC WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON NAVFAC SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO NAVFAC. PLEASE CONTACT THE OFFEROR FOR NAVFAC POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO

VERIFY ANY AND ALL INFORMATION ON THIS FORM.

Exhibit “B” – PPQ, Page 2 of 4

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.

Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been NO significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.

There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.

Exhibit “B” – PPQ, Page 3 of 4

Contractor Information (Firm Name): ________________________________________________ Client Information (Name): ________________________________________________________

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N

3. CUSTOMER SATISFACTION

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s) E VG S M U N

Exhibit “B” – PPQ, Page 4 of 4

Contractor Information (Firm Name): ________________________________________________ Client Information (Name): ________________________________________________________

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client. E VG S M U N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns).

E VG S M U N

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes No

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the user’s rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

E VG S M U N

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

E VG S M U N

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes No

d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

EXHIBIT “C”

OFFEROR TEAM COMPOSITION AND MANAGEMENT

N40080-20-R-5255 Use this form to provide information regarding the primary members, composition, and management of the proposed team for

Subfactor 4, TECHNICAL QUALIFIATIONS OF PROPOSED STAFFING. If Offeror is a partnership (e.g., JV, Mentor-Protégé), list each partner as a separate team member. If the experience of an entity is being claimed in Factor 2, that entity must be identified and described on this Exhibit. Modify form as necessary to include all primary construction and primary design team members. PLEASE

NOTE – “TEAM MEMBER” MEANS A COMPANY, LLC, ETC., NOT AN INDIVIDUAL PERSON. Do not include information for individuals. Do not exceed two (2) pages. IF YOUR PROPOSAL IS BASED ON 100% IN-HOUSE LABOR (I.E. NO

SUBCONTRACTORS OR CONSULTANTS), WRITE “NOT APPLICABLE.”

Team Member 1 Name: Location: DUNS:

Contractual relationship to the team:

Describe team member role, responsibilities, and meaningful involvement in performance of the contract:

If located outside of Virginia, explain how entity will have meaningful involvement from a remote location.

Team Member 2 Name: Location: DUNS:

Contractual relationship to the team:

Describe team member role, responsibilities, and meaningful involvement in performance of the contract:

If located outside of Virginia, explain how entity will have meaningful involvement from a remote location.

Team Member 3 Name: Location: DUNS:

Contractual relationship to the team:

Describe team member role, responsibilities, and meaningful involvement in performance of the contract:

If located outside of Virginia, explain how entity will have meaningful involvement from a remote location.

Team Member 4 Name: Location: DUNS:

Contractual relationship to the team:

Describe team member role, responsibilities, and meaningful involvement in performance of the contract:

If located outside of Virginia, explain how entity will have meaningful involvement from a remote location.

Team Member 5 Name: Location: DUNS:

Contractual relationship to the team:

Describe team member role, responsibilities, and meaningful involvement in performance of the contract:

If located outside of Virginia, explain how entity will have meaningful involvement from a remote location.

Discuss the rationale for proposing this team arrangement:

EXHIBIT “D”

SAFETY DATA SHEET

N40080-20-R-5255 This form is to be completed by the Offeror. Use this form to provide safety information for the Safety factor. EMR, DART and TRC rates shall not be submitted for subcontractors.

Joint Venture (JV) or Partnership: Complete Blocks 1 through 8 for each contractor who is part of the JV or partnership. Only one safety narrative (Block 9) is required.

1. Offeror Name:

Name of JV partner providing the information below (if applicable):

Offeror’s Three Previous Complete Calendar Years of Reported Safety Data:

Only complete year safety data will be considered. Indicate data rates as decimal figures, not whole numbers.

2. Experience Modification Rate (EMR): 2017 2018 2019

3a. For EMRs greater than 1.0, explain any extenuating circumstances and corrective actions taken:

3b. Explain any negative EMR trends:

3c. If you do not have an EMR for a given year, state so here and explain why:

4. Insurance Carrier Information:

Insurance Carrier Name:

Agent’s name: Phone No.: Email:

5. U.S. Dept. of Labor, OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate

2017 2018 2019

Instructions for calculating the DART rate can be found at http://www.bls.gov/iif/osheval.htm.

6a. For DART Rates of 3.0 or greater, explain any extenuating circumstances and corrective actions taken:

6b. Explain any negative DART Rate trends:

6c. If you do not have a DART Rate for a given year, state so here and explain why:

EXHIBIT “D” (continuation)

SAFETY NARRATIVE

N40080-20-R-5255

7. U.S. Dept. of Labor, OSHA Total Recordable Case (TRC) Rate

2017 2018 2019

Instructions for calculating the TRC rate can be found at http://www.bls.gov/iif/osheval.htm.

8a. For TRC Rates of 4.5 or greater, explain any extenuating circumstances and corrective actions taken:

8b. Explain any negative TRC Rate trends:

8c. If you do not have a TRC Rate for a given year, state so here and explain why:

N40080-20-R-5255

9. Technical Approach for Safety: Provide the Safety Narrative using this form. Do not exceed page limitation specified in the RFP. Any additional pages will not be considered.

Describe the plan that the Offeror will implement to evaluate safety performance of potential subcontractors, as a part of the selection process for all levels of subcontractors:

Describe the safety management system that the Offeror will use to oversee the safety compliance and performance of self-performed and subcontractor performed work:

Note: Form may be expanded up to the page limit specified in the RFP.

N40080-20-R-5255

9. Technical Approach for Safety (continuation): Provide the Safety Narrative using this form. Do not exceed page limitation specified in the RFP. Any additional pages will not be considered.

Describe any innovative methods that the Offeror will employ to ensure and monitor safe work practices at self-performed/and or all subcontractor levels:

Describe the methodology that the Offeror will use in order to execute an effective program that facilitates sound mishap prevention techniques and processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps:

REQUEST FOR INFORMATION (RFI)

N40080-20-R-5255

The Government does not intend to respond to inquiries submitted after the RFI due date shown in the solicitation. Please submit questions to Deidre Parker by email at deidre.parker@navy.mil.

Firm Name:

POC:

Address:

Phone Number:

Email Address:

QUESTION IS REGARDING:

Section of the RFP:

Paragraph:

Page Number:

QUESTION:

File details come from the government source that posted it. Updated .