ATTACH BB DRAWINGS PART 1.pdf
PDF 18 MB Posted
- Solicitation number
- 36C26125R0008
About this file
This document is a set of architectural and engineering drawings for the renovation and expansion of the Sterile Processing Service (SPS) at the VA Palo Alto Healthcare System. The project involves a comprehensive renovation of approximately 18,486 square feet in the basement of Building 100, with the goal of modernizing the SPS to meet VA Design Guide requirements and improve functional workflows.
The project is divided into five phases spanning 720 calendar days, including preparation of a temporary modular SPS and swing space, demolition of the existing SPS, construction of a new SPS, and activation of the new space. Key project constraints include maintaining hospital operations, adhering to infection control measures, and coordinating utility shutdowns. The renovation will create separate spaces for Sterile Processing Service (SPS) and Supply Chain Service (SCS), with a focus on unidirectional workflow, controlled access, and compliance with healthcare standards. The project is part of the VA Palo Alto Healthcare System's efforts to improve medical device processing and supply chain efficiency.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N
LOCATION MAP
N
AREA MAP
PROJECT LOCATION
BLDG 100
FOOTHILL EXPRESSWAY
LO
O
P R
O A
D th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS:
Drawing #
U.S. DEPARTMENT OF VETERANS AFFAIRS
Revision: Date:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
FULLY SPRINKLERED
APPROVED: DIRECTOR
APPROVED: ASSOCIATE DIRECTOR
APPROVED: CHIEF OF STAFF
SHEET TITLE
APPROVED: CHIEF ENGINEERINGAPPROVED: ASSISTANT DIRECTOR
STRUCTURAL ENGINEER
GREGORY P. LUTH & ASSOCIATES
3350 SCOTT BOULEVARD, BLDG. 48
SANTA CLARA, CA 95054
(408) 654-0475
MEP / TECHNICAL ENGINEER
SPUR DESIGN
2519 MADISON AVE. STE 100
KANSAS CITY, MO 64108
(913) 369-7200
FIRE PROTECTION ENGINEER
POOLE FIRE PROTECTION, INC.
19910 WEST 161ST STREET
OLATHE, KANSAS 66062
(913) 829-8690
MEDICAL EQUIPMENT PLANNING
INNOVA GROUP
3196 NORTH SWAN ROAD
TUCSON, AZ 85712
(520) 886-8650
CIVIL ENGINEER
KEIR & WRIGHT
3350 SCOTT BLVD, BLDG22
SANTA CLARA, CA 95051
(405) 727-6665
PHYSICAL SECURITY
FORCE PROTECT SECURITY CONSULTANTS
10901 FRONT BEACH RD, STE 1415
PANAMA CITY BEACH, FL 32407
(502) 836-4232
ARCH. REG. NO. C38975
ENGR. REG. NO. M39910
EXPIRES: 05/31/2023
EXPIRES: 06/30/2024
SPUR #: 1795.07
/2
/2
:0
:4
A
M
G-000
COVER SHEET
ECO
B100
BGJ
FINAL BID DOCUMENTS
RENOVATION AND EXPANSION OF SPS
VA PROJECT NUMBER: 640-23-108
RENOVATION AND EXPANSION
OF SPS
03/03/2023
640-23-108
VA PALO ALTO HEALTHCARE SYSTEM
3801 MIRANDA AVENUE
PALO ALTO, CA 94304
VA PALO ALTO HEALTHCARE SYSTEM
3801 MIRANDA AVENUE
PALO ALTO, CA 94304
FINAL BID DOCUMENTS
SHEET INDEX
SEQUENCE NUMBER SHEET NAME
[10] PLUMBING
60 P-000 PLUMBING LEGEND
61 PD-100 PLUMBING WASTE/VENT DEMOLITION FLOOR PLAN - BASEMENT SPS
62 PD-101 PLUMBING SUPPLY DEMOLITION FLOOR PLAN - BASEMENT SPS
63 PD-102 PLUMBING MEDICAL GAS DEMOLITION FLOOR PLAN - BASEMENT SPS
64 PS-100 PLUMBING SITE PLAN - TEMPORARY SPS
65 PL-100 PLUMBING WASTE/VENT NEW WORK FLOOR PLAN - BASEMENT SPS
66 PP-100 PLUMBING SUPPLY NEW WORK FLOOR PLAN - BASEMENT SPS
67 PP-101 PLUMBING SUPPLY NEW WORK FLOOR PLAN - BASEMENT SPS
68 PJ-100 PLUMBING MEDICAL GAS NEW WORK FLOOR PLAN - BASEMENT SPS
69 P-301 PLUMBING WASTE AND VENT ISOMETRIC
70 P-302 PLUMBING SUPPLY ISOMETRIC
71 P-303 PLUMBING ISOMETRICS
72 P-401 PLUMBING PARTIAL PLANS
73 P-402 MODULAR BUILDING PLUMBING PLAN
74 P-501 PLUMBING DETAILS
75 P-601 PLUMBING SCHEDULES
[12] MECHANICAL
76 M-000 LEGEND AND ABBREVIATIONS
77 MD-100 MECHANICAL PIPING DEMOLITION FLOOR PLAN - BASEMENT SPS
78 MD-101 MECHANICAL HVAC DEMOLITION FLOOR PLAN - BASEMENT SPS
79 MD-105 MECHANICAL HVAC DEMOLITION ROOF PLAN
80 MP-100 MECHANICAL PIPING NEW WORK FLOOR PLAN - BASEMENT SPS
81 MH-100 MECHANICAL HVAC NEW WORK FLOOR PLAN - BASEMENT SPS
82 MH-101 MECHANICAL HVAC NEW WORK FLOOR PLAN - MODULAR BUILDING
83 MH-105 MECHANICAL HVAC NEW WORK - ROOF PLAN
84 M-201 MECHANICAL FLOW DIAGRAMS
85 M-202 MECHANICAL AIRFLOW PLAN
86 M-301 MECHANICAL SECTIONS
87 M-401 MECHANICAL ENLARGED PLANS
88 M-501 MECHANICAL DETAILS
89 M-502 MECHANICAL DETAILS
90 M-601 MECHANICAL SCHEDULES
91 M-701 MECHANICAL CONTROLS
92 M-702 MECHANICAL CONTROLS
93 M-703 MECHANICAL CONTROLS
94 M-704 MECHANICAL CONTROLS
[13] ELECTRICAL
95 E-000 ELECTRICAL LEGEND
96 ES-101 ELECTRICAL SITE PLAN - TEMPORARY SPS
97 ES-401 MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS
98 ES-601 MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES
99 ED-100 ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN
100 ED-200 ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN
101 ED-205 ELECTRICAL POWER DEMOLITION ROOF PLAN
102 EL-100 ELECTRICAL LIGHTING BASEMENT FLOOR PLAN
103 EP-100 ELECTRICAL POWER BASEMENT FLOOR PLAN
104 EP-101 ELECTRICAL POWER FIRST FLOOR PLAN
105 EQ-100 SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN
106 EQ-105 SPS MECHANICAL EQUIPMENT POWER ROOF PLAN
107 E-401 ENLARGED ELECTRICAL FLOOR PLANS
108 E-501 ELECTRICAL DETAILS
109 E-601 ELECTRICAL ONE-LINE DIAGRAM
110 E-602 ELECTRICAL SCHEDULES
111 E-603 PANELBOARD SCHEDULES
[14] TECHNOLOGY
112 T-000 TECHNOLOGY LEGEND
113 TD-100 TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN
114 TN-100 TECHNOLOGY BASEMENT FLOOR PLAN
115 TI-100 PUBLIC ADDRESS BASEMENT FLOOR PLAN
116 TY-100 SECURITY BASEMENT FLOOR PLAN
117 T-401 ENLARGED TECHNOLOGY FLOOR PLANS
118 T-501 TECHNOLOGY DETAILS
119 T-601 TECHNOLOGY SCHEDULES AND RISER DIAGRAMS
TOTAL SHEETS: 119
SHEET INDEX
SEQUENCE NUMBER SHEET NAME
[01] GENERAL
01 G-000 COVER SHEET
02 GI001 GENERAL INFORMATION
03 GI002 RENDERINGS
04 GI011 BASEMENT LIFE SAFETY PLAN
05 GI012 INTERIM BASEMENT LIFE SAFETY PLAN
[05] CIVIL
06 C-001 COVER SHEET
07 CD-001 DEMOLITION PLAN
08 CS-001 DETAILS
09 CS-002 TOPOGRAPHIC SURVEY
10 CS-003 SITE IMPROVEMENT PLAN
11 CS-004 HYDRANT COVERAGE DIAGRAM
12 CG-001 EROSION CONTROL PLAN
[07] STRUCTURAL
13 SG-001 GENERAL NOTES
14 SG-002 SHEET LIST, LEGEND & ABBREVIATIONS
15 SG-101 BASEMENT EQUIPMENT PAD PLAN
16 SG-141 ROOF PLAN
17 SG-150 MODULAR UNIT FOUNDATION PLAN
18 SG-501 TYPICAL DETAILS
19 SG-502 MEP CONNECTION DETAILS
[08] ARCHITECTURAL
20 AD-001 SITE DEMOLITION PLAN
21 AD-002 SITE DEMOLITION PLAN - TEMPORARY MODULAR BUILDING AND SPS TRAILERS
22 AD-100 BASEMENT DEMOLITION FLOOR PLAN
23 AD-101 BASEMENT DEMOLITION RELECTED CEILING PLAN
24 AD-102 ROOF DEMOLITION PLAN
25 AS-001 ARCHITECTURAL SITE PLAN
26 AS-002 TEMPORARY MODULAR BUILDING SITE PLAN
27 AE-001 PARTITION TYPES
28 AE-101 OVERALL BASEMENT PLAN
29 AE-102 BASEMENT REFERENCE PLAN
30 AE-103 BASEMENT DIMENSION PLAN
31 AE-140 OVERALL ROOF PLAN
32 AE-141 ROOF PLAN
33 AE-150 MODULAR BUILDING - FLOOR PLANS
34 AE-151 MODULAR BUILDING - SIGNAGE PLAN
35 AE-250 MODULAR BUILDING - EXTERIOR ELEVATIONS AND SECTIONS
36 AE-350 MODULAR BUILDING - ENLARGED PLANS & INTERIOR ELEVATIONS
37 AE-401 ENLARGED PLANS
38 AE-501 CEILING DETAILS
39 AE-511 PLAN AND SECTION DETAILS
40 AE-601 DOOR SCHEDULE & WINDOW TYPES
41 AF-701 FLOOR FINISH PLAN
42 AF-711 FINISH SCHEDULE
43 AF-901 MILLWORK
44 AC-130 BASEMENT REFLECTED CEILING REFERENCE PLAN
45 AC-131 BASEMENT REFLECTED CEILING DIMENSION PLAN
46 AQ-801 BASEMENT EQUIPMENT PLAN
47 AQ-802 ENLARGED EQUIPMENT PLANS & INTERIOR ELEVATIONS
48 AQ-803 ENLARGED EQUIPMENT PLANS & INTERIOR ELEVATIONS
49 AQ-804 ENLARGED EQUIPMENT PLANS & INTERIOR ELEVATIONS
50 AQ-805 ENLARGED EQUIPMENT PLANS & INTERIOR ELEVATIONS
51 AQ-806 ENLARGED EQUIPMENT PLANS & INTERIOR ELEVATIONS
52 AQ-807 ENLARGED EQUIPMENT PLANS & INTERIOR ELEVATIONS
53 AQ-808 BASEMENT SIGNAGE
[09] FIRE PROTECTION
54 FA-001 FIRE ALARM GENERAL DIAGRAMS, LEGENDS, AND NOTES
55 FA-101 FIRE ALARM AUDIBILITY FLOOR PLAN
56 FA-102 FIRE ALARM FLOOR PLAN
57 FA-110 FIRE ALARM PLAN, NOTES, LEGEND, AND DIAGRAMS - MODULAR BUILDING
58 FX-101 FIRE SUPPRESSION GENERAL NOTES AND HAZARD CLASSIFICATION FLOOR PLAN
59 FX-110 FIRE SUPPRESSION PLAN, NOTES, LEGEND, AND DIAGRAMS - MODULAR BUILDING
ABBREVIATIONS CODES STANDARDS AND EXECUTIVE ORDERS
4' -0
M
A X
4' -0
M
A X
2' -1
0" M
A X
2' -3
M
IN
1'-6" MIN
1. GENERAL CONTRACTOR TO PROVIDE METAL SUPPORT BLOCKING
FOR ALL WALL MOUNTED ACCESSORIES, FIXTURES, AND EQUIPMENT.
SUPPORT BRACKETS TO BE PLACED AT ALL OPEN COUNTERTOPS -
18"-24" ON CENTER.
2. SPECIFIED MAXIMUMS ARE MEASURED FROM AFTER FINISHED
FLOOR TO THE OPERABLE PART OF THE FIXTURE.
3. FIXTURES SHOWN ARE REPRESENTATIONAL ONLY. NOT ALL
FIXTURES MAY BE USED. REFER TO SPECIFICATIONS FOR FIXTURE
TYPES USED IN THIS PROJECT.
4. FIXTURES MAY OVERLAP WAINSCOT. WHERE APPLICABLE, BACKING
TO BE PROVIDED AS SHIM FOR FLUSH APPLICATION. SHIM TO MATCH
SCHEDULED WALL FINISH.
6" MAX
9" M
IN
SHOWER
TOILET ROOM TURNING
RADIUS
DRINKING
FOUNTAINPAPER TOWEL
DISPENSER
SANITARY
NAPKIN
DISPENSER
4' -0
M
A X
WASTE
RECEPTACLE
LAVATORY
WITH MIRROR
ON CENTER
WALL
4' -0
M
A X
SOAP
DISPENSER
2' -1
0" M
A X
3' -4
M
A X
17 MIN
2' -4
/4
M
IN
3' -0
M
A X
1'-5 1/2" MIN
WALL
3' -0
M
A X
4' -0
M
A X
1'-6" MIN
7 1/2" MIN
WALL
LAVATORY
WITH APRON
1' -5
M
A X
1'-6" MIN
URINAL
WALL
1'-6"
CLEAR FLOOR
5'-0"
CLEAR FLOOR
4'-8"
3'-0" MIN
2' -9
1'-0"
3'-6" MIN 1'-0"
4'-6" MIN
1' -5
1' -7
M
IN
2' -9
WALLWALL
4' -0
/4
M
A X
WALL HOOK
7' -6
CLOCK
WALL
FFE
4' -0
M
A X
4' -0
M
A X
TOILET SEAT
COVER
DISPENSER
BABY
CHANGING
STATION
CLEAR FLOOR SPACE
@ WATER CLOSET
60"
W A
LL
H
U N
G W
.C
*5 6"
30"
30"
HANDRAILS AND
BUMPERGUARDS
FIXTURE MOUNTING HEIGHTS AND CLEARANCES
18" MIN
M
IN
FRONT APPROACH,
PULL SIDE
36" MIN
M
IN
HINGE APPROACH,
PULL SIDE
HINGE APPROACH,
PULL SIDE
*12" MIN
M
IN
FRONT APPROACH,
PUSH SIDE
*4 2"
M
IN
HINGE APPROACH,
PUSH SIDE
22" MIN 24" MIN
*4 8"
M
IN
LATCH APPROACH,
PULL SIDE
24" MIN*4
2"
M
IN
LATCH APPROACH,
PUSH SIDE
*IF BOTH CLOSER
AND LATCH ARE
PROVIDED
*54" MIN IF CLOSER
IS PROVIDED
*48" IF CLOSER IS
PROVIDED
FRONT APPROACH,
PUSH SIDE
M
IN
42" MIN
M
IN
DOOR AND FIXTURE CLEARANCES
MATERIALS LEGEND
PURPOSE: THE PUBLIC BUILDINGS AMENDMENT ACT OF 1988, PUBLIC LAW (PUB. L.) 100-678 REQUIRES FEDERAL AGENCIES TO FOLLOW NATIONAL RECOGNIZED "MODEL" BUILDING CODES. THE FEDERAL PARTICIPATION IN THE DEVELOPMENT AND USE OF VOLUNTARY STANDARDS, OFFICE OF MANAGEMENT AND BUDGET (OMB) CIRCULAR A-119, REQUIRES ALL EXECUTIVE AGENCIES TO RELY ON VOLUNTARY STANDARDS, BOTH DOMESTIC AND INTERNATIONAL, WHENEVER
FEASIBLE, AND TO PARTICIPATE IN VOLUNTARY STANDARD BODIES.
GENERAL: VA HAS ADOPTED THE LATEST EDITION OF THE FOLLOWING CODES AND STANDARDS AS A MINIMUM FOR ALL PROJECTS PERFORMED IN THE MODERNIZATION, ALTERATION, ADDITION, OR IMPROVEMENT OF ITS REAL PROPERTY AND THE CONSTRUCTION OF NEW STRUCTURES. VA DESIGN MANUALS AND MASTER SPECIFICATIONS SPECIFY OTHER CODES AND STANDARDS THAT VA FOLLOWS ON ITS PROJECTS:
• VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL
INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/).
• 2018 INTERNATIONAL BUILDING CODE (IBC) (ONLY WHEN SPECIFICALLY REFERENCED IN VA DESIGN DOCUMENTS, SEE NOTES BELOW)
• 2018 INTERNATIONAL EXISTING BUILDING CODE (IEBC) (IF APPLICABLE)
• NFPA 101 LIFE SAFETY CODE (MOST RECENT CODES APPLY) (SEE NOTES BELOW)
• 2018 NATIONAL FIRE CODES (NFPA)
• OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.
• 2020 VA SEISMIC DESIGN REQUIREMENTS, H-18-8
• 2020 NATIONAL ELECTRICAL CODE (NEC)
• 2015 INTERNATIONAL PLUMBING CODE (IPC)
• 2019 ASME BOILER AND PRESSURE VESSEL CODE
• 2007 ASME CODE FOR PRESSURE PIPING
• 2015 ARCHITECTURAL BARRIERS ACT (ABA) STANDARDS INCLUDING VA SUPPLEMENT, VA BARRIER FREE DESIGN STANDARD (PG-18-13)
• 2017 ANSI ICC A117.1 ACCESIBLE AND USABLE BUILDINGS AND FACILITIES
• 2019 BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE, AMERICAN CONCRETE INSTITUTE AND COMMENTARY (ACI 318)
• 2016 MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL STEEL BUILDINGS, AMERICAN
INSTITUTE OF STEEL CONSTRUCTION (AISC)
• ENERGY POLICY ACT OF 2005 (EPACT)
• 2006 DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-FAMILY HIGH-RISE RESIDENTIAL
BUILDINGS AND NEW LOW-RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435.
• 2006 FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS: MEMORANDUM OF UNDERSTANDING (MOU)
• 2018 EXECUTIVE ORDER 13834: EFFICIENT FEDERAL OPERATIONS
• 2021 THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE GENERAL REQUIREMENTS SECTION 01010 OF THE VA MASTER
CONSTRUCTION SPECIFICATION.
• 2016 VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY – ASHRAE STANDARD 62.1- 2004.
• 2019 SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE STANDARD 15 – 2007.
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES. HOWEVER, LOCAL AUTHORITIES SHOULD BE NOTIFIED ABOUT PLANNED PROJECTS AND GIVEN OPPORTUNITY TO REVIEW DRAWINGS PROVIDED THAT VA DOES NOT PAY FOR REVIEW OR INSPECTION FEES.
NOTES:
1. NFPA 101 PRIMARILY ADDRESSES LIFE SAFETY AND FIRE PROTECTION FEATURES WHILE THE IBC ADDRESSES A WIDE RANGE OF CONSIDERATIONS, INCLUDING, BUT NOT LIMITED TO, STRUCTURAL STRENGTH, SEISMIC STABILITY, SANITATION, ADEQUATE LIGHT AND VENTILATION, AND ENERGY CONSERVATION. VA BUILDINGS MUST MEET THE REQUIREMENTS OF NFPA 101 AND DOCUMENTS REFERENCED BY NFPA 101 IN ORDER TO COMPLY WITH THE ACCREDITATION REQUIREMENTS OF THE JOINT COMMISSION. THEREFORE, DESIGNS SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF NFPA 101 AND DOCUMENTS REFERENCED THEREIN. DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE ADDRESSED ABOVE IN THIS PROGRAM GUIDE. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
2. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
ASHRAE 90.1 - 2019 EDITION
BUILDING LOCATION: PALO ALTO, CALIFORNIA / SANTA CLARA COUNTY
CLIMATE ZONE (TABLE ANNEX 1-1): ZONE 3C
INTERIOR DESIGN CONDITIONS:
THE INTERIOR DESIGN TEMPERATURES FOR HEATING AND COOLING AS DEPICTED IN THE PROJECT DESIGN CONDITIONS SCHEDULE IN THE MECHANICAL CONTROL DRAWINGS SHALL BE THE MAXIMUM
AND MINIMUM VALUES FOR THE ASSOCIATED TEMPERATURE CONTROL ZONES.
BUILDING ENVELOPE REQUIREMENTS (TABLE 5.5-3):
ROOFS: REQUIRED: DESIGNED:
INSULATION ABOVE DECK R-25 c.i. EXISTING
METAL BUILDINGS: R-10 + R-19 FC EXISTING
ATTIC AND OTHER: R-38 EXISTING
WALLS, ABOVE GRADE
MASS: R-7.6 c.i. EXISTING METAL BUILDING: R-0 + R-9.8 c.i. EXISTING STEEL-FRAMED: R-13 + R-5 c.i. EXISTING
WOOD-FRAMED AND OTHER: R-13 EXISTING
WALL, BELOW GRADE
BELOW-GRADE WALL: NR EXISTING
FLOORS
MASS: R-10 c.i. EXISTING
STEEL-FRAMED: R-30 EXISTING
WOOD-FRAMED AND OTHER: R-30 EXISTING
SLAB-ON-GRADE FLOORS
UNHEATED SLABS: NR EXISTING
HEATED SLABS: R-15 for 24 in. EXISTING
OPAQUE DOORS
SWINGING: U-0.370 EXISTING
NONSWINGING: U-0.310 EXISTING
VERTICAL FENESTRATION, U-FACTOR
FIXED: U-0.42 EXISTING
OPERABLE: U-0.54 EXISTING
ENTRANCE DOOR: U-0.68 EXISTING
SKYLIGHT, 0% TO 3% OF ROOF, U-FACTOR
ALL TYPES: U-0.55 EXISTING
DEFINITIONS
c.i. = CONTINUOUS INSULATION
NR = NO (INSULATION) REQUIREMENT
ENERGY REQUIREMENTS
N
1. DRAWINGS ARE PART OF A COMPLETE DOCUMENTS SET. CONTRACTOR SHALL
CONFIRM ALL ITEMS REQUIRED BASED UPON THE OVERALL DESIGN INTENT OF THE
ENTIRE DOCUMENT SET.
2. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS, PRIOR TO BEGINNING ANY
WORK, TO CONFIRM THE ACCURACY OF THE DRAWINGS AND REPORT ANY
DISCREPANCIES TO THE ARCHITECT. DO NOT SCALE THE DRAWINGS. FIELD VERIFY
ALL DIMENSIONS AND EXISTING STRUCTURAL CONDITIONS.
3. ALL AREAS NOT INVOLVED IN THE SCOPE OF WORK FOR THIS PROJECT SHALL BE KEPT
CLEAN AND FREE OF OBSTRUCTIONS AT ALL TIMES.
4. ERECT BARRICADES AND WARNING SIGNS TO DIVERT AND WARN PASSERS-BY OF THE
CONSTRUCTION WORK. PROVIDE DUST PROOFING ENCLOSURES TO SEPARATE WORK
AREAS FROM THE EXISTING FACILITIES.
5. ALL TRASH AND DEBRIS TO BE REMOVED ON A DAILY BASIS.
6. PROVIDE PROTECTION FOR ALL EXISTING SURFACES AND CONDITIONS TO REMAIN IN
PLACE DURING THE SCOPE OF WORK. SHOULD ANY DAMAGE OCCUR, PATCH AND
REPAIR ANY DAMAGE TO ADJACENT FINISHES TO MATCH EXISTING.
7. ANY DAMAGE CAUSED TO THE BUILDING OR OWNER EQUIPMENT SHALL BE REPAIRED
OR REPLACED BACK TO ITS ORIGINAL CONDITIONS AT NO ADDITIONAL COST TO THE
OWNER.
8. COVER ALL RETURN AIR GRILLES WITHIN THE AREA OF CONSTRUCTION TO PREVENT
PARTICULATE MATERIAL FROM EXHAUSTING INTO SURROUNDING SPACES.
9. APPROPRIATE LIGHT FIXTURES SHALL BE TEMPORARILY SUSPENDED TO PROVIDE
ADEQUATE LIGHTING LEVELS FOR CONSTRUCTION.
10. CONTRACTOR AND SUBCONTRACTORS ARE REQUIRED TO COORDINATE WITH OTHER
DISCIPLINES TO INSTALL COMPLETE AND OPERATIONAL SYSTEMS. DRAWINGS, AS A
WHOLE, REPRESENT A COMPLETE SET AND DEPICT REQUIREMENTS FOR COMPLETE
AND OPERATIONAL SYSTEMS. INDIVIDUAL DRAWINGS MAY NOT DEPICT COMPLETE AND
ACCURATE INFORMATION TO COORDINATE COMPLETE AND OPERATIONAL SYSTEMS,
BUT DO SO AS AN ENTIRE DOCUMENT TO BE REFERENCED WITH OTHER INDIVIDUAL
DRAWINGS. CONTRACTOR AND SUBCONTRACTORS ARE REQUIRED TO REFERENCE
OTHER SHEETS AND SPECIFICATIONS AS AN ENTIRE SET OF CONSTRUCTION
DOCUMENTS THAT REFLECT WORK REQUIRED TO ACHIEVE A COMPLETE AND
OPERATIONAL GOAL. LACK OF COORDINATION AND REVIEW OF DRAWINGS AND
SPECIFICATIONS AS AN ENTIRE DOCUMENT TO INSTALL COMPLETE AND OPERATIONAL
SYSTEMS, BEING OBVIOUS AND TYPICAL INDUSTRY STANDARD, IDENTIFIED IN THE
DRAWINGS AND SPECIFICATIONS, SHALL NOT BE IN ANY WAY AN ADDITIONAL COST TO
THE GOVERNMENT.
11. CONTRACTOR SHALL SUBMIT A REQUEST, IN WRITING, TO INTERRUPT ANY SUCH
SERVICES TO COR (CONTRACTING OFFICER’S REPRESENTATIVE) 7 DAYS IN ADVANCE
OF PROPOSED INTERRUPTION. REQUEST SHALL STATE REASON, DATE, EXACT TIME
OF, AND APPROXIMATE DURATION OF SUCH INTERRUPTION. MAJOR INTERRUPTIONS
OF ANY SYSTEM MUST BE REQUESTED, IN WRITING, AT LEAST 60 CALENDAR DAYS
PRIOR TO THE DESIRED TIME AND SHALL BE PERFORMED AS DIRECTED BY THE COR.
MAJOR INTERRUPTIONS SHALL BE COORDINATED WITH OTHER MAJOR INTERRUPTIONS
AND MAY NOT BE SCHEDULED FOR ONE DISCIPLINE MORE THAN TWICE THROUGHOUT
THE OVERALL CONSTRUCTION SCHEDULE UNLESS REQUESTED IN WRITING AND
APPROVED BY THE COR. CONTRACTOR WILL BE ADVISED, IN WRITING, OF APPROVAL
OF REQUEST, OR OF WHICH OTHER DATE AND/OR TIME SUCH INTERRUPTION WILL
CAUSE THE LEAST INCONVENIENCE TO OPERATIONS OF THE MEDICAL CENTER.
INTERRUPTION TIME APPROVED BY THE MEDICAL CENTER MAY OCCUR AT TIMES
OTHER THAN CONTRACTOR'S NORMAL WORKING HOURS. SCHEDULE INTERRUPTION
MAY BE ON WEEKENDS OR LATE HOURS AND MAY NOT BE AN ADDITIONAL COST TO
THE GOVERNMENT. COORDINATE ALL INTERRUPTIONS THAT MAY AFFECT THE NORMAL
OPERATION OF THE FACILITY WITH THE COR WHEN SUBMITTING THE CONSTRUCTION
SCHEDULE OR UPDATES TO THE CONSTRUCTION SCHEDULE.
12. NO ASBESTOS CONTAINING MATERIALS ARE TO BE USED ON THIS PROJECT. SPUR
DESIGN, THE A/E OF RECORD, CAN CERTIFY THAT NO ASBESTOS CONTAINING
BUILDING MATERIALS (ACBM) OR LEAD BASED PAINT (LBP) PRODUCTS WERE
DESIGNED/SPECIFIED AS BUILDING MATERIAL IN ANY OF THE CONSTRUCTION
DOCUMENTS.
GENERAL NOTES
AREA NAME
150 SF
AE-101
A101
SIM
00000
00.0
AE-101
1 1
A101
LEVEL NAME
00'-00"
00'-00"
4B
3A
FIBERGLASS BATT INSULATION
ROOM NAME
000A
150 SF
/1 A101 X0000
6"
3' -0
M
A X
ROOM TAG
AREA TAG
SPECIALTY EQUIPMENT TAG
DOOR TAG
KEYED NOTE TAG
WALL TAG
WINDOW TAG
A101
SIM
A101
SIM
A
ACST ACOUSTIC
ADA AMERICANS WITH DISABILITIES ACT
ACT ACOUSTICAL CEILING TILE
ADDL ADDITIONAL
ADDN ADDITION
ADJ ADJACENT, ADJOINING, OR ADJUSTABLE
ADMIN ADMINISTRATION
AE ARCHITECT/ENGINEER
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AHJ AUTHORITY HAVING JURISDICTION
AIA AMERICAN INSTITUTE OF ARCHITECTS
ALT ALTERNATE
ALT NO ALTERNATE NUMBER
AMT AMOUNT
APPROX APPROXIMATE
AR AS REQUIRED
ARCH ARCHITECT
ASC ABOVE SUSPENDED CEILING
AVG AVERAGE
B
BD BOARD
BLDG BUILDING
BLKG BLOCKING
BLT IN BUILT-IN
BOS BOTTOM OF STEEL
BOT BOTTOM
BRKT BRACKET
BTWN BETWEEN
C
CAB CABINET
CAV CAVITY
CD CONSTRUCTION DOCUMENTS
CFM CUBIC FEET PER MINUTE
CFS CUBIC FEET PER SECOND
CIP CAST-IN-PLACE
CJ CONTROL JOINT
CL CENTER LINE
CLG CEILING
CLG HT CEILING HEIGHT
CLR COLOR
CO CONTRACTING OFFICER
COL COLUMN
COMM COMMUNICATION
CONC CONCRETE
CONT CONTINUOUS
COORD COORDINATE
COR CONTRACTING OFFICER'S REPRESENTATIVE
CP CONTRACTOR PROVIDED
CP/CI CONTRACTOR PROVIDED / CONTRACTOR INSTALLED
CSWK CASEWORK
CTR CENTER
CU FT CUBIC FEET
D
DBL DOUBLE
DEMO DEMOLITION
DEPT DEPARTMENT
DET DETAIL
DIA DIAMETER
DIR DIRECTION
DIST DISTANCE
DOC DOCUMENT
DR DOOR
E
EA EACH
EJ EXPANSION JOINT
EL ELEVATION
ELEV ELEVATOR
ENTR ENTRANCE
EQ EQUAL
EXIST EXISTING
EXP EXPOSED
EXT EXTERIOR
F
FED FEDERAL
FF FINISH FACE
FF EL FINISH FLOOR ELEVATION
FIN FINISH
FIN BS FINISH BOTH SIDES
FIN FLR FINISH FLOOR
FIN GR FINISH GRADE
FIXT FIXTURE
FLDG FOLDING
FLEX FLEXIBLE
FLG FLOORING
FLMT FLUSH MOUNT
FLR FLOOR
FOC FACE OF CONCRETE
FOM FACE OF MASONRY
FR FIRE RESISTANT
FT FEET
FTG FOOTING
FV FIELD VERIFY
G
GR FL GROUND FLOOR
H
HDW HARDWARE
HEPA HIGH EFFICIENCY PARTICULATE AIR (FILTER)
HORIZ HORIZONTAL
HT HEIGHT
I
IBC INTERNATIONAL BUILDING CODE
INSUL INSULATION
INT INTERIOR
ILO IN LIEU OF
L
LAV LAVATORY
LBS POUND
LDG LANDING
LF LINEAR FEET (FOOT)
LIN LINEAR
LOC LOCATION
LT LIGHT
LVR LOUVER
M
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MEMB MEMBRANE
MFR MANUFACTURER
MID MIDDLE
MIL STD MILITARY STANDARD
MIN MINIMUM
MISC MISCELLANEOUS
MO MASONRY OPENING
MOD MODIFY
MTG MOUNTING
MTL METAL
MVBL MOVABLE
N
NA NOT APPLICABLE
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NTS NOT TO SCALE
O
OA OVERALL
OC ON CENTER
OD OUTSIDE DIAMETER
OPNG OPENING
OPP OPPOSITE
OPR OPERABLE
ORIG ORIGINAL
P
PA PUBLIC ADDRESS
PCF POUNDS PER CUBIC FOOT
PCT PERCENT
PERF PERFORATED
PERIM PERIMETER
PL PROPERTY LINE
PLBG PLUMBING
PNL PANEL
PR PAIR
PRKG PARKING
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PWR POWER
Q
QTY QUANTITY
R
RCP REFLECTED CEILING PLAN
REC RECESSED
REF REFERENCE
REM REMOVABLE
REP REPAIR
REPL REPLACE
REQ REQUIRE
REQD REQUIRED
RFG ROOFING
RM ROOM
RO ROUGH OPENING
S
SCHED SCHEDULE
SF SQUARE FOOT (FEET)
SGL SINGLE
SIM SIMILAR
SJ SCORED JOINT
SLNT SEALANT
SPEC SPECIFICATION
SQ SQUARE
SQ IN SQUARE INCH
SQ YD SQUARE YARD
STD STANDARD
STOR STORAGE
T
TEL TELEPHONE
TEMP TEMPORARY
TFF TOP OF FINISH FLOOR
TOF TOP OF FOOTING
TOM TOP OF MASONRY
TOP TOP OF PARAPET
TOPO TOPOGRAPHY
TOS TOP OF SLAB
U
UNO UNLESS NOTED OTHERWISE
UTIL UTILITY
V
VAR VARIES
VC VA PROVIDED / CONTRACTOR
INSTALLED
VV VA PROVIDED / VA INSTALLED
W
W/ WITH
W/O WITHOUT
W/C WATER CLOSET
WC WHEELCHAIR
X
X BRACE CROSS BRACE
REFERENCE SYMBOLS IDENTIFICATION TAGS
NOTE: NOT ALL ABBREVIATIONS OR SYMBOLS WILL BE UTILIZED FOR THIS PROJECT.
GRID HEAD AND
LINE
LEVEL INDICATOR
MATCH LINE AND
VIEW REFERENCE
NORTH ARROW W/
PROJECT NORTH
SPOT ELEVATION
DETAIL
SECTION
*48" MIN IF BOTH CLOSER
AND LATCH PROVIDED
WALL
SECTION
BUILDING
SECTION
DETAIL
ELEVATION
INTERIOR
ELEVATION
BUILDING
ELEVATION
1 1
BARIATRIC TOILET ROOM
TURNING RADIUS
CLEAR FLOOR SPACE
@ ADA LAVATORY
CLEAR FLOOR SPACE
@ ADA DRINKING
FOUNTAIN
MINERAL WOOL INSULATION
EXPANDED POLYSTYRENE INSULATION
POLYISOCYANURATE INSULATION
SPRAY-APPLIED CLOSED CELL INSULATION
SPRAY-APPLIED CLOSED CELL INSULATION
CONCRETE / PRECAST CONCRETE
EARTH / SOIL
SAND, EIFS FINISH, OR PLASTER FINISH
GYPSUM BOARD FINISH
BRICK
CONCRETE MASONRY UNIT
STONE / CAST STONE
GYPSUM BOARD
EXTERIOR SHEATHING BOARD
PLYWOOD
*59" FOR FLOOR
MOUNTED W.C.
T O
B .O
R
E F
LE
C
T
IV
E
S U
R F
A C
E
1"
M
IN 39"- 41"
7" - 9"
3"
1' -6
M
IN
3' -6
M
A X
FIRE EXTINGUISHER
CABINET
WEIGHT > 40LBS
5' -0
M
A X
FIRE EXTINGUISHER
CABINET
WEIGHT < 40LBS
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS:
Drawing #Revision: Date:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
STRUCTURAL ENGINEER
GREGORY P. LUTH & ASSOCIATES
3350 SCOTT BOULEVARD, BLDG. 48
SANTA CLARA, CA 95054
(408) 654-0475
MEP / TECHNICAL ENGINEER
SPUR DESIGN
2519 MADISON AVE. STE 100
KANSAS CITY, MO 64108
(913) 369-7200
FIRE PROTECTION ENGINEER
POOLE FIRE PROTECTION, INC.
19910 WEST 161ST STREET
OLATHE, KANSAS 66062
(913) 829-8690
FULLY SPRINKLERED
MEDICAL EQUIPMENT PLANNING
INNOVA GROUP
3196 NORTH SWAN ROAD
TUCSON, AZ 85712
(520) 886-8650
SHEET TITLE
CIVIL ENGINEER
KEIR & WRIGHT
3350 SCOTT BLVD, BLDG22
SANTA CLARA, CA 95051
(405) 727-6665
PHYSICAL SECURITY
FORCE PROTECT SECURITY CONSULTANTS
10901 FRONT BEACH RD, STE 1415
PANAMA CITY BEACH, FL 32407
(502) 836-4232
ARCH. REG. NO. C38975
ENGR. REG. NO. M39910
EXPIRES: 05/31/2023
EXPIRES: 06/30/2024
SPUR #: 1795.07
/2
/2
:0
:4
A
M
GI001
GENERAL INFORMATION
ZDL
B100
BGJ
FINAL BID DOCUMENTS
RENOVATION AND EXPANSION OF SPS
03/03/2023
640-23-108
VA PALO ALTO HEALTHCARE SYSTEM
3801 MIRANDA AVENUE
PALO ALTO, CA 94304
| 02_CIVIL |
| Sheets and Views |
| C-001 COVER SHEET |
| CD-001 DEMOLITION PLAN |
| CS-001 DETAILS |
| CS-002 TOPOGRAPHIC SURVEY |
| CS-003 SITE IMPROVEMENT PLANS |
| CS-004 HYDRANT COVERAGE DIAGRAM |
| CG-001 EROSION CONTROL PLAN |
| 03_STRUCTURAL |
| SG-001 - GENERAL NOTES |
| SG-002 - SHEET LIST, LEGEND & ABBREVIATIONS |
| SG-101 - BASEMENT EQUIPMENT PAD PLAN |
| SG-141 - ROOF PLAN |
| SG-150 - MODULAR UNIT FOUNDATION PLAN |
| SG-501 - TYPICAL DETAILS |
| SG-502 - MEP CONNECTION DETAILS |
| 08_ELECTRICAL |
| 1795.07_E19_andrew - Sheet - E-000 - ELECTRICAL LEGEND |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - E-501 - ELECTRICAL DETAILS |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - E-602 - ELECTRICAL SCHEDULES |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - E-603 - PANELBOARD SCHEDULES |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 09_TECHNOLOGY |
| 1795.07_E19_andrew - Sheet - T-000 - TECHNOLOGY LEGEND |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - TY-100 - SECURITY BASEMENT FLOOR PLAN |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |
| EQ-100 - SPS MECHANICAL EQUIPMENT POWER BASEMENT FLOOR PLAN |
| EQ-105 - SPS MECHANICAL EQUIPMENT POWER ROOF PLAN |
| ES-101 - ELECTRICAL SITE PLAN - TEMPORARY SPS |
| ES-401 - MODULAR BUILDING ELECTRICAL AND TECHNOLOGY FLOOR PLANS |
| ES-601 - MODULAR BUILDING ONE-LINE DIAGRAM AND SCHEDULES |
| T-000 - TECHNOLOGY LEGEND |
| T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| T-501 - TECHNOLOGY DETAILS |
| T-601 - TECHNOLOGY SCHEDULES AND RISER DIAGRAMS |
| TD-100 - TECHNOLOGY DEMOLITION BASEMENT FLOOR PLAN |
| TI-100 - PUBLIC ADDRESS BASEMENT FLOOR PLAN |
| TN-100 - TECHNOLOGY BASEMENT FLOOR PLAN |
| TY-100 - SECURITY BASEMENT FLOOR PLAN |
| 1795.07_E19_andrew - Sheet - T-401 - ENLARGED TECHNOLOGY FLOOR PLANS |
| Sheets |
| E-000 - ELECTRICAL LEGEND |
| E-401 - ENLARGED ELECTRICAL FLOOR PLANS |
| E-501 - ELECTRICAL DETAILS |
| E-601 - ELECTRICAL ONE-LINE DIAGRAM |
| E-602 - ELECTRICAL SCHEDULES |
| E-603 - PANELBOARD SCHEDULES |
| ED-100 - ELECTRICAL LIGHTING DEMOLITION BASEMENT FLOOR PLAN |
| ED-200 - ELECTRICAL POWER DEMOLITION BASEMENT FLOOR PLAN |
| ED-205 - ELECTRICAL POWER DEMOLITION ROOF PLAN |
| EL-100 - ELECTRICAL LIGHTING BASEMENT FLOOR PLAN |
| EP-100 - ELECTRICAL POWER BASEMENT FLOOR PLAN |
| EP-101 - ELECTRICAL POWER FIRST FLOOR PLAN |