This document provides instructions for calculating self-performed work on a federal contract. It outlines requirements for offerors to identify the percentage of self-performed work in accordance with regulations limiting subcontracting. Offerors must complete calculations for each task order competed showing their total proposed price, subtracted costs for profit, materials, and subcontracting. The percentage of self-performed work must be equal to or less than 15%. The related solicitation is for refurbishing and upgrading elevators in two buildings at a Veterans Affairs medical center.

View the file

Other files

File Type Posted
Wage Determination 1.19.24.pdf PDF
36C26024R0009 0006.pdf PDF
36C26024R0009 0005.pdf PDF
Wage Determination 1.5.24.pdf PDF
Wage Determination 12.22.23.pdf PDF
36C26024R0009 0004.pdf PDF
36C26024R0009 0003.pdf PDF
36C26024R0009 0002.pdf PDF
36C26024R0009 0001.pdf PDF
WD 11.24.23.pdf PDF
668-18-109_Pre Bid Site Walk Sign In Sheet_2023.12.03.pdf PDF
Attachment 17 Security Requirements.pdf PDF
Attachment 18 Contractor Rules of Behavior.pdf PDF
Attachment 4 668-18-109_Supplement to SPEC 01 00 00 Part 1-6-I.pdf PDF
Attachment 10 668-18-109_Project Drawings 6 of 6.pdf PDF
Attachment 15 Wage Determination 11.17.23.pdf PDF
Attachment 2 668-18-109_Project Specifications 1 of 2_R1.pdf PDF
Attachment 5 668-18-109_Project Drawings 1 of 6.pdf PDF
Attachment 13 668-18-109_Lead Sampling Report.pdf PDF
Attachment 6 668-18-109_Project Drawings 2 of 6.pdf PDF
36C26024R0009.pdf PDF
Attachment 7 668-18-109_Project Drawings 3 of 6.pdf PDF
Attachment 12 668-18-109_Limited Asbestos Good Faith Survey - Addendum 1.pdf PDF
Attachment 16 Price Breakout.xlsx XLSX spreadsheet
Attachment 3 668-18-109_Project Specifications 2 of 2_R1.pdf PDF
Attachment 1 668-18-109_SOW-CON_2023-08-15.pdf PDF
Attachment 8 668-18-109_Project Drawings 4 of 6.pdf PDF
Attachment 11 668-18-109_Limited Asbestos Good Faith Survey.pdf PDF
Attachment 9 668-18-109_Project Drawings 5 of 6.pdf PDF
Attachment 14 668-18-109_DWG Clarification Document_2023-06-22.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 19

INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW

“Limitations on Subcontracting” (FAR 52.219-14 and VAAR 852.219-10)

Offeror:

Project # & Description:

Offeror’s are to identify self-performance IAW CFR Title 13: Business Credit and Assistance

PART 125—GOVERNMENT CONTRACTING PROGRAMS

https://www.gpo.gov/fdsys/pkg/CFR-2011-title13-vol1/pdf/CFR-2011-title13-vol1-part125.pdf

§125.6 Prime contractor performance requirements (limitations on subcontracting).

https://www.gpo.gov/fdsys/pkg/CFR-2012-title13-vol1/pdf/CFR-2012-title13-vol1-sec125-6.pdf

For this solicitation under CFR 125.6(7)(g), insert the following: “For evaluations, the period of time used to determine compliance will be the period of performance which the evaluating agency uses to evaluate the proposal for each individual Task Order”.

OFFEROR’S SELF PERFORMED CALCULATIONS

Offeror’s Self-Performed Estimated Calculations:

Offeror’s are required to complete for each Task Order for which they compete.

A Offeror’s proposed price (total) $

B Subtract profit or fees $

C Subtract cost of materials $

D Offeror’s total estimated cost of performance for personnel (A-B-C=D)

E Offeror’s total estimated self-performed cost of contract performance

F Offeror’s percentage of self-performed work (e/d*100 = %)

*block F must be equal to or less than 15%

List of Proposed Subcontractors for this project / Value of those subcontracts:

Subcontractor $Value

Subcontractor $Value

Subcontractor $Value

Subcontractor $Value

668-18-109 Refurbish and Upgrade Elevators in Bldg. 1 and 27

a) Definitions: (from 13 CFR 125.6)

b) Cost of the contract. All allowable direct and indirect costs allocable to the contract, excluding profit or fees.

c) Cost of contract performance incurred for personnel. Direct labor costs and any overhead which has only direct labor as its base, plus the concern's General and Administrative rate multiplied by the labor cost.

d) Cost of materials. Includes costs of the items purchased, handling and associated shipping costs for the purchased items (which includes raw materials), off-the-shelf items (and similar proportionately high-cost common supply items requiring additional manufacturing or incorporation to become end items), special tooling, special testing equipment, and construction equipment purchased for and required to perform on the contract. In the case of a supply contract, the acquisition of services or products from outside sources following normal commercial practices within the industry are also included.

e) Personnel. Individuals who are “employees” under §121.106 of this chapter except for purposes of the HUBZone program, where the definition of “employee” is found in §126.103 of this chapter.

f) Subcontracting. That portion of the contract performed by a firm, other than the concern awarded the contract, under a second contract, purchase order, or agreement for any parts, supplies, components, or subassemblies which are not available off-the-shelf, and which are manufactured in accordance with drawings, specifications, or designs furnished by the contractor, or by the government as a portion of the solicitation. Raw castings, forgings, and moldings are considered as materials, not as subcontracting costs. Where the prime contractor has been directed by the Government to use any specific source for parts, supplies, components subassemblies or services, the costs associated with those purchases will be considered as part of the cost of materials, not subcontracting costs.