This document provides an amendment to a solicitation for construction services. The amendment provides responses to questions regarding requirements for infection control walls and car operating panel locations in elevator modernization projects at the Mann-Grandstaff VA Medical Center in Spokane, Washington. Dimensions are provided for installation of temporary barriers between floors in Building 1 and Building 27. Clarification is also given that the digital display for car operating panels is intended to be located on the cab side walls, not at the entrance, as the available space on return panels would not accommodate the specified display size.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODECODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
0003 01-02-2024 668-18-109
36C260
Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
To all Offerors/Bidders
36C26024R0009
11-21-2023
X
X 1
Project: 668-18-109 / Refurbish and Upgrade Elevators in Bldg. 1 and 27
See Continuation Page for Amendment details.
All other terms and conditions remain the same.
The POC for this amendment is Taminie Panich, taminie.panich@va.gov
36C26024R0009 003
SF 30 BLOCK 14 CONTINUATION PAGE(S)
It has been determined necessary and in the best interest of the Government to amend solicitation 36C6024R0009 to provide questions and answers.
Question 19: Please clarify if all infection control walls (LT1 temp barrier) are to be installed up to the concrete floor above. If so, please provide dimensions from finished floor to concrete floor above for each floor.
Government response: The infection control walls (LT1 temp barriers) are to be installed in accordance with the government infection control regulations, this will require containment from the finished floor to the structure above.
Dimensions from finished floor to concrete floor above for each floor.
Building 1:
BF to 1F – 11’-0”
1F to 2F – 12’-0”
2F to 3F – 11’-0”
3F to 4F – 11’-0”
4F to 5F – 11’-0”
5F to 6F – 11’-0”
6F to 7F – 11’-0”
7F to 8F – 11’-0”
8F to Penthouse – 12’-0”
Penthouse to Machine Room – 12’-3”
Machine room to Roof – 9’-5”
Building 27:
BF to 1F – 12’-0”
1F to 2F – 14’-0”
2F to Roof – 12’-0”
Question 20: Current platform is sized based on space available in hoist way, an increase in size is not possible given the seismic requirements and the existing hoistway.
Specification calls for a car operating panel in each return and specifies Elite display which require 13” of space. With the door opening size specified this is not possible.
Available space on each return panel with 2SCO 4’-0” doors is 7.75”. Please provide clarification on car operating panel locations and requirements or confirmation that the hoistway width will be increased.
36C26024R0009 003
Government response: The digital display is not intended to be on the interior of the CAB on the same wall as the door. There is no intent in this design to alter the dimension of the hoistway.
The details located in the Contract Documents A-201 and A-203 show the digital display being placed on the side walls of the cab not the entrance of the CAB.