Att. 5 - Set 3 of 8 Final Drawings By Building 590 22 700.pdf

PDF 29 MB Posted

Attached to
Y1DA--590-22-700 | Construct EHRM Infrastructure Upgrade | Hampton, VA | Federal contract opportunity
Solicitation number
36C77626R0041
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

These are final construction drawings (Set 3 of 8) for the EHRM Infrastructure Upgrades project at Hampton VA Medical Center in Hampton, Virginia, project number 590-22-700. The drawings depict phasing plans, floor plans, mechanical systems, electrical systems, and telecommunications infrastructure for multiple buildings including Buildings 7, 8, 9, 10, 11, 13, 14, 15, 17, 18, and 27, prepared at 100% Construction Documents phase dated July 18, 2025.

The scope includes VRF/VRV cooling system installations with indoor wall-mounted units, refrigerant line routing, condensate drainage, and sprinkler system modifications across multiple facilities and floors. Mechanical work encompasses new ductless split systems, equipment relocation, and piping installations with specific attention to fire-rated penetrations and ICRA (Infection Control Risk Assessment) protocols for occupied healthcare spaces. Electrical work includes panelboard modifications, circuit additions, power distribution to new mechanical equipment, telecommunications bonding backbones, and data outlet upgrades from Category 6 to Category 6A cabling. Telecommunications infrastructure incorporates new fiber optic backbone cables, cable tray systems, horizontal cabling distribution, and equipment relocation within designated telecom rooms. The drawings mandate coordination with the VA for equipment shutdowns, phasing plans, and minimal disruption to essential systems, with contractor responsibility for field verification, NICET-certified design drawings for fire protection work, and compliance with current VA guides and NFPA 13 standards. The design indicates a Design-Build delivery method with SPEES/STAMPCONSULTANT as the A/E of record.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--590-22-700 | Construct EHRM Infrastructure Upgrade | Hampton, VA |, newest first.
File Type Posted
Att. 3 - Brand Name Justification.pdf PDF
Att. 2 - Specifications - 4-23-2026.pdf PDF
Att. 1 - Tech Questions Tracker - 590-22-700.pdf PDF
36C77626R0041 0003.pdf PDF
36C77626R0041 0002.pdf PDF
Att. 1 - 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS - APR 2026.pdf PDF
36C77626R0041 0001.pdf PDF
Attachment 01 - Site Visit Sign in Sheet.pdf PDF
Att. 12 - Set 2 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 6 - Set 4 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 22 - Limitations on Subcontracting.pdf PDF
Att. 18 - Set 8 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 13 - Set 3 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 10 - Set 8 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 9 - Set 7 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 7 - Set 5 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 24 - Key Personnel.pdf PDF
Att. 23 - KSI.pdf PDF
Att. 17 - Set 7 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 15 - Set 5 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 14 - Set 4 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 8 - Set 6 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 3 - Set 1 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 2 - Specifications.pdf PDF
36C77626R0041.pdf PDF
Att. 21 - HEFP SEP Design Alerts 1-9 and 11-16.pdf PDF
Att. 20 - Division Pricing Template.xlsx XLSX spreadsheet
Att. 19 - DBA Wage Determination.pdf PDF
Att. 16 - Set 6 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 11 - Set 1 of 8 Final Drawings By Discipline 590 22 700.pdf PDF
Att. 4 - Set 2 of 8 Final Drawings By Building 590 22 700.pdf PDF
Att. 1 - Construction SOW.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DN

DN

27B

27 31

27A

110A

110B

110D

13W

148-D

148-S

148-A

148T

146B

146A

138A 138136

137A

137C

137D

137B

137C

148B

173A

148-C

170 150

110C

143 167

G R

A V

E L

R O

A D

FRANKLIN BOULEVARD

FRANKLIN BOULEVARD

AVERILL AVENUE

AVERILL AVENUE

A M

E S

S T

R E

E T

HARRIS AVENUE

JONES CREEK

K N

O X S

T R

E E

T

T H

O M

P S

O N

S T

R E

E T

F R A N

K

LI

N B

O U

LE

V A R

D

MALLORY STREET

M A

R T

IN

L. K

IN

G

JR

. B O

U L E

V A R

D

M A R

TIN

L. K

IN

G

JR

. B O U

LE

V

AR

D

E M

A N

C

IP

A T

IO

N D

R

SHORE ROAD

H A R R

IS

A V E N

U E

HARRIS AVENUE

M c C

L E

L L A

N

S E

W E

LL

A

V E

N U

E

A V

E N

U E

B

A

C

D

E

F

G

H

I J

K

L

M

N P

O

Q

R S

T

U

V

BLDG. 7BLDG. 8BLDG. 9

BLDG. 10 BLDG. 11

94 SF

ROOM

2-1

369 SF

ROOM

2-2

578 SF

MEZZ STORAGE

2-0

SECTION 1A:

CONTRACTOR TO COORDINATE WITH VA

FOR ROOM CLOSURES AND AVAILABILITY

TO COMPLETE DATA WIRING IN THIS AREA.

TR

ICRA PHASING LINE

ICRA CLASS II

ICRA CLASS III

ICRA CLASS IV

FEC

FE

FIRE EXTINGUISHER CABINET

FIRE EXTINGUISHER

KEY AREA SHOWN

TRUE

NORTH

BUILDING 7, 8, 9,10 &11

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/0

/2

:3

:3 a m

B

IM

/5

-2

-7

V A

H a m p to n

E H

R M

/B L D

G

-8 -9

-1

-1

.r v t

7AS102

BUILDING 7, 8, 9, 10, 11 - MEZZANINE -

PHASING PLAN

7, 8, 9, 10, 11

MA RB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

LEGEND

1/8" = 1'-0"

BUILDING 7, 8, 9, 10, 11 - MEZZANINE - PHASING PLAN

PROJECT

NORTH

0' 4' 8' 16'

KEY PLAN

Revisions: Date: 101 of 713

OA D F H K M R S U

B C E G I J L N P Q T V

007-M-401

FURNITURE

STORAGE

1-10

BATHROOM

1A-10

BATHROOM

8C-11

AREA MAINT.

8A-11

MEETING ROOM

8-11

STORAGE / HWH

8B-11

BREAK ROOM

7-11

BATHROOM

6-11 BATHROOM

5-11

IT CLOSET

1B-11

STORAGE

4A-11

ELECTRICAL

ROOM

4-11

OFFICE

3-11

BATHROOM

2A-11

BATHROOM

3A-11

STORAGE ROOM

ELECTRONICS

1A-11

OFFICE

2-11

CORRIDOR

1-11

ROOM

4A-9

PLUMBING SHOP

6-8

ELECTRICAL

STORAGE

7-7

STORAGE

6-7

OFFICE

5-7

TR

5A-7

ELECTRICAL

ROOM

4-7

BREAK ROOM

3-7

BATHROOM/SHOWER

2-7

MECHANICAL

SHOP

1-7

MECHANICAL

SHOP

1-8

OFFICE

2-8

BATHROOM/SHOWER

3-8

BATHROOM/SHOWER

2-9

BREAK ROOM

4-8

DDC CONTROLS

5-8

LOCKER BREAK

ROOM

4-9

BREAK ROOM

3-9

CARPENTER

SHOP

1-9

OFFICE

7-9

OFFICE

6-9

PAINT ROOM

5-9

OFFICE

7-8

OFFICE

8-9

TOOL CRIB

9-9

MECH STORAGE

6A-8

SPRINKLER

6A-9

007-M-401

007-M-401

007-M-401

AREA SHOWN

TRUE

NORTH

BUILDING 007

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT/DISCIPLINE

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 300

KENT, WA 98032

/0

/2

:5

:4 a m

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /M

E C

H

B L D

G

-0

-0

-0

- 0

.r v t

007-M-101

BLDG 007 - LVL 01 - OVERALL PLAN

MGH/JW AP/CY/JJ/MA/EA/RQ/BC

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

1/8" = 1'-0"1

BLDG 007 - LVL 01 - OVERALL PLAN

PROJECT

NORTH

SITE PLAN

Revisions: Date:

7/18/25 102 of 713

SHOWN AREA

PROJECT

NORTH

N P Q

T

OFFICE

5-7

IT CLOSET

5A-7

MECHANICAL

SHOP

1-8

OFFICE

6-7

SHOP

1-7

ELECTRICAL

SHOP GIP

STORAGE

7-7

MECH. GIP

STORAGE

6-8

N P Q

TR

5A-7

OFFICE

5-7

MECHANICAL

SHOP

1-8

ELECTRICAL

STORAGE

7-7

STORAGE

6-7

MECHANICAL

SHOP

1-7

PLUMBING SHOP

6-8

N P Q

4 3

IT CLOSET

5A-7

OFFICE

5-7

MECHANICAL

SHOP

1-8

OFFICE

6-7

ELECTRICAL

SHOP GIP

STORAGE

7-7

MECH. GIP

STORAGE

6-8

SHOP

1-7

5A-7

N P Q T V

TR

5A-7 OFFICE

5-7

MR

T

H

MECHANICAL

SHOP

1-7

STORAGE

6-7

BATHROOM/SHOWER

2-7

BREAK ROOM

3-7

ELECTRICAL

ROOM

4-7

007-CU-01-5A-7

MECHANICAL

SHOP

1-8

D

RL/RS

3/8"Ø, 5/8"Ø

3/4"Ø

007-VRF-01-5A-7 5

RL/RS

ELECTRICAL

STORAGE

7-7 3/8"Ø, 5/8"Ø6

R L /R

S D

007-VRF-02-5A-7 5

3/4"Ø 7

3/8"Ø, 5/8"Ø6 11 11

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT/DISCIPLINE

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 300

KENT, WA 98032

/0

/2

:5

:4 a m

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /M

E C

H

B L D

G

-0

-0

-0

- 0

.r v t

007-M-401

BLDG 007 - LVL 01 - DEMOLITION, FLOOR

PLANS & RCPS

MGH/JW AP/CY/JJ/MA/EA/RQ/BC

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

DEMOLISH EXISTING DUCTLESS AC UNIT. DEMOLISH

REFRIGERANT PIPE SERVING DUCTLESS AC UNIT.

DEMOLISH CONDENSATE DRAIN PUMP, DEMOLISH

CONDENSATE PIPE AND DEMOLISH ASSOCIATED

CONDENSING UNIT.

DEMOLISH EXISTING THERMOSTAT. TURN OVER TO COR.

CONTRACTOR TO TAKE A PRE-CONSTRUCTION AIRFLOW

READING AND BALANCE NEW DIFFUSER TO SAME

AIRFLOW. DIFFUSER AND DUCTWORK SIZE AND TYPE IN

NEW PHASE TO MATCH DEMOLISHED.

DEMOLISH EXISTING QUICK RESPONSE SPRINKLER.

INSTALL NEW VRF/VRV INDOOR WALL MOUNTED COOLING

UNIT. SEE EQUIPMENT SCHEDULES ON SHEET M-601.

INSTALL NEW REFRIGERANT LINES PER MANUFACTURER

REQUIREMENTS (INDOOR UNIT TO OUTDOOR UNIT).

PROVIDE PIPE INSULATION FOR ALL REFRIGERANT LINES

PER SPECIFICATION SECTION 23 07 11. PROVIDE PIPE

SUPPORT PER SPECIFICATION SECTION 23 05 11. PIPE

SIZES SHOWN ON PLANS ARE ONLY APPLICABLE TO BASIS

OF DESIGN MANUFACTURER.

INSTALL NEW CONDENSATE LINE. PROVIDE PIPE SUPPORT

PER SPECIFICATION SECTION 23 05 11.

INSTALL REFRIGERANT SENSOR AT A HEIGHT OF NOT

MORE THAN 1 FT. ABOVE FINISHED FLOOR.

CONDENSATE TO BE DISCHARGED TO THE GROUND.

TERMINATE CONDENSATE PIPING WITH A DOWNTURNED

ELBOW 12" ABOVE FINISHED GRADE.

SEE "CONDENSING UNIT GROUND MOUNT SUPPORT

DETAIL" ON SHEET M-501.

PROVIDE WALL OPENING AND PIPE SLEEVE. SEE "PIPE

THRU WALL (RATED/UNRATED) DETAIL" ON SHEET M-501.

EXISTING FIRE PROTECTION PIPING TO REMAIN.

EXTEND NEW SPRINKLER LINE OFF EXISTING BRANCH

LINE. ALL NEW SPRINKLER PIPING SHALL MATCH EXISTING

PIPE SIZES. INSTALL NEW STANDARD RESPONSE

SPRINKLER IN UPRIGHT POSITION.

EXISTING QUICK RESPONSE SPRINKLER TO REMAIN.

NEW CEILING SUPPLY DIFFUSER. SEE KEYNOTE #3.

PROJECT

NORTH

PROJECT

NORTH

PROJECT

NORTH

PROJECT

NORTH

1/4" = 1'-0"1

RM 5A-7 - DEMOLITION FLOOR PLAN

1/4" = 1'-0"4

RM 5A-7 - RCP

1/4" = 1'-0"2

RM 5A-7 - DEMOLITION RCP

KEYNOTES #

KEY PLAN

GENERAL NOTES

1. ALL PIPING IS SHOWN OFFSET AND DIAGRAMMATIC FOR

CLARITY. CONTRACTOR SHALL RACK PIPING AS CLOSE AS

POSSIBLE TO INSIDE WALL OF TELECOM ROOM.

2. NEW WORK SHOWN DARK, EXISTING WORK SHOWN

LIGHT.

3. A SINGLE LINE IS USED TO INDICATE ALL REFRIGERANT

PIPING ROUTED BETWEEN THE INDOOR AND OUTDOOR

UNIT(S). THIS SINGLE LINE REPRESENTS ALL PIPING

REQUIRED TO PROVIDE A COMPLETE AND FUNCTIONING

SYSTEM.

4. ROUTE ALL INTERIOR CONDENSATE AND REFRIGERANT

PIPING CONCEALED IN WALLS, CHASES OR CEILING

SPACES.

FIRE PROTECTION NOTES

1. FOR THE PURPOSES OF CLEARNESS AND LEGIBILITY,

DRAWINGS ARE DIAGRAMMATIC AND FOR DESIGN INTENT

ONLY. CONTRACTOR MUST VERIFY ALL DIMENSIONS BY

FIELD MEASUREMENT BEFORE BEGINNING ANY

FABRICATION OR CONSTRUCTION.

2. ALL WORK SHALL BE COMPLETED IN STRICT ACCORDANCE

WITH THE CURRENT VA GUIDES AND LOCAL FIRE

PROTECTION CODES AND ORDINANCES.

3. CONTRACTOR SHALL HAVE NICET III/IV TECHNICIAN DESIGN

DRAWINGS OR A LICENSED FIRE PROTECTION ENGINEER

STAMP ON ALL SHOP DRAWINGS.

4. COORDINATE EXACT LOCATION OF PIPING, SPRINKLERS,

EQUIPMENT AND MATERIALS WITH OTHER TRADES IN

ACCORDANCE WITH NFPA 13.

5. CONTRACTOR SHALL COORDINATE WITH GENERAL

CONTRACTOR AND VA COR PRIOR TO ANY CUTTING OF

WALLS AND ROOF.

6. THE CONTRACTOR SHALL PROVIDE FIRE CAULKING AT ALL

PIPING PENETRATIONS OF FIRE RATED ASSEMBLIES AS

REQUIRED.

7. TELECOM ROOMS SHALL HAVE FM APPROVED, UPRIGHT,

STANDARD RESPONSE SPRINKLERS WITH FUSIBLE LINKS.

PROVIDE LISTED MECHANICAL GUARDS. ALL EXPOSED

FIRE PROTECTION LINES SHALL BE PAINTED RED.

8. TELECOM ROOMS ARE CONSIDERED LIGHT HAZARD FOR

SPRINKLER HEAD DENSITY. ANY OTHER HAZARD

CLASSIFICATION AND SPRINKLER DENSITY ARE TO BE IN

ACCORDANCE WITH THE LATEST VERSIONS OF NFPA 13

AND VA FIRE PROTECTION DESIGN GUIDE.

9. DO NOT INSTALL SPRINKLER HEADS OR PIPING ABOVE

TELECOMMUNICATION RACKS WHERE FEASIBLE BUT STILL

IN ACCORDANCE WITH NFPA 13.

1/4" = 1'-0"3

RM 5A-7 - FLOOR PLAN TR

7/18/25 103 of 713

FACP

B

B

B

B

B

B

B

B

B

B

B

AA

A

A

A

A

A

A

A

A

A

A

A

A A

B B

A A

B B

AREA SHOWN

B

A

C

D

E

F

G

H

I J

K

L

M

N P

O

Q

R S

T

U

V

PANEL SHOP 9

PANEL SHOP 8

30KVA XFMR

PANEL M-1

MDP 7

FACP

PANEL A

BLDG 10

PANEL D

007-CU-01-5A-7

007-011-5A-7A-10,12

007-P-02

007-P-01

FIRE ALARM PANEL

PRIMARY BONDING

BUSBAR(PBB) E-504

007-011EP401

007-011EP401

007-011EP401

007-011EP401

007-011-5A-7A-14

FURNITURE STORAGE

1-10

BATHROOM

1A-10

BATHROOM

8C-11

AREA MAINT.

8A-11

MEETING ROOM

8-11

STORAGE / HWH

8B-11

BREAK ROOM

7-11

BATHROOM

6-11 BATHROOM

5-11

IT CLOSET

1B-11

STORAGE

4A-11

ELECTRICAL ROOM

4-11

OFFICE

3-11

BATHROOM

2A-11

BATHROOM

3A-11

STORAGE ROOM

ELECTRONICS

1A-11

OFFICE

2-11

CORRIDOR

1-11

ROOM

4A-9

PLUMBING SHOP

6-8

ELECTRICAL STORAGE

7-7

STORAGE

6-7

OFFICE

5-7

TR

5A-7

ELECTRICAL ROOM

4-7

BREAK ROOM

3-7

BATHROOM/SHOWER

2-7

MECHANICAL SHOP

1-7

MECHANICAL SHOP

1-8

OFFICE

2-8

BATHROOM/SHOWER

3-8

BATHROOM/SHOWER

2-9

BREAK ROOM

4-8

DDC CONTROLS

5-8

LOCKER BREAK ROOM

4-9

BREAK ROOM

3-9

CARPENTER SHOP

1-9

OFFICE

7-9

OFFICE

6-9

PAINT ROOM

5-9

OFFICE

7-8

OFFICE

8-9

TOOL CRIB

9-9

MECH STORAGE

6A-8

SPRINKLER

6A-9

OPEN FOR EQUIPMENT

STORAGE

PARKING LOT LIGHTS5

PARKING LOT LIGHTS6

BLDG 007, 008 & 009

BLDG 010 & 011

'A' SIDE POWER, CONCEALED WHERE POSSIBLE

'B' SIDE POWER, CONCEALED WHERE POSSIBLE

'A' SIDE POWER, UNDERGROUND /UNDERFLOOR

'B' SIDE POWER, UNDERGROUND /UNDERFLOOR

PROVIDED TO INDICATE 'A' AND 'B' SIDE SOURCED POWER FEEDERS.

REFERENCE GENERAL SYMBOL LEGEND FOR ADDITIONAL INFORMATION.

LEGEND

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/2

/2

:1

:0

A

M

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /E

E

B L D

G

-8 -9

-1 -1

.r v t

007-011EP101

BLDG 007-011 - LEVEL 01 - ELECTRICAL PLAN

007-011

JPB/WNM BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

- 1/8" = 1'-0"

1 BLDG 007-011 - LEVEL 01 - ELECTRICAL PLAN 4'0 8' 16'

TRUE

NORTH

KEY PLAN

KEY NOTES

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.

ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE

DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE

NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO

ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN

ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH

VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL PROVIDE PULL BOXES FOR ALL FEEDERS WHERE FEEDER RUNS

EXCEED 250FT OR HAVE MORE THAN 270 DEGREES OF TOTAL BEND. PULL BOX

PLACEMENT AND SIZING BY CONTRACTOR. COORDINATE PULL BOX LOCATIONS WITH

ALL OBSTRUCTIONS, TRADES, AND VA AS REQUIRED.

9. ALL CONDUIT SHALL BE CONCEALED IN WALLS OR ABOVE ACCESSIBLE T-BAR

CEILINGS UNLESS OTHERWISE NOTED.

10. COORDINATE ALL CEILING REMOVAL AND REPLACEMENT WITH THE GENERAL

CONTRACTOR FOR COMPLETION OF WORK.

TRUE

NORTH

GENERAL NOTES

PROVIDE CONVENIENCE RECEPTACLE, 20A, 120V, GFCI, HOUSED IN WEATHER RATED

DIE-CAST ALUMINUM WHILE-IN-USE COVER.

EXISTING EQUIPMENT SHALL BE MODIFIED. REFERENCE ONE-LINE DIAGRAMS FOR

ADDITIONAL INFORMATION.

PROVIDE TBC AS SHOWN. REFERENCE TELECOM BONDING RISER DIAGRAM ON SHEET

EG601 FOR ADDITIONAL INFORMATION.

PROVIDE TELECOMMUNICATIONS BONDING BACKBONE (TBB) TO CONNECT PBB TO

SBB(S). REFERENCE TELECOM BONDING RISER DIAGRAM ON SHEET EG601 FOR

ADDITIONAL INFORMATION.

EXISTING CIRCUIT(S) SHALL BE REFED FROM PANELBOARD "M1" AS SHOWN IN

KEYNOTE '6' ON THIS SHEET. DEMOLISH EXISTING CONDUCTOR AND ABOVE GROUND

RACEWAY BACK TO SOURCE AS INDICATED. REFERENCE ONE-LINE DIAGRAMS FOR

ADDITIONAL INFORMATION.

RE-FEED EXISTING CIRCUIT(S) AS INDICATED. PROVIDE RACEWAY AND CONDUCTORS

AS REQUIRED. REFERENCE ONE-LINE DIAGRAMS FOR ADDITIONAL INFORMATION.

Revisions: Date:

J

A

A

A

A

A

A

A

A

A

A

A

AAA

A

A

A

A

B B

B

B

B

B

B

B

B

Mo

A A

B B

A A

B B

AREA SHOWN

P Q

DATA RACK

FIBER OPTIC

PANEL

TELEPHONE

TERMINAL BOARD

PANEL E-1

(FLUSH MOUNTED)

TYP.

ACCESS CONTROL

PANEL

EXISTING SECONDARY

BONDING BUSBAR

OFFICE

5-7

144 SFTR

5A-7

EXISTING AC UNIT 12

P Q

OFFICE

5-7

144 SF

E-502

PANEL E-1

(FLUSH MOUNTED)

FIBER OPTIC

PANEL

TELEPHONE

TERMINAL BOARD

ACCESS CONTROL

PANEL

007-P-01

007-P-02

A

007-VRF-01-5A-7

E-504

007-011-5A-7A-30

007-011-5A-7A

007-011-5A-7A-29

007-011-5A-7A-2

007-TR-02

D D

DATA RACK,

TYP.

007-VRF-02-5A-7

TR

5A-7

119 SF

007-011-5A-7A-13,15

007-011-5A-7A-19,21

TO PANELBOARD "MDP 7"

(SEE SHEET 007-011EP101)

TO PANELBOARD "MDP 7"

(SEE SHEET 007-011EP101)

TO PRIMARY BONDING BUSBAR

(SEE SHEET 007-011EP101)

P Q

TYP.

OFFICE

5-7

144 SF

TR

5A-7

P Q

OFFICE

5-7

144 SF

TR

5A-7

119 SF

E-505

TYP.

E-505

007-011-5A-7A

007-011-5A-7A-5

DATA RACK,

TYP.

L1E

L1E

5A-7

5-7

'A' SIDE POWER, CONCEALED WHERE POSSIBLE

'B' SIDE POWER, CONCEALED WHERE POSSIBLE

'A' SIDE POWER, UNDERGROUND /UNDERFLOOR

'B' SIDE POWER, UNDERGROUND /UNDERFLOOR

PROVIDED TO INDICATE 'A' AND 'B' SIDE SOURCED POWER FEEDERS.

REFERENCE GENERAL SYMBOL LEGEND FOR ADDITIONAL INFORMATION.

LEGEND

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/2

/2

:1

:0

A

M

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /E

E

B L D

G

-8 -9

-1 -1

.r v t

007-011EP401

BLDG 007-011- LEVEL 01 - ENLARGED

ELECTRICAL PLANS

007-011

JPB/WNM BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

KEY NOTES

KEY PLAN

GENERAL NOTES

1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD

DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY

NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.

2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.

ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE

DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF

DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.

5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO

PERFORMING WORK.

7. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO

ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL

REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL

CONFORM WITH VA STANDARDS.

8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

FOR TR ROOM PANEL SCHEDULES REFERENCE THE TYPICAL A AND B POWER

SCHEDULE CLASSIFICATION FOR ADDITIONAL INFORMATION.

10. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

11. ALL CONDUIT SHALL BE CONCEALED IN WALLS OR ABOVE ACCESSIBLE T-BAR

CEILINGS UNLESS OTHERWISE NOTED.

12. COORDINATE ALL CEILING REMOVAL AND REPLACEMENT WITH THE GENERAL

CONTRACTOR FOR COMPLETION OF WORK.

PROJECT

NORTH

EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL

BE DEMOLISHED BACK TO SOURCE.

SOURCE A POWER PANELBOARD "007-011-5A-7A".

VRF UNIT(S). PROVIDE RACEWAYS AND CONDUCTORS PER MANUFACTURER'S

REQUIREMENTS. REFERENCE MECHANICAL DRAWINGS AND COORDINATE WITH

MECHANICAL CONTRACTOR AS REQUIRED.

OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.

FURNISH AND INSTALL POWER SUPPLY WITHIN JUNCTION BOX AS INDICATED ABOVE

ACCESSIBLE CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER

SUPPLY FOR EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE

DOORS WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS

REQUIRED. SEE REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH

ARCHITECT AND DOOR INSTALLER.

EXISTING EQUIPMENT TO BE RELOCATED AS SHOWN IN DETAIL '4'.

RELOCATED EQUIPMENT. CIRCUIT LIGHT TO EXISTING SWITCH. EXTEND EXISTING

CONDUIT AND WIRE AS REQUIRED.

EXISTING BUSBAR TO BE DEMOLISHED AND REPLACED. CONTRACTOR SHALL

PRESERVE AND PROTECT EXISTING CONNECTIONS FOR RE-TERMINATION.

PROVIDE SECONDARY BONDING BUSBAR. PROVIDE CONDUCTOR TO EXTEND

EXISTING CONNECTIONS TO BUSBAR AS REQUIRED. REFERENCE

TELECOMMUNICATIONS BONDING RISER DIAGRAM ON SHEET EG601 FOR ADDITIONAL

INFORMATION.

CIRCUIT SWITCH TO EXISTING CIRCUIT DEMOLISHED IN DETAIL '3'. EXTENT CONDUIT

AND WIRE AS REQUIRED.

PROVIDE TELECOMMUNICATIONS BONDING BACKBONE (TBB) TO CONNECT PBB TO

SBB. REFERENCE TELECOM BONDING RISER DIAGRAM ON SHEET EG601 FOR

ADDITIONAL INFORMATION.

DEMOLISH EXISTING DUCTLESS AC UNIT AND ASSOCIATED CONDENSING UNIT.

ASSOCIATED CONDUIT AND WIRE SHALL BE DEMOLISHED BACK TO SOURCE.

REFERENCE MECHANICAL PLANS FOR ADDITIONAL INFORMATION.

1/2" = 1'-0"007-011EP101

1 RM 5A-7 & 5-7 - DEMOLITION ELECTRICAL PLAN

1/2" = 1'-0"007-011EP101

2 RM 5A-7 - ELECTRICAL PLAN

1/2" = 1'-0"007-011EP101

3 RM 5A-7 & 5-7 - DEMOLITION LIGHTING PLAN

1/2" = 1'-0"007-011EP101

4 RM 5A-7 - LIGHTING PLAN

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

Revisions: Date:

CBL-MDP7

2 runs 350 kcmil 1000 ft

PD-MCB-MDP7

SQUARE D

MG

600A

PD-7A

SQUARE D

FH

100 AF

100 AT

PD-7-CPU

SQUARE D

FH

100 AF

100 AT

PD-7-M1

SQUARE D

JG

250 AF

250 AT

PD-8

SQUARE D

FH

100 AF

100 AT

PD-9

SQUARE D

FH

100 AF

100 AT

PD-A_2

SQUARE D

FH

100 AF

100 AT

PD-D

SQUARE D

FH

100 AF

100 AT

CBL-7A

1 runs

1 AWG

65 ft

CBL-7-CPU

1 runs

1 AWG

65 ft

CBL-7-M1

1 runs 250 kcmil 20 ft

CBL-8

1 runs

1 AWG

40 ft

CBL-9

1 runs

1 AWG

120 ft

CBL-A_2

1 runs

1 AWG

140 ft

CBL-D

1 runs

1 AWG

180 ft

PD-MDP-7A

SQUARE D

QD

200 AF

200 AT

PD-MDP-7E1

SQUARE D

Q2

100 AF

100 AT

BUS-007-7A

208 V 225 A

BUS-007-E1

208 V 100 A

BUS-008-SHOP-8

208 V 100 A

BUS-009-SHOP-9

208 V 100 A

PD-MCB-A_1

CUTLER-HAMMER

EDB

100 AF

100 AT

BUS-007-A

208 V 100 A

PD-MCB-D

CUTLER-HAMMER

EDB

100 AF

100 AT

BUS-007-D

208 V 100 A

TO BUS-129-SWBD-129

(SHEET 028EP601)

20A/1P 40A/2P 50A/2P 30A/1P

PANELBOARD "MDP 7", 600A, 208/120V, 3PH, 4W

60A/3P 60A/3P

AHU-1 AHU-2

60A/3P

AHU-3

60A/3P

AHU-4

60A/3P

AHU-5

20A/1P

EXHAUST

FAN

20A/2P 70A/2P

EXHAUST

FAN

EXHAUST

FAN

EXHAUST

FAN

EXHAUST

FAN

20A/1P 20A/1P 20A/1P 20A/1P

CNC

ROUTER

BLDG #9

PLASMA

CUTTER

SHOP 8

PANELBOARD "M1", 250A, 208/120V, 3PH, 4W

PD-MDP-7M1

SQUARE D

JD

250 AF

250 AT

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

100A/3P

007-P-02

PANELBOARD

"007-011-5A-7A"

100A 208/120V

3PH

SPD

30A/3P

007-P-01

3P SPACE 20A/1P

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLE

CIRCUIT

(QTY=14)

NEMA L21-30R

30A, 208V

LOCKING

TR 5A-7

SIDE B

(QTY=12)

CBL-MDP7

2 runs 350 kcmil 1000 ft

PD-MCB-MDP7

SQUARE D

MG

600A

PD-7A

SQUARE D

FH

100 AF

100 AT

PD-7-CPU

SQUARE D

FH

100 AF

100 AT

PD-7-M1

SQUARE D

JG

250 AF

250 AT

PD-8

SQUARE D

FH

100 AF

100 AT

PD-9

SQUARE D

FH

100 AF

100 AT

PD-A_2

SQUARE D

FH

100 AF

100 AT

PD-D

SQUARE D

FH

100 AF

100 AT

CBL-7A

1 runs

1 AWG

65 ft

CBL-7-CPU

1 runs

1 AWG

65 ft

CBL-7-M1

1 runs 250 kcmil 20 ft

CBL-8

1 runs

1 AWG

40 ft

CBL-9

1 runs

1 AWG

120 ft

CBL-A_2

1 runs

1 AWG

140 ft

CBL-D

1 runs

1 AWG

180 ft

PD-MDP-7A

SQUARE D

QD

200 AF

200 AT

PD-MDP-7E1

SQUARE D

Q2

100 AF

100 AT

BUS-007-7A

208 V 225 A

BUS-007-E1

208 V 100 A

BUS-008-SHOP-8

208 V 100 A

BUS-009-SHOP-9

208 V 100 A

PD-MCB-A_1

CUTLER-HAMMER

EDB

100 AF

100 AT

BUS-007-A

208 V 100 A

PD-MCB-D

CUTLER-HAMMER

EDB

100 AF

100 AT

BUS-007-D

208 V 100 A

TO BUS-129-SWBD-129

(SHEET 028EP601)

20A/1P 40A/2P 50A/2P 30A/1P

PANELBOARD "MDP 7", 600A, 208/120V, 3PH, W

60A/3P 60A/3P

AHU-1 AHU-2

60A/3P

AHU-3

60A/3P

AHU-4

60A/3P

AHU-5

20A/1P

EXHAUST

FAN

20A/2P 70A/2P

EXHAUST

FAN

EXHAUST

FAN

EXHAUST

FAN

EXHAUST

FAN

20A/1P 20A/1P 20A/1P 20A/1P

CNC

ROUTER

BLDG #9

PLASMA

CUTTER

SHOP 8

PANELBOARD "M1", 250A, 208/120V, 3PH, 4W

PD-MDP-7M1

SQUARE D

JD

250 AF

250 AT

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

CONTINUE TO

EXISTING

LIGHTING AND

RECEPTACLES

(QTY=15)2 1P SPACE

(QTY=2)

3P SPACE

3P SPACE

(QTY=13)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/2

/2

:3

:4

A

M

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /V

A H

A M

P T

O N

L e g e n d s

G e n e ra l N o te s

D ia g ra m s a n d

D e ta ils .r v t

007-011EP601

BLDG 007-011 - ONE-LINE DIAGRAM

007-011

JPB/WNM BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

- NTS

2 BLDG 007-011 - ONE-LINE DIAGRAM - REVISED

1. CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS. ANY

DISCREPANCIES FOUND SHALL BE REPORTED TO THE ENGINEER.

2. CONTRACTOR SHALL PROVIDE ALL SHUTDOWN PLANS, TEMPORARY POWER

PLANS,AND PHASING PLANS FOR VA AND ENGINEER REVIEW AND APPROVAL

PRIOR TO COMMENCING WORK. ALL PLANS SHALL BE SUBMITTED FOR REVIEW

30 DAYS PRIOR TO IMPLEMENTATION.

3. SHORT CIRCUIT CALCULATIONS BASED ON VA PROVIDED AS-BUILTS.

4. REFERENCE SHEET(S) "007-011E-702" THROUGH "007-011E-703" FOR ELECTRICAL

EQUIPMENT LOAD SCHEDULES.

5. REFERENCE SHEET "007-011E-701" FOR ALL CONDUIT AND WIRING

INFORMATION.

6. COMPLETE BUILDING ONE-LINE PROVIDED FOR INFORMATIONAL PURPOSES

AND AS-BUILDING PURPOSES.

GENERAL NOTES

KEY NOTES

EXISTING PANEL TO BE MODIFIED. SEE ASSOCIATED REVISED ONE-LINE

DIAGRAM FOR ADDITIONAL INFORMATION.

(1) 20A/1P CIRCUIT SHALL BE DISCONNECTED AND REFED FROM PANELBOARD

"M1". REFERENCE KEY NOTE 2 ON THIS SHEET FOR ADDITIONAL INFORMATION.

REFERENCE ASSOCIATED PANEL SCHEDULE FOR ADDITIONAL INFORMATION.

EXISTING SPACE TO BE UTILIZED TO FEED ADDITIONAL CIRCUIT. REFERENCE

REVISED ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

EXISTING BRANCH CIRCUIT TO BE DISCONNECTED FROM PANEL "MDP 7" AND

REFED FROM PANEL "M1". PROVIDE CIRCUIT BREAKER IN EXISTING SPACE TO

FEED LOAD. REFERENCE KEY NOTE 1 ON THIS SHEET FOR ADDITIONAL

INFORMATION.

POWER DATA RETRIEVAL POINT NOTES

POWER DATA RETRIEVAL POINT: EXISTING PANELBOARD ''MDP 7'' MAIN HAS

BEEN METERED. REFERENCE EQUIPMENT LOAD SCHEDULE VIA BUILDING 07

700-SERIES SCHEDULE SHEET FOR ADDITIONAL INFORMATION.

- NTS

1 BLDG 007-011 - ONE-LINE DIAGRAM - EXISTING

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/2

/2

:3

:3

A

M

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /V

A H

A M

P T

O N

L e g e n d s

G e n e ra l N o te s

D ia g ra m s a n d

D e ta ils .r v t

007-011E-701

BLDG 007-011 - ELECTRICAL PANELBOARD

AND CONDUIT AND WIRE SCHEDULES

007-011

JPB/WNM BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

1. CONTRACTOR SHALL UPDATE ALL PANEL CIRCUIT DIRECTORIES TO INDICATE IN

ANY AND ALL CHANGES; ALL REVISED CIRCUIT DIRECTORIES SHALL BE

TYPEWRITTEN.

2. ALL DIGITAL POWER METERS (DPM) AND SURGE PROTECTIVE DEVICES (SPD)

ARE INTEGRAL TO ELECTRICAL DISTRIBUTION EQUIPMENT, UNLESS

OTHERWISE NOTED.

GENERAL NOTES

KEY NOTES

UTILIZE EXISTING SPACE TO PROVIDE CIRCUIT BREAKER AS INDICATED.

EXISTING LOAD RELOCATED FROM PANELBOARD "MDP-7". REFEED AS

INDICATED. REFERENCE ASSOCIATED ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

EXISTING PANELBOARD OR SWITCHBOARD TO BE MODIFIED AS INDICATED BY

BLACK TEXT. ALL GRAY TEXT SHOWS AS-BUILT EXISTING CONDITIONS.

SCHEDULE IS PROVIDED TO SHOW CIRCUITING INFORMATION ONLY.

REFERENCE ASSOCIATED LOAD SCHEDULE FOR OVERALL PANEL LOAD.

UP

UP

WAP

WAPWAP

WAP

WAP

WAP

WAP

W

WAP

AB TTS

AB TTS

AB TTS

AB TTS

AB TTS

AB TTS

WAP

WAP

WAP

WAP WAP

WAP

WAP

WAP

AB TTS

WAP

AREA SHOWN

B

A

C

D

E

F

G

H

I J

K

L

M

N P

O

Q

R S

T

U

V

OPEN FOR EQUIPMENT STORAGE

007-011TN401a

007-011TN401a

TYP.

DATA OUTLETS AND DEVICES IN THIS AREA SHALL BE

SERVED FROM TELECOMMUNICATIONS ROOM 5A-7.

007-011TN401b

007-011TN401a

007-011TN401b

007-011TN401a

DD2

DD2

DD2

DD2

DD4

DD4

DD2

DD3

DD2

DD2

DD2

DD2

DD2

DD2

DD4

DD2 DD4

2 DD2

DD2

DD2DD2

DD2DD2DD2DD2

DD2 DD2

DD2

DD2

DD2

DD3

DD4

TYP.

DD2

DD2 DD2DD2

DD2

DD2

DD2

ALERTUS DEVICE 4

DDC CONTROL PANEL 5

N2

N2

N2

N2 N2

N2

N2 N2

N2

N2

N2

N2N2

N2 N2N2

N2

N2

N2 N2

N2 N2

N2 N2

N2 N2

N2 N2

N2

N2

N2

N2

N2

N2

N2

N2

N2

N2

N2

DD2

N2

N2

DD2

N2

DD2

N2DD2

DD2

N2

DD2

N2 4

N4

N4

007-011TN401b

007-011TN401b

N4N4 N4

DD3

N2

DD3

N2

DD3

N2

DD3

N2

DD3

N2

DD3

N2 N2

DD3

DD2

N2

DD2

N2

PTZ CAMERA

THE CABLE & JACKS AT BOTH ENDS

FOR THESE 6 WAO'S HAVE BEEN

UPGRADED TO CAT6A. INSERT

JACKS INTO NEW PATCH PANEL

180° CAMERA

FURNITURE STORAGE

1-10

BATHROOM

1A-10

BATHROOM

8C-11

AREA MAINT.

8A-11

MEETING ROOM

8-11

STORAGE / HWH

8B-11

BREAK ROOM

7-11

BATHROOM

6-11 BATHROOM

5-11

IT CLOSET

1B-11

STORAGE

4A-11

ELECTRICAL ROOM

4-11

OFFICE

3-11

BATHROOM

2A-11

BATHROOM

3A-11

STORAGE ROOM

ELECTRONICS

1A-11

OFFICE

2-11

CORRIDOR

1-11

ROOM

4A-9

PLUMBING SHOP

6-8

ELECTRICAL STORAGE

7-7

STORAGE

6-7

OFFICE

5-7TR

5A-7

ELECTRICAL ROOM

4-7

BREAK ROOM

3-7

BATHROOM/SHOWER

2-7

MECHANICAL SHOP

1-7

MECHANICAL SHOP

1-8

OFFICE

2-8

BATHROOM/SHOWER

3-8

BATHROOM/SHOWER

2-9

BREAK ROOM

4-8

DDC CONTROLS

5-8

LOCKER BREAK ROOM

4-9

BREAK ROOM

3-9

CARPENTER SHOP

1-9

OFFICE

7-9

OFFICE

6-9

PAINT ROOM

5-9

OFFICE

7-8

OFFICE

8-9

TOOL CRIB

9-9

MECH STORAGE

6A-8

SPRINKLER

6A-9

OPEN FOR EQUIPMENT

STORAGE

Y

D# N#

Y

D# N#

OUTLET, DATA OR VOIP TELEPHONE. THE FOLLOWING INFORMATION

INDICATED ON THE SYMBOL:

"#" = QUANTITY OF OUTLET PORTS.

"D" = EXISTING CABLES TO BE DEMOLISHED.

"N" = REPLACEMENT CABLES TO BE PROVIDED.

REFERENCE SHEET TNG002 FOR ADDITIONAL INFORMATION.

BLDG 007, 008 & 009

BLDG 010 & 011

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/0

/2

:1

:3 a m

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /E

E

B L D

G

-8 -9

-1 -1

.r v t

007-011TN101

BLDG 007-011 - LEVEL 01 -

TELECOMMUNICATIONS PLAN

007-011

KG BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

GENERAL NOTES

- 1/8" = 1'-0"

1 BLDG 007-011 - LEVEL 01 - TELECOMMUNICATIONS PLAN 4'0 8' 16'

PROJECT

NORTH

PROVIDE TELECOMMUNICATIONS OUTLET WITH PORT QUANTITY SHOWN TO REPLACE

EXISTING TELECOMMUNICATIONS OUTLET; EXISTING OUTLET CONDUIT SHALL REMAIN

AND BE UTILIZED TO FEED NEW CABLING; REFERENCE SHEET DETAIL '1' ON SHEET

TN501 AND THE GENERAL NOTES ON THIS SHEET FOR ADDITIONAL INFORMATION.

COORDINATE WITH VA FOR EXACT OUTLET PLACEMENT.

EXISTING WIRELESS ACCESS POINT TO BE RE-FED WITH (2) CAT6A CABLES.

PROVIDE CABLE TRAY AS INDICATED. REFERENCE DETAIL "6" ON SHEET TN501 AND

TELECOMMUNICATIONS WAO AND CABLE TRAY SCHEDULE ON SHEET TN701. WHERE

WALL EXTENDS TO CEILING, CABLE TRAY SHALL STOP AND TRANSITION TO

HORIZONTAL FIRE STOP SLEEVES [(2) 4", MINIMUM]. WHERE EXISTING CABLE TRAY IS

PRESENT, IT SHALL BE DEMOLISHED AND REPLACED AS INDICATED. EXISTING

SLEEVES MAY BE UTILIZED IF SUITABLE FOR REUSE, BUT NOT IN PLACE OF FIRE STOP

SLEEVES AS MENTIONED ABOVE. WHERE CLEARANCES OR OBSTRUCTIONS DO NOT

PERMIT INSTALLATION OF CABLE TRAY, PROVIDE J-HOOKS AS REQUIRED FOR CABLE

DISTRIBUTION.

EXISTING AB TTS (ALERTUS BEACON TEXT TO SPEECH DEVICES) TO BE RECABLED

WITH (1) CAT6A CABLE AS REQUIRED. COORDINATE WITH VA FOR EXACT LOCATION.

EXISTING DDC CONTROL PANEL TO BE RECABLED WITH (1) CAT6A CABLE AS

REQUIRED. COORDINATE WITH VA FOR EXACT LOCATION.

PROVIDE (2) 4" CONDUITS INSTALLED OVERHEAD WITH FIRE PROOFING AS REQUIRED.

CONDUITS SHALL PROVIDE PATHWAY FOR HORIZONTAL CABLING BETWEEN

ACCESSIBLE CEILING SPACES OF BUILDING 7 AND BUILDING 11. ALL HORIZONTAL

CABLING EXTENDING BETWEEN BUILDING 7 AND 11 SHALL BE OUTDOOR RATED.

KEY PLAN

KEY NOTES

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE

DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE

NOTED.

2. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

3. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

4. ALL TELECOMMUNICATIONS CABLING CATEGORY 6 AND BELOW SHALL BE REMOVED

AND REPLACED WITH CAT6A PORTS AND CABLE QUANTITIES INDICATED, UNLESS

NOTED OTHERWISE.

5. TELECOMMUNICATIONS CABLES SHALL BE ROUTED IN EXISTING PATHWAY VACATED

BY EXISTING CABLING. PROVIDE RACEWAYS TO EXTEND TO ASSOCIATED TR.

6. A TELECOMMUNICATIONS OUTLET UPGRADE SHALL INCLUDE, BUT IS NOT LIMITED TO

REMOVING AND DISPOSING EXISTING DEVICES AND CABLES; PROVIDING ALL LABOR,

MATERIALS, TOOLS, TEST INSTRUMENTS, AND CONSUMABLES REQUIRED FOR THE

INSTALLATION, TERMINATION, TESTING, LABELING, AND CERTIFICATION OF A FULLY

FUNCTIONAL CATEGORY 6A OUTLET WITH THE PORT QUANTITY INDICATED.

7. WHERE NEW DATA OUTLETS ARE BEING PROVIDED AND EXISTING DATA OUTLET

CURRENTLY DOES NOT EXIST, PROVIDE (1) 1" CONDUIT FROM NEW BACKBOX TO

ACCESSIBLE CEILING SPACE TO SECURELY ROUTE DATA CABLING FROM OUTLET TO

TR VIA CABLE TRAY. IF CABLE TRAY IS NON-EXISTENT, EXTEND RACEWAY FROM

OUTLET TO TR AS REQUIRED.

8. PROVIDE PULL BOXES SIZED PER ANSI/TIA-569 AT 100-FT INTERVALS IN STRAIGHT

CONDUIT RUNS, OR CONDUIT CONTAINING BENDS TOTALING MORE THAN 180

DEGREES.

9. PROVIDE CONDUITS AND SLEEVES AS REQUIRED FOR ROUTING AND INSTALLATION

OF HORIZONTAL AND BACKBONE CABLING. PROVIDE FIRE-STOP MATERIALS TO SEAL

IN AND AROUND CONDUIT PER CODE. REFER TO ARCHITECTURAL DRAWINGS FOR

PARTITION TYPES AND WALL HEIGHTS.

10. OUTLET LOCATIONS ARE APPROXIMATE. DETERMINE EXACT LOCATIONS IN FIELD;

DOCUMENT VARIANCES BASED ON AS-BUILT DRAWINGS.

11. THE CONTRACTOR SHALL BID AND INSTALL CAT6A CABLE WITH AN OD NOT GREATER

THAN 0.250 INCH (6.35mm) (4) CAT6A CABLES WITH AN 0.250 INCH (6.35mm) OD OR

SMALLER CAN BE INSTALLED IN A ¾” CONDUIT SUPPORTING A 40% FILL RATIO.

12. CONTRACTOR TO BID AN ADDITIONAL 10% OF THE TOTAL NUMBER OF WAO's PER

FLOOR. A WAO IS DEFINED AS TWO CAT6A OUTLETS.

13. (1) DDC CONTROLLER WILL BE FED WITH (1) CAT6A CABLE FROM TR5A-7.

CONTRACTOR TO COORDINATE LOCATION OF DDC CONTROLLER WITH THE STATION.

TRUE

NORTH

GENERAL NOTES

Revisions: Date: 108 of 713

W

WW

X

C

D X

W

360°

WAP WAP

AREA SHOWN

P Q

DATA RACK

FIBER OPTIC

PANEL

TELEPHONE

TERMINAL BOARD

PANEL E-1

(FLUSH MOUNTED)

ACCESS CONTROL

PANEL

EXISTING SECONDARY

BONDING BUSBAR

OFFICE

5-7

144 SF

DD2

TR

5A-7

119 SF

DD2

DD2

P Q

O

P Q

ACCESS CONTROL

PANEL

FIBER OPTIC

PANEL

TELEPHONE

TERMINAL BOARD

PANEL E-1

(FLUSH MOUNTED)

007-011-5A-7A

TN502

TN503

OFFICE

5-7

144 SF

TR

5A-7

119 SF

N2

C

TYP.

9DATA RACK,

TYP.

007-VRF-01-5A-7

007-VRF-02-5A-7

N2

N2

SECONDARY

BONDING BUSBAR

P Q

TYP.

TYP.

OFFICE

5-7

144 SF

TR

5A-7

119 SF

5A-7

5-7

P Q

TYP.

TN501

OFFICE

5-7

144 SF

TR

5A-7

119 SF

TYP.

TN501

DATA RACK,

TYP.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/0 /2

:2

:5 p m

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /E

E

B L D

G

-8 -9

-1 -1

.r v t

007-011TN401a

BLDG 007-011- LEVEL 01 - ENLARGED

TELECOMMUNICATIONS PLANS

007-011

KG BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

KEY NOTES

KEY PLAN

GENERAL NOTES

PROJECT

NORTH

1/2" = 1'-0"007-011TN101

1 RM 5A-7 & 5-7 - DEMOLITION FLOOR PLAN

1/2" = 1'-0"007-011TN101

2 RM 5A-7 - TELECOMMUNICATIONS PLAN

1/2" = 1'-0"007-011TN101

3 RM 5A-7 & 5-7 - DEMOLITION OVERHEAD PLAN

1/2" = 1'-0"007-011TN101

4 RM 5A-7 - OVERHEAD PLAN

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

EXISTING DATA RACK TO BE DECOMMISIONED BY VA. CONTRACTOR SHALL

COORDINATE WITH VA AS REQUIRED.

EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED RACEWAYS AND CABLING

SHALL BE DEMOLISHED BACK TO SOURCE.

EXISTING HORIZONTAL CABLING SLEEVE TO BE PRESERVED. EXISTING FIBER OPTIC

AND/OR EXISTING VERTICAL CABLING RELATED TO EXISTING TR RACKS TO BE

DEMOLISHED.

EXISTING VERTICAL CABLING SLEEVE TO BE PRESERVED. EXISTING FIBER OPTIC

AND/OR EXISTING VERTICAL CABLING RELATED TO EXISTING TR RACKS TO BE

DEMOLISHED.

EXISTING CABLE TRAY TO BE DEMOLISHED.

PROVIDE CONDUIT (4", MINIMUM) WITH APPROPRIATE FIRE-PROOFING AND CAULKING

AS REQUIRED TO EXTEND FROM LEVEL 01 ACCESSIBLE CEILING TO MEZZANINE

ACCESSIBLE CEILING. CONDUIT PROVIDED TO SERVE HORIZONTAL CABLING SERVING

WAOs FROM TR AS INDICATED ON PLANS.

PROVIDE (2)-DOOR ACCESS CONTROL PANEL TO SERVE ALL PACS DOOR SECURITY

EQUIPMENT FOR THIS TR ROOM. PROVIDE ALL REQUIRED CONNECTIONS,

PROGRAMMING, POWER SUPPLIES, AND COMPONENTS TO PROVIDE A COMPLETE

AND FULLY FUNCTIONAL SYSTEM. REFERENCE SPECIFICATION "28 13 00 - PHYSICAL

ACCESS CONTROL SYSTEM" FOR ADDITIONAL INFORMATION.

EXISTING WIRE ACCESS POINT TO BE RE-FED WITH (2) CAT6A CABLES.

PROVIDE TELECOMMUNICATIONS OUTLET WITH PORT QUANTITY SHOWN TO REPLACE

EXISTING TELECOMMUNICATIONS OUTLET; EXISTING OUTLET CONDUIT SHALL REMAIN

SHALL REMAIN AND BE UTILIZED TO FEED NEW CABLING; REFERENCE DETAIL '1' ON

SHEET TN501 AND THE GENERAL NOTES ON THIS SHEET FOR ADDITIONAL

INFORMATION. COORDINATE WITH VA FOR EXACT OUTLET PLACEMENT.

WIRE BASKET CABLE TRAY.

Revisions: Date:

1. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

2. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

3. ALL TELECOMMUNICATIONS CABLING CATEGORY 6 AND BELOW SHALL BE REMOVED

AND REPLACED WITH CAT6A PORTS AND CABLE QUANTITIES INDICATED, UNLESS

NOTED OTHERWISE.

4. TELECOMMUNICATIONS CABLES SHALL BE ROUTED IN EXISTING PATHWAY VACATED

BY EXISTING CABLING. PROVIDE RACEWAYS TO EXTEND TO ASSOCIATED TR.

5. A TELECOMMUNICATIONS OUTLET UPGRADE SHALL INCLUDE, BUT IS NOT LIMITED TO

REMOVING AND DISPOSING EXISTING DEVICES AND CABLES; PROVIDING ALL LABOR,

MATERIALS, TOOLS, TEST INSTRUMENTS, AND CONSUMABLES REQUIRED FOR THE

INSTALLATION, TERMINATION, TESTING, LABELING, AND CERTIFICATION OF A FULLY

FUNCTIONAL CATEGORY 6A OUTLET WITH THE PORT QUANTITY INDICATED.

6. WHERE NEW DATA OUTLETS ARE BEING PROVIDED AND EXISTING DATA OUTLET

CURRENTLY DOES NOT EXIST, PROVIDE (1) 1" CONDUIT FROM NEW BACKBOX TO

ACCESSIBLE CEILING SPACE TO SECURELY ROUTE DATA CABLING FROM OUTLET TO

TR VIA CABLE TRAY. IF CABLE TRAY IS NON-EXISTENT, EXTEND RACEWAY FROM

OUTLET TO TR AS REQUIRED.

7. PROVIDE CONDUITS AND SLEEVES AS REQUIRED FOR ROUTING AND INSTALLATION OF

HORIZONTAL AND BACKBONE CABLING. PROVIDE FIRE-STOP MATERIALS TO SEAL IN

AND AROUND CONDUIT PER CODE. REFER TO ARCHITECTURAL DRAWINGS FOR

PARTITION TYPES AND WALL HEIGHTS.

8. ALL TELECOMMUNICATION ROOMS SHALL BE PROVIDED WITH FIRE-RATED PLYWOOD

BACKBOARDS. REFERENCE EXACT PLACEMENTS WITH ARCHITECTURE DRAWINGS AS

REQUIRED.

9. ANY LIVE SYSTEMS IN DEMO'D TR'S MUST REMAIN LIVE. CONTRACTOR TO

COORDINATE WITH THE STATION TO IDENTIFY SYSTEMS THAT ARE LIVE. IF SYSTEMS

ARE LIVE; INSTALL NEW CABLE FROM DEMO’D TR TO NEW TR. REFER TO DETAIL '3' ON

TN506.

10. RAIL KITS ARE PROVIDED BY THE GC FOR EQUIPMENT MOUNTED IN THE TR CHANNEL

RACKS.

11. LADDER RACK IN ALL TR'S WILL BE MOUNTED 6" OFF THE WALLS TO ACCOMMODATE

ELECTRICAL AND MECHNICAL EQUIPMENT.

W

W

AREA SHOWN

O

56 SF

IT CLOSET

1B-11

ACCESS CONTROL PANEL

ACCESS POWER CONTROLLER

PANEL

DATA RACK

TELEPHONE

TERMINAL

BOARD

EXISTING

BONDING

BUSBAR

O

56 SF

IT CLOSET

1B-11

ACCESS CONTROL PANEL

ACCESS POWER CONTROLLER

PANEL

TELEPHONE

TERMINAL

BOARD

EXISTING

BONDING

BUSBAR

1B-11

O

56 SF

IT CLOSET

1B-11

TYP.

TYP.

O

56 SF

IT CLOSET

1B-11

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/0

/2

:1

:4 a m

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /E

E

B L D

G

-8 -9

-1 -1

.r v t

007-011TN401b

BLDG 007-011- LEVEL 01 - ENLARGED

TELECOMMUNICATIONS PLANS

007-011

KG BCL/GPB

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

KEY NOTES

KEY PLAN

GENERAL NOTES

1/2" = 1'-0"007-011TN101

1 RM 1B-11 - DEMOLITION FLOOR PLAN

1/2" = 1'-0"007-011TN101

2 RM 1B-11 - TELECOMMUNICATIONS PLAN1'0 2' 4'

PROJECT

NORTH

PROJECT

NORTH

1/2" = 1'-0"007-011TN101

3 RM 1B-11 - DEMOLITION OVERHEAD PLAN

1/2" = 1'-0"007-011TN101

4 RM 1B-11 - OVERHEAD PLAN

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

1'0 2' 4'

PROJECT

NORTH

EXISTING DATA RACK TO BE DECOMMISIONED BY VA. CONTRACTOR SHALL

COORDINATE WITH VA AS REQUIRED.

EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED RACEWAYS AND CABLING

SHALL BE DEMOLISHED BACK TO SOURCE.

PROVIDE TELECOMMUNICATIONS OUTLET WITH PORT QUANTITY SHOWN TO REPLACE

EXISTING TELECOMMUNICATIONS OUTLET; EXISTING OUTLET CONDUIT SHALL REMAIN

SHALL REMAIN AND BE UTILIZED TO FEED NEW CABLING; REFERENCE DETAIL '1' ON

SHEET TN501 AND THE GENERAL NOTES ON THIS SHEET FOR ADDITIONAL

INFORMATION. COORDINATE WITH VA FOR EXACT OUTLET PLACEMENT.

EXISTING CABLE TRAY TO BE DEMOLISHED.

EXISTING VERTICAL CABLING SLEEVE TO BE PRESERVED. EXISTING FIBER OPTIC

AND/OR EXISTING VERTICAL CABLING RELATED TO EXISTING TR RACKS TO BE

DEMOLISHED.

Revisions: Date:

1. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

2. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

3. ALL TELECOMMUNICATIONS CABLING CATEGORY 6 AND BELOW SHALL BE REMOVED

AND REPLACED WITH CAT6A PORTS AND CABLE QUANTITIES INDICATED, UNLESS

NOTED OTHERWISE.

4. TELECOMMUNICATIONS CABLES SHALL BE ROUTED IN EXISTING PATHWAY VACATED

BY EXISTING CABLING. PROVIDE RACEWAYS TO EXTEND TO ASSOCIATED TR.

5. A TELECOMMUNICATIONS OUTLET UPGRADE SHALL INCLUDE, BUT IS NOT LIMITED TO

REMOVING AND DISPOSING EXISTING DEVICES AND CABLES; PROVIDING ALL LABOR,

MATERIALS, TOOLS, TEST INSTRUMENTS, AND CONSUMABLES REQUIRED FOR THE

INSTALLATION, TERMINATION, TESTING, LABELING, AND CERTIFICATION OF A FULLY

FUNCTIONAL CATEGORY 6A OUTLET WITH THE PORT QUANTITY INDICATED.

6. WHERE NEW DATA OUTLETS ARE BEING PROVIDED AND EXISTING DATA OUTLET

CURRENTLY DOES NOT EXIST, PROVIDE (1) 1" CONDUIT FROM NEW BACKBOX TO

ACCESSIBLE CEILING SPACE TO SECURELY ROUTE DATA CABLING FROM OUTLET TO

TR VIA CABLE TRAY. IF CABLE TRAY IS NON-EXISTENT, EXTEND RACEWAY FROM

OUTLET TO TR AS REQUIRED.

7. PROVIDE CONDUITS AND SLEEVES AS REQUIRED FOR ROUTING AND INSTALLATION OF

HORIZONTAL AND BACKBONE CABLING. PROVIDE FIRE-STOP MATERIALS TO SEAL IN

AND AROUND CONDUIT PER CODE. REFER TO ARCHITECTURAL DRAWINGS FOR

PARTITION TYPES AND WALL HEIGHTS.

8. ALL TELECOMMUNICATION ROOMS SHALL BE PROVIDED WITH FIRE-RATED PLYWOOD

BACKBOARDS. REFERENCE EXACT PLACEMENTS WITH ARCHITECTURE DRAWINGS AS

REQUIRED.

9. ANY LIVE SYSTEMS IN DEMO'D TR'S MUST REMAIN LIVE. CONTRACTOR TO

COORDINATE WITH THE STATION TO IDENTIFY SYSTEMS THAT ARE LIVE. IF SYSTEMS

ARE LIVE; INSTALL NEW CABLE FROM DEMO’D TR TO NEW TR. REFER TO DETAIL '3' ON

TN506.

B C E

G I J L N P Q T V

A D F H K M O R S U

FURNITURE

STORAGE

1-10

BATHROOM

1A-10

BATHROOM

8C-11

AREA MAINT.

8A-11

MEETING ROOM

8-11

STORAGE / HWH

8B-11

BREAK ROOM

7-11

BATHROOM

6-11 BATHROOM

5-11

IT CLOSET

1B-11

STORAGE

4A-11

ELECTRICAL ROOM

4-11

OFFICE

3-11

BATHROOM

2A-11

BATHROOM

3A-11

STORAGE ROOM

ELECTRONICS

1A-11

OFFICE

2-11

CORRIDOR

1-11

ROOM

4A-9

PLUMBING SHOP

6-8

ELECTRICAL

STORAGE

7-7

STORAGE

6-7

OFFICE

5-7

TR

5A-7

ELECTRICAL ROOM

4-7

BREAK ROOM

3-7

BATHROOM/SHOWER

2-7

MECHANICAL SHOP

1-7

MECHANICAL SHOP

1-8

OFFICE

2-8

BATHROOM/SHOWER

3-8

BATHROOM/SHOWER

2-9

BREAK ROOM

4-8

DDC CONTROLS

5-8

LOCKER BREAK

ROOM

4-9

BREAK ROOM

3-9

CARPENTER SHOP

1-9

OFFICE

7-9

OFFICE

6-9

PAINT ROOM

5-9

OFFICE

7-8

OFFICE

8-9

TOOL CRIB

9-9

MECH STORAGE

6A-8

SPRINKLER

6A-9

OPEN FOR

EQUIPMENT

STORAGE

REFER TO TS01 FOR

CONTINUATION

HH01

B

REFER TO TS001

FOR CONTINUATION

HH02

A

(1) 4"C - (1) 24 STRAND

OS2 FIBER CABLE (A) AND

(1) 4"C - SPARE

711T-400

711T-400

B

A

PULLBOX, (TYP.)

(1) 4"C - (1) 24 STRAND

OS2 FIBER CABLE (B)

AND (1) 4"C - SPARE

(1) 4"C - (1) 24 STRAND

OS2 FIBER CABLE (B)

(1) 4"C - (1) 24 STRAND

OS2 FIBER CABLE (A)

(1) 4"C - (1) 24

STRAND OS2

FIBER CABLE (A)

PW-PB-1

Eddie C. Willis, Jr.

REG. NO. 191562R

EXPIRES 12-31-2025

REGIS

TE

R

ED

CO

MMUNICA T IONS DISTRIBUT IO

N

DESIGNER

RCDD

225 W WASHINGTON STREET

SUITE 2700

CHICAGO, IL 60606

P: 312.294.0501 F: 312.294.0003 www.imegcorp.com

PROJECT #22010109.00

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/2

/2

:1

:2

A

M

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /5

- 7

.B

B

B

B

B

.T

R

.r v t

711T-101

BLDG. 07,11 LEVEL 01 PLAN - TECHNOLOGY

007-011

EW IMEG

100% CONSTRUCTION

DOCUMENTS

05/09/2025

509-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

N O R

HT

1/8" = 1'-0"

LEVEL 01 PLAN - TECHNOLOGY

SHEET NOTES:

1. REFER TO SITE PLAN TS001 FOR ADDITIONAL

INFORMATION.

2. REFER TO T500 AND T501 FOR CAMPUS OPTICAL FIBER

CABLE RISER DIAGRAMS.

3. REFER TO 2/T400 FOR HANDHOLE DETAIL.

4. NEW BACKBONE OPTICAL FIBER CABLES SHALL BE

INDOOR/OUTDOOR TYPE.

5. ALL BACKBONE OPTICAL FIBER CABLE PATHWAYS SHALL

BE NEW. DO NOT RE-USE EXISTING BACKBONE CABLE

PATHWAYS FOR NEW BACKBONE CABLES.

6. TRANSITION PVC CONDUITS TO GRC IN CRAWL SPACE OR

EXPOSED EXTERIOR LOCATIONS. TRANSITION TO EMT

CONDUITS AT INTERIOR OF BUILDING. SEAL ALL

PENETRATIONS TO MAINTAIN FIRE-RATINGS OF WALL,

CEILING AND FLOORS.

KEY NOTES:

1. PROVIDE PULLBOX ON EXTERIOR WALL AT HEIGHT OF

FIRST FLOOR CEILING. ROUTE CONDUIT FROM

HANDHOLE UP WALL INTO PULLBOX. PROVIDE

PENETRATION THRU WALL AND CONTINUE CONDUIT

ROUTE OVER TO TR #5A-7.

2. PROVIDE A CONDUIT SLEEVE THROUGH THE WALL TO

THE CABLE TRAY.

PROJECT

NORTH

0' 4' 8' 16'

Revisions: Date: 111 of 713

FIBER

DISTRIBUTION

CABINET

NOTES:

1. THIS RISER IS DIAGRAMMATIC AND MAY NOT SHOW ACTUAL ROUTING OR QUANTITIES

OF MATERIALS SHOWN. THIS RISER IS SHOWN FOR CLARIFICATION OF

CONNECTION(S), LOCATIONS AND CABLE TYPE. ALL INFORMATION OUTLETS ARE

TYPICAL OF THE OUTLETS IN THE AREA SHOWN. REFER TO FLOOR PLANS FOR MORE

SPECIFIC ROUTING INFORMATION. REFER TO SPECIFICATIONS FOR ADDITIONAL

REQUIREMENTS.

2. REFER TO ELECTRICAL DRAWINGS FOR CHANNEL RACK AND FIBER OPTIC

DISTRIBUTION CABINET SPECIFICATIONS

TELECOMMUNICATIONS ENCLOSURE - TR #5A-7

24 STRANDS OS2 FIBER OPTIC

CABLE, CORE "A" , TO BUILDING 135

24 STRANDS OS2 FIBER OPTIC

CABLE, CORE "B" , TO BUILDING 135

CHANNEL RACK

LEVEL O1

TR

5A-7

A

B

WORK IN ROOM

BY OTHER

(1) 4"C - (1) 24-STRAND OS2 FIBER CABLE (A)

(1) 4"C - (1) 24-STRAND OS2 FIBER

CABLE (B)

TR

5A-7

A

B

(1) 4"C - (1) 24-STRAND OS2 FIBER CABLE (A)

(1) 4"C - (1) 24-STRAND OS2 FIBER

CABLE (B)

Eddie C. Willis, Jr.

REG. NO. 191562R

EXPIRES 12-31-2025

REGIS

TE

R

ED

CO

MMUNICA T IONS DISTRIBUT IO

N

DESIGNER

RCDD

225 W WASHINGTON STREET

SUITE 2700

CHICAGO, IL 60606

P: 312.294.0501 F: 312.294.0003 www.imegcorp.com

PROJECT #22010109.00

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/2

/2

:1

:2

A

M

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /5

- 7

.B

B

B

B

B

.T

R

.r v t

711T-400

BLDG. 07,11 TECHNOLOGY DETAILS AND

DIAGRAMS

007-011

EW IMEG

100% CONSTRUCTION

DOCUMENTS

05/09/2025

509-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

NO SCALE

FIBER RISER DIAGRAM

NOTES:

1. REFER TO ELECTRICAL DRAWINGS FOR ROOM LAYOUT AND RACK ELEVATIONS.

2. ROUTE OPTICAL FIBER CABLE TO OVERHEAD CABLE TRAY AND TERMINATE IN FIBER DISTRIBUTION

CABINET.

KEYNOTES:

1. THROUGH WALL PENETRATION FOR BACKBONE CONDUIT. OPTICAL FIBER CABLES CONTINUES ON

CABLE TRAY TO RACKS.

N O R

HT

1/2" = 1'-0"

TELECOM ROOM ENLARGEMENT TR #5A-7

N O R

HT

1/2" = 1'-0"

TELECOM ROOM PATHWAY TR #5A-7

Revisions: Date: 112 of 713

27B

27 31

27A

110A

110B

110D

148-D

148-S

148-A

148T

146B

146A

138A 138136

137A

137C

137D

137B

137C

148B

173A

148-C

170 150

110C

143 167

G R

A V

E L

R O

A D

FRANKLIN BOULEVARD

FRANKLIN BOULEVARD

AVERILL AVENUE

AVERILL AVENUE

A M

E S

S T

R E

E T

HARRIS AVENUE

JONES CREEK

K N

O X S

T R

E E

T

T H

O M

P S

O N

S T

R E

E T

F R A N

K

LI

N B

O U

LE

V A R

D

MALLORY STREET

M A

R T

IN

L. K

IN

G

JR

. B O

U L E

V A R

D

M A R

TIN

L. K

IN

G

JR

. B O U

LE

V

AR

D

E M

A N

C

IP

A T

IO

N D

R

SHORE ROAD

H A R R

IS

A V E N

U E

HARRIS AVENUE

M c C

L E

L L A

N

S E

W E

LL

A

V E

N U

E

A V

E N

U E

A B C D E F G H I J K L M N O P Q R S T

125 SF

EXAM ROOM

A32

125 SF

EXAM ROOM

A30

125 SF

EXAM ROOM

A28

207 SF

NURSE

STATION

A19

65 SF

MEDS

A19a

62 SF

STAFF

TOILET

A31

45 SF

HAC

A35

125 SF

EXAM ROOM

A36

125 SF

EXAM ROOM

A38

117 SF

OFFICE 1

A40

117 SF

OFFICE 2

A42

117 SF

OFFICE 3

A44

117 SF

OFFICE 4

A46

117 SF

OFFICE 5

A48

307 SF

BREAK

ROOM

A26

121 SF

NURSING

A14

125 SF

EXAM ROOM

A16

125 SF

EXAM ROOM

A18

124 SF

EXAM ROOM

A20

124 SF

EXAM ROOM

A22

49 SF

PATIENT

TOILET

A12

52 SF

VISITOR

TOILET

A02a

877 SF

WAITING

AREA

A02

95 SF

VESTIBULE

A01

87 SF

CLEAN

UTILITY

A05

52 SF

DIRTY

UTILITY

A07

105 SF

LAB

A09

125 SF

EXAM ROOM

A15

125 SF

EXAM ROOM

A17

150 SF

GYN 1

A37

42 SF

HALL

A37a

49 SF

GYN TOILET

A37a1

150 SF

GYN 2

A41

348 SF

MECHANICAL/ELECTRICAL

M1

211 SF

CORRIDOR

C03

312 SF

CORRIDOR

C02

268 SF

CORRIDOR

C01

300 SF

RECEPTION

A08

4 SF

GAS

A06

116 SF

TR /

SECURITY

CLOSET

A51

98 SF

TRIAGE

B01

159 SF

PHARMACIST

OFFICE

A50

31 SF

HALL

A52

59 SF

STAFF

TOILET

A52b

19 SF

EQUIP

STORAGE

A52a

534 SF

CORRIDOR

C04

402 SF

CORRIDOR

C05

156 SF

CORRIDOR

C06

334 SF

CORRIDOR

C07

123 SF

MST PSYCH 1

B02

20 SF

STORAGE

B03

197 SF

CORRIDOR

C08

123 SF

MST PSYCH 2

B04

121 SF

MST SOCIAL

WORKER 2

B05

123 SF

MH PSYCH 1

B06

121 SF

NH SOCIAL

WORKER 1

B07

123 SF

MH PSYCH 2

B08

121 SF

NH SOCIAL

WORKER 2

B09

123 SF

MH PSYCH 3

B10

264 SF

ARTS AND

CRAFTS

B12

247 SF

LARGE

GROUP 1

B16

247 SF

LARGE

GROUP 2

B18

56 SF

UNISEX

TOILET

B15

201 SF

SMALL

GROUP 2

B20

65 SF

OBSERVATION

B22

51 SF

STAFF

TOILET

B23

200 SF

SMALL

GROUP 1

B24

121 SF

MH

ADVANCED

PRACTICE

NURSE

B25

112 SF

OFFICE 2

B26

121 SF

MST SOCIAL

WORKER 1

B27

109 SF

MH

ADDICTION

THERAPIST

B28

101 SF

OFFICE 1

B30

PHASE 1:

CONTRACTOR TO COMPLETE THE WORK OF THIS TR AND

ASSOCIATED DATA DROPS. COMPLETE ONE SECTION AT A

TIME AS DIRECTED TO COR.

SECTION 1A:

CONTRACTOR TO COORDINATE WITH VA FOR ROOM

CLOSURES AND AVAILABILITY TO COMPLETE DATA

WIRING IN THIS AREA. WORK SHALL BE DONE ON NIGHT

SHIFTS OR ON WEEKENDS.

FE

FE

FE

FE

FE

DIAMOND LINE

D

IA

M O

N D

L

IN

E

EXISTING FE. REPLACE WITH NEW SEMI-

RECESSED FEC. REPLACE EXISTING FE

WITH NEW CLEAN AGENT EXTINGUISHER

THAT MEETS OR EXCEEDS THE ABC

RATING AND SIZE OF EXISTING

EXTINGUISHER. SEE DETAIL 3/A-603

CHASE

CHASE

KEY AREA SHOWN

TRUE

NORTH

TR

ICRA PHASING LINE

ICRA CLASS II

ICRA CLASS III

ICRA CLASS IV

FEC

FE

FIRE EXTINGUISHER CABINET

FIRE EXTINGUISHER

BUILDING 013

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

/0 /2

:5

:1 a m

B

IM

/5

-2

-7

V A

H a m p to n E

H R

M /B

L D

G

.r v t

13AS101

BUILDING 013 - LEVEL 01 - PHASING PLAN

MA AL

100% CONSTRUCTION

DOCUMENTS

07/18/2025

590-22-700EHRM INFRASTRUCTURE

UPGRADES - HAMPTON

HAMPTON VA MEDICAL CENTER, HAMPTON, VIRGINIA

1/8" = 1'-0"

BUILDING 13 - LEVEL 01 - PHASING PLAN

PROJECT

NORTH

0' 4' 8' 16'

LEGENDLEGEND

KEY PLAN

Revisions: Date: 113 of 713

TO DEMOLISH

EXISTING DOOR TO REMAIN

EXISTING DOOR TO DEMOLISH

EXISTING LIGHTS TO DEMOLISH

NEW DOOR

NEW LIGHTS (SEE ELECTRICAL DETAILS)

PENDENT…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .