72-Sec 31 37 16 Energy Dissipator.pdf

PDF 81 KB Posted

Attached to
2201256.01 - Whistlestop Park
Solicitation number
US.160528
Issued by
Montgomery County, Pennsylvania

About this file

This is a technical specification document for an Energy Dissipator component, prepared for Montgomery Township in Montgomery County, Pennsylvania, in connection with the Whistlestop Park rehabilitation project (Contract 2022-01256.01). The specification details the installation of a rock energy dissipator, which serves as a stormwater management feature designed to dissipate energy and prevent erosion. The work includes site preparation through clearing, grubbing, and earthwork; placement of geotextile fabric conforming to Pennsylvania Department of Transportation Publication 408 Specifications Class 1 standards; and careful placement of sound rock material in full thickness to ensure even distribution and minimal voids. The rock material must meet Type A coarse aggregate requirements per Section 703.2 of PennDOT Publication 408, with size and gradation as indicated on project drawings. Installation must be completed in a single operation to prevent segregation, and the surrounding area shall be restored in accordance with applicable grading, seeding, sodding, and planting sections. Related site work including clearing, grubbing, earthwork, excavation, backfill, compaction, and finish grading is referenced as specified in Sections 31 11 00, 31 20 00, 31 23 33, 32 92 00, and 32 93 02.

The specification references Pennsylvania Department of Transportation standards and publication requirements for material quality assurance and installation protocols. Manufacturer's literature for geotextile fabric must be submitted in accordance with Section 01 33 00. All materials require proper handling, transportation, and storage as outlined in Section 01 60 00, with damaged materials to be protected and unsuitable subsurface material removed and replaced with acceptable fill. The Whistlestop Park project, which includes softball field rehabilitation, playground perimeter fencing, pickleball courts, a loop trail, and stormwater basins, is subject to Pennsylvania Prevailing Wage Act requirements and Pennsylvania Public Works Employment Verification provisions, with a bid deadline of April 30, 2026.

View the file

Other files

File Type Posted
13-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
50-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
54-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
48-Sec 32 18 23.13-Natural Grass Sports Field Construction.pdf PDF
41-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
26-Doc 00 91 13 - 01 Appendix I - Cover.pdf PDF
29-Doc 00 73 00 06 - Appendix C - Cover.pdf PDF
38-Doc 00 73 00 12- Appendix F - Cover.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
69-Doc 00 73 00 15 - Appendix G - Other DCED Requirements.pdf PDF
55-Doc 00 73 00 03 - Appendix A 2026-02-02 - prevailing wages whistlestop SN26-00920.pdf PDF
7-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
67-Sec 32 93 02 Exterior Planting.pdf PDF
77-Sec 33 44 15 Boxes and Endwalls.pdf PDF
28-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
78-06 FINAL Site Drawings - Gilmore 2026-03-12.pdf PDF
47-Sec 01 57 14 Erosion Control Blanket.pdf PDF
17-Doc 00 62 76 - C-620 Appl for Payment 2007.pdf PDF
19-Sec 31 20 00 Earthwork.pdf PDF
21-Doc 00 61 13.16 - Payment Bond.pdf PDF
76-Doc 00 73 00 17 - Appendix H - DCNR Signage Policy.pdf PDF
40-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
46-Sec 01 33 00 - Submittals.pdf PDF
12-Doc 00 73 00 13 - Appendix F - Nondiscrimination-Sexual Harassment Provisions.pdf PDF
43-Doc 00 45 10 - BIDDERS ACKNOWLEDGEMENT FORM.pdf PDF
9-Doc 00 73 00 08 - Appendix D - Cover.pdf PDF
51-Sec 31 23 16.26 Rock Removal.pdf PDF
75-Sec 32 92 00 Finish Grading Seeding and Sodding.pdf PDF
27-Sec 33 44 14 Storm Inlets Catch Basins Endwalls End Sections.pdf PDF
56-Sec 31 11 00 Clearing and Grubbing.pdf PDF
35-Doc 00 73 00 11- Appendix E - Americans with Disabilities Act.pdf PDF
62-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
65-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
34-Doc 00 65 19.13 - Contractors Affidavit.pdf PDF
58-Sec 32 18 23.53-Acrylic Color Coat - Generic.pdf PDF
3-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
57-Sec 32 12 00 - Asphalt Paving.pdf PDF
20-Doc 00 73 00 09 - Appendix D - Architectural Barriers Act.pdf PDF
10-Doc 00 61 19 - Maintenance Bond.pdf PDF
71-Doc 00 73 00 07 - Appendix C - State Contractor Responsibility Program.pdf PDF
52-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
2-Doc 00 41 00 - Bid Form.pdf PDF
14-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
22-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
25-Doc 01 01 01 - Appendix J Technical Specs Cover Sheet.pdf PDF
59-Doc 00 41 00 - BID FORM - EBID.pdf PDF
30-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
36-Doc 00 73 00 10- Appendix E - Cover.pdf PDF
45-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
60-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENERGY DISSIPATOR

31 37 16-1

SECTION 31 37 16

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Rock Energy Dissipator

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 31 11 00: Clearing and Grubbing

2. Section 31 20 00: Earthwork

3. Section 31 23 33: Excavation, Backfill and Compaction

4. Section 32 92 00: Finish Grading, Seeding and Sodding

5. Section 32 93 02: Exterior Planting

6. Section 33 44 14: Storm Inlets, Catch Basin, Endwalls, End Sections

1.03 QUALITY ASSURANCE

A. Reference Standards:

1. Pennsylvania Department of Transportation

Publication 408 Specifications Publication 72 Standards for Roadway Construction

1.04 SUBMITTALS

A. Manufacturer's Literature:

1. Submit manufacturer's descriptive literature for the following items in accordance with Section 01 33 00:

• Geotextile Fabric

1.05 PRODUCT DELIVERY, STORAGE & HANDLING

A. During loading, transporting and unloading, exercise care to prevent damage to materials.

B. Other Requirements

1. Section 01 60 00 also addresses transportation of handling along with storage and protection of materials and equipment.

31 37 16-2

PART 2 - PRODUCTS

2.01 BASIC MATERIALS

A. Rock:

1. Acceptable quality; sound; free from structural objects and foreign substances.

2. Rock must come from material providing a Type A coarse aggregate per Section 703.2, Publication 408 Specifications.

3. Rock size and gradation shall conform to requirements indicated on the Drawings and set forth in Section 850, Publication 408 Specifications.

2.02 FABRICATED PRODUCTS

A. Geotextile Fabric:

1. Conform with Section 735, Publication 408 Specifications for Class 1 geotextile.

PART 3 - EXECUTION

3.01 PREPARATION

A. Perform clearing, grubbing, and earthwork in accordance with Sections 31 11 00, 31 20

00, and 31 23 33 as required at location(s) shown on Drawings.

B. Remove unsuitable material below the energy dissipator and replace with acceptable material.

3.02 INSTALLATION

A. Energy dissipator shall be constructed of such size and configuration as shown on the Drawings.

B. Geotextile fabric shall be placed under the proposed rock energy dissipator in accordance with Section 212.3(c), Publication 408 Specifications and the Drawings.

C. Rock shall be carefully placed on the geotextile fabric to produce an even distribution with minimum of voids and without tearing the geotextile fabric.

D. Rock shall be placed in full thickness in one operation in a manner to prevent segregation and rearranged, as necessary to insure uniform distribution.

3.03 RESTORATION

A. Area around energy dissipator shall be restored in accordance with the Drawings and Sections 32 92 00 and 32 93 02.

END OF SECTION