30-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf

PDF 68 KB Posted

Attached to
2201256.01 - Whistlestop Park
Solicitation number
US.160528
Issued by
Montgomery County, Pennsylvania

About this file

This is a contract considerations document that establishes the administrative procedures and requirements for project execution under agreements with Montgomery Township in Pennsylvania. The document outlines the framework for scheduling work values, submitting applications for payment, managing change orders, and processing project alternates. Contractors must submit a preliminary Schedule of Values in duplicate within 10 days of the agreement's effective date, formatted according to supplementary conditions and including direct proportional amounts of overhead and profit for each line item. Monthly payment applications must be submitted in three copies on EJCDC Form C-620, accompanied by payroll certification forms, PennDOT Form CS4171 Certificate of Compliance for asphalt materials, an updated construction progress schedule, and waiver of liens documentation with the final payment application. The Engineer may authorize minor changes through supplemental instructions, issue Proposal Requests requiring contractor estimates within 15 days, or accept contractor-proposed changes documented in accordance with Section 01 60 00. Change orders may be executed as stipulated price, unit price, work change directives on EJCDC Form C-940, or time and material arrangements, with final execution on EJCDC Form C-941 following Engineer approval.

The contract structure allows for flexible compensation methods based on the nature of proposed changes, requiring contractors to maintain detailed records for time and material work and provide comprehensive supporting documentation for cost substantiation. All accepted project alternates identified in the agreement are incorporated into the contract framework. The procedures establish clear authorization hierarchies, with the Engineer serving as the primary decision-maker for change approval and cost determination, ensuring transparent documentation and systematic processing of all contract modifications and payment requests throughout the project lifecycle.

View the file

Other files

File Type Posted
13-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
50-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
54-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
48-Sec 32 18 23.13-Natural Grass Sports Field Construction.pdf PDF
41-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
26-Doc 00 91 13 - 01 Appendix I - Cover.pdf PDF
29-Doc 00 73 00 06 - Appendix C - Cover.pdf PDF
38-Doc 00 73 00 12- Appendix F - Cover.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
69-Doc 00 73 00 15 - Appendix G - Other DCED Requirements.pdf PDF
55-Doc 00 73 00 03 - Appendix A 2026-02-02 - prevailing wages whistlestop SN26-00920.pdf PDF
7-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
67-Sec 32 93 02 Exterior Planting.pdf PDF
77-Sec 33 44 15 Boxes and Endwalls.pdf PDF
28-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
78-06 FINAL Site Drawings - Gilmore 2026-03-12.pdf PDF
47-Sec 01 57 14 Erosion Control Blanket.pdf PDF
17-Doc 00 62 76 - C-620 Appl for Payment 2007.pdf PDF
19-Sec 31 20 00 Earthwork.pdf PDF
21-Doc 00 61 13.16 - Payment Bond.pdf PDF
76-Doc 00 73 00 17 - Appendix H - DCNR Signage Policy.pdf PDF
40-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
46-Sec 01 33 00 - Submittals.pdf PDF
12-Doc 00 73 00 13 - Appendix F - Nondiscrimination-Sexual Harassment Provisions.pdf PDF
43-Doc 00 45 10 - BIDDERS ACKNOWLEDGEMENT FORM.pdf PDF
9-Doc 00 73 00 08 - Appendix D - Cover.pdf PDF
51-Sec 31 23 16.26 Rock Removal.pdf PDF
75-Sec 32 92 00 Finish Grading Seeding and Sodding.pdf PDF
27-Sec 33 44 14 Storm Inlets Catch Basins Endwalls End Sections.pdf PDF
56-Sec 31 11 00 Clearing and Grubbing.pdf PDF
35-Doc 00 73 00 11- Appendix E - Americans with Disabilities Act.pdf PDF
62-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
65-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
34-Doc 00 65 19.13 - Contractors Affidavit.pdf PDF
58-Sec 32 18 23.53-Acrylic Color Coat - Generic.pdf PDF
3-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
57-Sec 32 12 00 - Asphalt Paving.pdf PDF
20-Doc 00 73 00 09 - Appendix D - Architectural Barriers Act.pdf PDF
10-Doc 00 61 19 - Maintenance Bond.pdf PDF
71-Doc 00 73 00 07 - Appendix C - State Contractor Responsibility Program.pdf PDF
52-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
2-Doc 00 41 00 - Bid Form.pdf PDF
14-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
22-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
25-Doc 01 01 01 - Appendix J Technical Specs Cover Sheet.pdf PDF
59-Doc 00 41 00 - BID FORM - EBID.pdf PDF
36-Doc 00 73 00 10- Appendix E - Cover.pdf PDF
45-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
60-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
8-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CONSIDERATIONS

01 29 00-1

SECTION 01 29 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Schedule of values.

2. Application for payment.

3. Change procedures.

4. Alternates.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 52 00: Agreement: Contract Price

2. Section 01 22 00: Measurement and Payment

3. Section 01 33 00: Submittals: Schedule of Values

3. Section 01 60 00: Material and Equipment: Product substitutions and options.

1.03 SCHEDULE OF VALUES

A. Submit a printed schedule on Contractor's standard form or electronic media printout.

B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

C. Format: See Supplementary Conditions

D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application for Payment.

1.04 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application on EJCDC Form C-620 (Document 00 62 76).

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly

D. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety Company (with Final Payment Application only)

E. Include Payroll Certification forms with each Payment Application.

F. Include PennDOT Form CS4171 Certificate of Compliance for all asphalt materials

F. Include an updated construction progress schedule.

1.05 CHANGE PROCEDURES

A. Engineer will advise of minor changes in the Work not involving an adjustment to Contract

01 29 00-2

Price or Contract Time as authorized by Paragraph 9.5 of the General Conditions by issuing supplemental instructions.

B. Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.

C. Contractor may propose changes by submitting a request for change to Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors. Document any requested substitutions in accordance with Section 01 60 00.

D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Engineer.

E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Engineer.

F. Work Change Directive: Engineer may issue a directive, on EJCDC Form C-940 Work Change

Directive signed by Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

I. Change Order Form: EJCDC Form C-941 (Document 00 63 63).

J. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.06 ALTERNATES

A. Accepted Project alternates will be identified in the Agreement.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION