This is a Quality Control specification document for a state and local construction contract opportunity with Montgomery Township, Pennsylvania for the Whistlestop Park project (Contract 2022-01256.01). The specification establishes comprehensive quality assurance and control requirements for installation, tolerances, testing, and workmanship standards throughout the project. The work scope includes rehabilitation of a softball field, construction of perimeter fencing for a new playground, pickleball courts, a loop trail, stormwater basins, basin rehabilitation, and associated landscaping and features. The contractor must comply with manufacturers' instructions, industry standards current as of the bid date, and applicable codes, with the Engineer having authority to clarify any conflicts between documents. Mock-ups must be assembled and accepted before proceeding with remaining work, and an independent testing laboratory will perform required tests with results submitted to the Engineer in duplicate. The contract requires sealed bids submitted online via PennBid until April 30, 2026 at 10:00 AM, with public opening at Montgomery Township offices located at 1001 Stump Road, Montgomeryville, PA 18936.

The specification requires a 10% bid bond with submission and mandates Performance and Payment Bonds each at 100% of the contract amount, plus a 15% Maintenance Bond. All work must comply with the Pennsylvania Prevailing Wage Act (Act 422) and Pennsylvania Public Wages Employment Verification Act (Act 127). The project is subject to DCNR Contract BRC-PRD-28-98 and DCED Contract C000083542 funding provisions. PennBid assesses a nominal fee of 0.33% of the bid amount (minimum $150, maximum $6,000 plus tax) only to awarded bidders. All bids remain valid for sixty days after opening, and bidders may withdraw bids within two business days of opening. The specification emphasizes that quality assurance monitoring must prevent tolerance accumulation, verify field measurements against shop drawings, and ensure products are secured with appropriate anchorage devices to withstand stresses and physical distortion.

View the file

Other files

File Type Posted
13-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
50-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
54-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
48-Sec 32 18 23.13-Natural Grass Sports Field Construction.pdf PDF
41-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
26-Doc 00 91 13 - 01 Appendix I - Cover.pdf PDF
29-Doc 00 73 00 06 - Appendix C - Cover.pdf PDF
38-Doc 00 73 00 12- Appendix F - Cover.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
69-Doc 00 73 00 15 - Appendix G - Other DCED Requirements.pdf PDF
55-Doc 00 73 00 03 - Appendix A 2026-02-02 - prevailing wages whistlestop SN26-00920.pdf PDF
7-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
67-Sec 32 93 02 Exterior Planting.pdf PDF
77-Sec 33 44 15 Boxes and Endwalls.pdf PDF
28-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
78-06 FINAL Site Drawings - Gilmore 2026-03-12.pdf PDF
47-Sec 01 57 14 Erosion Control Blanket.pdf PDF
17-Doc 00 62 76 - C-620 Appl for Payment 2007.pdf PDF
19-Sec 31 20 00 Earthwork.pdf PDF
21-Doc 00 61 13.16 - Payment Bond.pdf PDF
76-Doc 00 73 00 17 - Appendix H - DCNR Signage Policy.pdf PDF
40-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
46-Sec 01 33 00 - Submittals.pdf PDF
12-Doc 00 73 00 13 - Appendix F - Nondiscrimination-Sexual Harassment Provisions.pdf PDF
43-Doc 00 45 10 - BIDDERS ACKNOWLEDGEMENT FORM.pdf PDF
9-Doc 00 73 00 08 - Appendix D - Cover.pdf PDF
51-Sec 31 23 16.26 Rock Removal.pdf PDF
75-Sec 32 92 00 Finish Grading Seeding and Sodding.pdf PDF
27-Sec 33 44 14 Storm Inlets Catch Basins Endwalls End Sections.pdf PDF
56-Sec 31 11 00 Clearing and Grubbing.pdf PDF
35-Doc 00 73 00 11- Appendix E - Americans with Disabilities Act.pdf PDF
62-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
65-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
34-Doc 00 65 19.13 - Contractors Affidavit.pdf PDF
58-Sec 32 18 23.53-Acrylic Color Coat - Generic.pdf PDF
3-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
57-Sec 32 12 00 - Asphalt Paving.pdf PDF
20-Doc 00 73 00 09 - Appendix D - Architectural Barriers Act.pdf PDF
10-Doc 00 61 19 - Maintenance Bond.pdf PDF
71-Doc 00 73 00 07 - Appendix C - State Contractor Responsibility Program.pdf PDF
2-Doc 00 41 00 - Bid Form.pdf PDF
14-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
22-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
25-Doc 01 01 01 - Appendix J Technical Specs Cover Sheet.pdf PDF
59-Doc 00 41 00 - BID FORM - EBID.pdf PDF
30-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
36-Doc 00 73 00 10- Appendix E - Cover.pdf PDF
45-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
60-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
8-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY CONTROL

01 40 00-1

SECTION 01 40 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Quality assurance - Control of installation.

2. Tolerances.

3. References and standards.

4. Mock-up.

5. Testing laboratory services.

6. Observation services.

7. Manufacturers' field services.

8. Examination.

9. Preparation.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 72 00: General Conditions: References to Standards and Specifications of

Technical Societies; Reporting and Resolving Discrepancies.

2. Document 00 73 00: Supplementary Conditions: Duties, Responsibilities and Limitation of

Authority of the Resident Project Representative.

3. Section 01 33 00: Submittals: Submission of manufacturer’s instructions and certificates.

4. Section 01 42 13: Organization and Reference Acronyms

5. Section 01 60 00: Material and Equipment: Requirements for material and product quality.

1.03 QUALITY ASSURANCE-CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply fully with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Comply with specified standards as minimum quality for the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion or disfigurement.

1.04 TOLERANCES

A. Monitor fabrication and installation tolerance control of Products to produce acceptable Work. Do not permit tolerances to accumulate.

01 40 00-2

B. Comply with manufacturers’ tolerances. Should manufacturers’ tolerances conflict with Contract Documents, request clarification from Engineer before proceeding.

C. Adjust Products to appropriate dimensions; position before securing Products in place.

1.05 REFERENCES AND STANDARDS

A. For Products or workmanship specified by association, trade or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date for receiving bids, except where a specific date is established by code.

C. Obtain copies of standards where required by Product specification sections.

D. Should specified reference standard conflict with Contract Documents, request clarification from Engineer before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Engineer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.06 MOCK-UP

A. Tests will be performed under provisions identified in this section and identified in the respective Product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Engineer and is specified in Product specification sections to be removed; remove mock-up and clear area when directed to do so.

1.07 TESTING LABORATORY SERVICES

A. Contractor shall furnish to Engineer duplicate certified copies of all routine tests made by the mill, shop or factory at which material or equipment is fabricated or manufactured for the Work when so specified in individual specification sections.

B. An independent firm will perform tests and other services when so specified in individual specification sections and as required by Engineer.

C. Testing and source quality control may occur on or off the Project site. Perform off-site testing as required by Engineer.

D. Reports will be submitted by the independent firm to Engineer, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access and assistance by incidental labor as requested.

1. Notify Engineer and independent firm 24 hours prior to expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

F. Testing does not relieve Contractor to perform Work to contract requirements.

01 40 00-3

G. Retesting required because of non-conformance to specified requirements shall be performed by the same independent firm on instructions by Engineer.

H. Contractor shall pay for all testing and laboratory services and/or test reports as are required in individual specification sections.

1.08 OBSERVATION SERVICES

A. Owner will employ and pay for observation services during construction of the Project.

B. Cooperate with construction observer; furnish safe access and assistance by incidental labor as requested.

1. Notify construction observer 24 hours prior to expected time for operations requiring services.

C. Observation does not relieve Contractor to perform Work to contract requirements.

1.09 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, workmanship, start-up of equipment, test, adjust and balance of equipment, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers’ written instructions.

C. Refer to Section 01 33 00 - Submittals, Manufacturers’ field reports article.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work.

Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct locations.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

END OF SECTION