40-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf

PDF 73 KB Posted

Attached to
2201256.01 - Whistlestop Park
Solicitation number
US.160528
Issued by
Montgomery County, Pennsylvania

About this file

This is a standard construction specification document for coordination and meetings procedures applicable to Montgomery Township's Whistlestop Park project in Pennsylvania. The specification establishes comprehensive requirements for project coordination, including field engineering, preconstruction meetings, progress meetings, and construction procedures. A preconstruction meeting must be held after the effective agreement date and prior to work commencement, with required attendance from the Owner, Engineer, Resident Project Representative, Contractor, Contractor's Superintendent, and major Subcontractors. The meeting agenda encompasses personnel designation, contract document distribution, scheduling, subcontractor and product lists, procedures for field decisions and submittals, security and housekeeping, testing procedures, and record document maintenance. Progress meetings shall be scheduled throughout the work as needed, chaired by the Resident Project Representative, with agenda items including progress reviews, field observations, submittal status, fabrication schedules, quality standards, and change order impacts. Meeting minutes must be distributed within five working days to all participants.

The specification requires the Contractor to coordinate scheduling and work sequencing to ensure efficient installation of interdependent construction elements and to verify setbacks, easements, and drawing dimensions. The Owner provides survey control and reference points, while the Contractor bears responsibility for protection and re-establishment costs. For alteration work procedures, the Contractor must employ skilled installers, minimize damage during removal and patching, provide smooth transitions where new work abuts existing work, and match textures and appearances. The Contractor assumes full responsibility for construction-related damage to private, leased, or Owner vehicles on the site and must submit detailed construction procedures and schedules to the Engineer prior to work commencement, including a complete inventory of materials and equipment required for performance.

View the file

Other files

File Type Posted
13-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
50-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
54-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
48-Sec 32 18 23.13-Natural Grass Sports Field Construction.pdf PDF
41-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
26-Doc 00 91 13 - 01 Appendix I - Cover.pdf PDF
29-Doc 00 73 00 06 - Appendix C - Cover.pdf PDF
38-Doc 00 73 00 12- Appendix F - Cover.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
69-Doc 00 73 00 15 - Appendix G - Other DCED Requirements.pdf PDF
55-Doc 00 73 00 03 - Appendix A 2026-02-02 - prevailing wages whistlestop SN26-00920.pdf PDF
7-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
67-Sec 32 93 02 Exterior Planting.pdf PDF
77-Sec 33 44 15 Boxes and Endwalls.pdf PDF
28-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
78-06 FINAL Site Drawings - Gilmore 2026-03-12.pdf PDF
47-Sec 01 57 14 Erosion Control Blanket.pdf PDF
17-Doc 00 62 76 - C-620 Appl for Payment 2007.pdf PDF
19-Sec 31 20 00 Earthwork.pdf PDF
21-Doc 00 61 13.16 - Payment Bond.pdf PDF
76-Doc 00 73 00 17 - Appendix H - DCNR Signage Policy.pdf PDF
46-Sec 01 33 00 - Submittals.pdf PDF
12-Doc 00 73 00 13 - Appendix F - Nondiscrimination-Sexual Harassment Provisions.pdf PDF
43-Doc 00 45 10 - BIDDERS ACKNOWLEDGEMENT FORM.pdf PDF
9-Doc 00 73 00 08 - Appendix D - Cover.pdf PDF
51-Sec 31 23 16.26 Rock Removal.pdf PDF
75-Sec 32 92 00 Finish Grading Seeding and Sodding.pdf PDF
27-Sec 33 44 14 Storm Inlets Catch Basins Endwalls End Sections.pdf PDF
56-Sec 31 11 00 Clearing and Grubbing.pdf PDF
35-Doc 00 73 00 11- Appendix E - Americans with Disabilities Act.pdf PDF
62-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
65-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
34-Doc 00 65 19.13 - Contractors Affidavit.pdf PDF
58-Sec 32 18 23.53-Acrylic Color Coat - Generic.pdf PDF
3-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
57-Sec 32 12 00 - Asphalt Paving.pdf PDF
20-Doc 00 73 00 09 - Appendix D - Architectural Barriers Act.pdf PDF
10-Doc 00 61 19 - Maintenance Bond.pdf PDF
71-Doc 00 73 00 07 - Appendix C - State Contractor Responsibility Program.pdf PDF
52-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
2-Doc 00 41 00 - Bid Form.pdf PDF
14-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
22-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
25-Doc 01 01 01 - Appendix J Technical Specs Cover Sheet.pdf PDF
59-Doc 00 41 00 - BID FORM - EBID.pdf PDF
30-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
36-Doc 00 73 00 10- Appendix E - Cover.pdf PDF
45-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
60-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
8-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

5. Alteration Project procedures.

6. Construction coordination requirements.

1.02 RELATED SECTIONS

A. This section not used.

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion and for portions of Work designated for Owner’s occupancy.

C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.04 FIELD ENGINEERING

A. Owner will locate survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points and will compensate Owner for re-establishment of survey control and reference points.

B. Control datum for survey is that established by Owner provided survey.

B. Verify set-backs and easements; confirm drawing dimensions and elevations.

D. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.

1.05 PRECONSTRUCTION MEETING

A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors.

C. Agenda:

1. Designation of personnel representing the parties in Contract, and the Engineer.

2. Distribution of Contract Documents.

3. Scheduling.

01 31 00-2

4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

6. Use of premises by Owner and Contractor.

7. Owner’s requirements [and [partial] occupancy].

8. Construction facilities and controls provided by Owner.

9. Security and housekeeping procedures

10. Procedures for testing.

11. Procedures for maintaining record documents.

D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

PART 2 - PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 ALTERATION PROJECT PROCEDURES

A. Materials: As specified in Product sections; match existing Products and work for patching and extending work.

B. Employ skilled and experienced installer to perform alteration work.

C. Close openings in exterior surfaces to protect existing work from weather and extremes of temperature and humidity.

D. Remove, cut, and patch Work in a manner to minimize damage and to provide means of

01 31 00-3 restoring products and finishes to [original] [or] [specified] condition.

E. Where new Work abuts or aligns with existing, provide a smooth and even transition. Patch Work to match existing adjacent Work in texture and appearance.

F. When finished surfaces are cut so that a smooth transition with new Work is not possible, terminate existing surface along a straight line at a natural line of division and submit recommendation to Engineer for review.

G. Where a change of plane of ¼ inch or more occurs, submit recommendation for providing a smooth transition to Engineer for review.

H. Patch or replace portions of existing surfaces which are damaged, lifted, discolored, or showing other imperfections.

I. Finish surfaces as specified in individual Product sections.

3.02 CONSTRUCTION COORDINATION REQUIREMENTS

A. General

1. Contractor shall be responsible for any construction related damage to private/leased or Owner vehicles on the site.

B. Construction Coordination Requirements

1. Prior to start of construction, Contractor shall meet with Owner and Engineer to schedule the Work, determine possible conflicts with existing utilities.

2. Contractor shall submit to Engineer, in writing, a detailed description and schedule of the proposed construction procedures. Information submitted to the Engineer shall include a complete inventory of materials and equipment needed to perform the work.

3. Owner may notify Contractor through the Resident Project Representative should he deem Contractor’s actions detrimental to public safety.

4. The Resident Project Representative shall not direct Contractor or his work forces in areas of Contractor’s responsibility for construction, workmanship and progress of work or changes in Contract scope.

END OF SECTION