This document is an amendment to Solicitation Number 36C77624B0025 for the construction of Electronic Health Record Modernization (EHRM) infrastructure upgrades at the Ann Arbor VA Medical Center.

The amendment includes responses to 17 offeror questions, providing clarification on various aspects of the project such as door numbering, UPS runtime, flooring requirements, cabling, window film application, and fire extinguishers. The solicitation closing date and bid opening time remain unchanged at 2:00 PM and 2:30 PM Eastern Time, respectively, on October 15, 2024. All other terms and conditions of the solicitation remain unchanged. The overall contract is for the VA Technology Acquisition Center Austin to perform construction work for the Department of Veterans Affairs.

View the file

Other files

File Type Posted
S07 - Complete Abstract of Bids OF 1419- Ann Arbor EHRM 10 16 2024.pdf PDF
S07 - Complete Abstract of Bids OF 1419- Ann Arbor EHRM.pdf PDF
IFB 36C77624B0025 Amendment 0005 Asbestos Info.pdf PDF
36C77624B0025 Amendment 0003.pdf PDF
S05 Ann_Arbor CMS_Question_Matrix_V3.xlsx XLSX spreadsheet
Attachment 12 - EHRM Window Screen Details.pdf PDF
Attachment 08 - 075423 TPO Roofing.pdf PDF
Attachment 14 - MS Versions of PDFs.zip ZIP file
Attachment 07 - 013323 Shop Drawings_CA Edits 2.pdf PDF
Attachment 02 - 1E.ET472.pdf PDF
Attachment 06 - 000110 TOC - updated TPO and 236323.pdf PDF
Attachment 11 - CABLE MATRICES.pdf PDF
Attachment 04 - 21-092 SubReg 100 Percent.pdf PDF
Attachment 10 - Addendum 1.pdf PDF
Attachment 09 -236323 AirCooledClosedCircuitFluidCooler.pdf PDF
36C77624B0025 0002.docx DOCX document
Attachment 05 - 21-092-Pre-Bid RFIs_AE responses 1.pdf PDF
Attachment 15 - DB WR GD No MI20240100 09062024.pdf PDF
Attachment 03 - 1W.A-491_Addendum 1.pdf PDF
Attachment 01 - Q and A Results Ann Arbor MI.docx DOCX document
Attachment 13 - G-003_Addendum 1.pdf PDF
S04 - Pre-Bid Site Visit Sign-in Sheet - 09 04 2024.pdf PDF
S04 - Virtual Visit Attendee List - 08 29 2024.docx DOCX document
36C77624B0025 Ammendment 0001.docx DOCX document
S04 -Virtual and Site Visit Agenda - IFB 2024 08 29 2024.doc DOC document
S04 - Pre-Bid Site Visit Sign-in Sheet - 09 04 2024.docx DOCX document
Attachment 02_Drawings 07122024 Part 1.pdf PDF
Attachment 04_Drawings 07122024 Part 3.pdf PDF
Attachment 11 Division Breakdown Template.xls XLS spreadsheet
Attachment 06_Drawings 07122024 Part 5.pdf PDF
Attachment 05_Drawings 07122024 Part 4.pdf PDF
Attachment 08_Limitations on Subcontracting - Construction.docx DOCX document
Attachment 03_Drawings 07122024 Part 2.pdf PDF
Attachment 07_Drawings 07122024 Part 6.pdf PDF
Attachment 09_JA Ann Arbor Final REDACTED.pdf PDF
Attachment 10 DB Wages General Decision Number MI20240100 07 26 24.pdf PDF
Attachment 01_Specifications Ann Arbor MI.pdf PDF
36C77624B0025_1.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 5

0004 10/04/2024

506-21-705

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

To all Offerors/Bidders

36C77624B0025

08-22-2024

X

X X

X 1

The purpose of this amendment is to answer additional offeror questions.

The due date/time for bids is unchanged and remains at 2:00 PM Eastern Time on Tuesday, 10/15/2024.

Bids will be opened at 2:30 PM Eastern Time on Tuesday, 10/15/2024.

See following pages for Questions and Answers.

All other terms and conditions remain unchanged.

David Mark

10/04/2024

Question #1: Spec Section 08 17 00: This specification section references a specific door #B360A. We cannot find this door on the Door Schedule or can we find it on the architectural drawings for any of the 54 data and electrical rooms. Does this spec. section and door number apply to this project?

Answer #1: The door number in the 08 17 00 specification section is incorrect. The Door should be listed as #B306A.

Question #2: Specifications call for 240-minute discharge time for the UPS however most of these EHRM projects call for 10 minutes. If we provided a 240-minute runtime we would need a large room to store all the batteries.

Answer #2: Provide minimum 10 minute discharge time.

Question #3: Drawings show an 80 kW UPS and specifications call for a 150 kW UPS.

Please let us know which is correct.

Answer #3: 80 kW

Question #4: Per the requirements for the flooring, it appears all moisture testing is required (calcium chloride, relative humidity and ph testing) as well as all potential contaminants including adhesives mechanically removed down to the slab. If moisture is found, mitigation and leveling or patching is required. Is this accurate for the scope?

Answer #4: PH Testing required on all floors with slab on grade only. Mitigate as necessary.

Question #5: I can make a full system recommendation including primer, moisture mitigation, self-leveling and patching compound based on the specifications, and I can provide a full system drawing and spec. We have successful VA and hospital project references. If I provide this system spec, can it be included in the project for the basis of design?

Answer #5: Contractor to use a system of their choosing for BOD and submit in shop drawings. No BOD is currently stated.

Question #6: Asbestos – we manufacture primers and self-leveling underlayments that are approved for use over well bonded asbestos adhesives and tile. If these products can help avoid abatement, is this something that would help you?

Answer #6: All asbestos and/or lead paint that is noted on the contract documents to be removed or discovered as part of the work is required to be abated and removed from the site following all abatement procedures listed in the asbestos abatement specifications. No products that leave the asbestos or lead paint in place will be approved.

Question #7: Electrical: Not all C-stack re-cabling drawings identify the need to NOT re-cable.

Is it the intent for the C-stack closets that no new Category cabling will be installed and no new fiber will be installed for primary or redundant paths?

Answer #7: C-stack is intended to be decommissioned with regards to OIT equipment. All cabling called for to be re-pulled at the c-stack vicinity is to be pulled to B-Stack.

Question #8: Upon reviewing the RFP, I noticed that while it specifies the installation of safety window film on the interior face of glazing, the provided documentation does not include window elevations, a schedule, dimensions, or specific details on where the window film should be applied throughout the building.

Window Dimensions: Are there elevations or a window schedule available that provide the height and dimensions of the windows requiring film?

Film Placement: Should the window film be applied to all windows, or only certain locations? If so, could you specify where the safety window film is required?

Answer #8:

Window Dimensions: See Sheet 6/ A-601 for referencing window film. Window film is listed on A-602. Where window film is applicable is noted by a keynote per location. Contractor to verify size. The Contractor shall provide 175 SF of window film for the project. The TR rooms that require window film are: Bldg 1 - L133 (80 SF); Bldg 2 - 210 (20 SF); Bldg 15 - 15-2 (24 SF);

Bldg 28 - F224A (51 SF).

Film Placement:: See Sheet 6/ A-601 for referencing window film. Window film is listed on A-

602. Where window film is applicable is noted by a keynote per location. Contractor to verify size. All windows in the TR room(s) shall be covered with film.

Question #9: Could we have a better location of Rooms AB23 - 1W, CB07 – 1W, A180 – 1W and A752 – 1W which all are listed on Drawing G-108? We cannot find them on the Tele-Com detail drawings. We did find a CB07 – 1E detail drawing but not for 1W.

Answer #9: On sheet G-008:

CB07 is in 1E, reference 1E.ET401.

AB23 is in 1W - No scope of work.

A180 is in B28 and is the MCR, reference 28.ET411

A752 is erroneous, should be A753, reference 1W.ET471

Question #10: Exterior Security Grill Detail 6/A-601 did not establish intent for vertical & horizontal bar spacings. (The RFI 11 response does not clarify this matter.)

Please clarify bar spacings.

Please clarify final product coatings.

Please confirm bidders shall scale and bid in a budgetary manner for this grillage.

Answer #10: The bar spacing shall be 2" both horizontally and vertically. The grille shall be made from a material that can be exposed to northern climates, stainless steel, galvanized metal (painted) or aluminum.

Question #11: The specs only call for fire cabinets, there is no information on the extinguisher type and size. We need to know the type and size of fire extinguisher that will accommodate the cabinets.

Answer #11: The fire extinguisher cabinet shall accommodate a 20 LB, "Clean Agent" type extinguisher. The wall mount option should use the same type & size extinguisher.

Question #12: Sheet 1E.A-402, note callout #7, states for a new wall mounted fire extinguisher but the drawing show a cabinet at the tagged location. Can you confirm that only fire cabinets are desired or are fire extinguishers desired too.

Answer #12: Wall bracket type mounted fire extinguishers shall be used in all existing CMU wall type applications. If a fire extinguisher is shown on a new wall (or an existing metal stud wall,) then a cabinet shall be used.

Question #13: Sheet 1E.A-402, note callout #7, states for a new wall mounted fire extinguisher but the drawing show a cabinet at the tagged location. Can you confirm that this callout is correct or not?

Answer #13: The note 7 is correct. This should be a wall mounted, bracket type, fire extinguisher and not a cabinet.

Question #14: Drawing 1.G-124: Says to repull cables to new F224A TR. How many cables?

Answer #14: Bid 480 total at a length of 295'-0".

Question #15: Does existing CAT6A cabling that is getting re-terminated need to be re-terminated on new patch panels? Or use existing?

Answer #15: Existing patch panels can be re-used.

Question #16: 28. PROVIDE 12 PORT WALL MOUNTED COPPER PATCH PANEL I THE

EXISTING TR/FACILITY ROOM AND ANOTHER 12 PORT IN EACH NEW TR AND RUN 12-

4PR CAT 6A CABLE BETWEEN THESE TR'S TERMINATE AND TEST, LABEL EACH PORT.

Clarify where this is needed, in the new A stack, or all TR's ? What is considered the existing TR/facility room?

Answer #16: This is needed everywhere there is an existing TR/Facility room that is being abandoned (for instance A stack and C stack). TR/Facility room is all rooms where there is an existing OIT switch providing network connectivity.

Question #17: Does OM4 and OS1 fibers need to be indoor/outdoor or is indoor acceptable for fibers that do not leave the main building?

Answer #17: Indoor is acceptable.