Attachment 06 - 000110 TOC - updated TPO and 236323.pdf
PDF 127 KB Posted
- Attached to
- Z2DA--506-21-705 EHRM Infrastructure Upgrades - Ann Arbor, MI - Construction (VA-25-00001864)
- Solicitation number
- 36c77624b0025
About this file
This document is a Table of Contents for the bid documents related to the EHRM Infrastructure Upgrade project at the Ann Arbor VA Medical Center, Project No. 506-21-705. It lists the various sections and specifications that are included in the bid package, such as general requirements, existing conditions, concrete, masonry, metals, thermal and moisture protection, openings, finishes, specialties, fire suppression, plumbing, HVAC, electrical, communications, and electronic safety and security. The related federal contract opportunity is for the construction of these EHRM infrastructure upgrades at the Ann Arbor VA Medical Center, with a solicitation number of 36c77624b0025. The contracting agency is the Department of Veterans Affairs Technology Acquisition Center Austin.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ann Arbor VA Healthcare System February 28, 2024 EHRM Infrastructure Upgrade Bid Documents Ann Arbor, MI, 48105 Project No: 506-21-705 Addendum 01 09/16/2024
03-01-22
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 06-21 01 35 26 Safety Requirements 11-21 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 00.1 Contractor’s Quality Control Report (QCR) 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 11-21 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 19 Selective Demolition 08-17 02 82 11 Traditional Asbestos Abatement 01-21 02 82 11.1 Asbestos Assessment 02 82 13.13 Glovebag Asbestos Abatement 01-21 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21 02 83 33.13.1 Lead Based Paint Assessment
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 01-21 04 05 13 Masonry Mortaring 10-17 04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18 05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
Ann Arbor, MI, 48105 Project No: 506-21-705 Addendum 01 09/16/2024
03-01-22
00 01 10 - 2
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21 07 21 13 Thermal Insulation 01-21 07 52 16.11 Cold Adhesive Styrene-Butadiene-Styrene Modified
Bituminous Membrane Roofing 12-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 71 00 Roof Specialties 01-21 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 17 00 Integrated Door Opening Assemblies 04-23 08 31 13 Access Doors and Frames 01-21 08 71 00 Door Hardware 01-21 08 87 00 Window Film
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 19 Resilient Tile Flooring 05-18 09 69 00 Access Flooring 08-23 09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21 10 26 00 Wall and Door Protection 01-21 10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20
Ann Arbor, MI, 48105 Project No: 506-21-705 Addendum 01 09/16/2024
03-01-22
00 01 10 - 3
SECTION NO. DIVISION AND SECTION TITLES DATE
22 07 11 Plumbing Insulation 09-19 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 02-20
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20 23 23 00 Refrigerant Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 40 00 HVAC Air Cleaning Devices 03-20 23 63 23 Air-Cooled, Closed-Circuit Fluid Cooler N/A 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 81 23 Computer-Room Air-Conditioners 03-20 23 82 16 Air Coils 03-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 22 00 Low-Voltage Transformers 01-18 26 24 16 Panelboards 01-18 26 24 16.1 TR Panel Schedules 26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 33 53 Static Uninterruptible Power Supply 11-22 26 41 00 Facility Lightning Protection 01-17 26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
Ann Arbor, MI, 48105 Project No: 506-21-705 Addendum 01 09/16/2024
03-01-22
00 01 10 - 4
27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Conduits And Backboxes for Communications Systems 10-18 27 05 36 Cable Trays for Communications Systems 11-21 27 05 53 Identification for Communications Systems 07-21 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Structured Cabling 11-21 27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 11-21 27 11 19 Communications Termination Blocks and Patch Panels 11-21 27 11 26 Communications Rack Mounted Power Protection and Power
Strips 11-21
27 13 13 Communications Copper Backbone Cabling 11-21 27 13 13.13 Communications Copper Cable Splicing and Terminations 11-21 27 13 23 Communications Optical Fiber Backbone Cabling 11-21 27 15 10 Data Ports 27 15 13 Communications Copper Horizontal Cabling 11-21 27 15 13.13 Communications Optical Fiber Splicing and Terminations 11-21 27 16 19 Communications Patch Cords, Station Cords, and Cross
Connect Wire 11-21
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and
Security 10-18
28 05 26 Grounding and Bonding for Electronic Safety and Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11
--- END ---
File details come from the government source that posted it. Updated .