VA WCHCS Bldg 45 Oneline Report 23.pdf
PDF 76 KB Posted
- Attached to
- H263--Fire Protection Services Federal contract opportunity
- Solicitation number
- 36C25925Q0190
About this file
This is a fire alarm testing report dated March 23, 2023, documenting the inspection and testing of fire safety devices at VA Hospital WCHCS Building 45. The report, prepared by ALARMSpecialists Inc. of Centennial CO, details the testing results for multiple types of fire safety equipment including pull stations, smoke detectors, duct detectors, tamper switches, water flow switches, and audible/visual notification devices (speakers and strobes).
The testing covered 8 pull stations, 4 smoke detectors, 2 duct detectors with HVAC shutdown verification, 2 tamper switches, 1 water flow switch, and 77 speaker/strobe devices throughout the building. All devices tested passed inspection with specified performance metrics noted (e.g., 53-second response time for the water flow switch). The report fulfills multiple compliance requirements under EC.02.03.05, including EP 2 (six-month testing of water flow devices), EP 3 (annual testing of detectors and pull stations), EP 4 (annual testing of audible/visual alarms), and EP 19 (annual testing of smoke detection shutdown devices for air handling equipment).
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared by ALARMSpecialists, Inc
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested Device Location No de Lo op Device Status Comments March 23, 2023 Pull Station Gym 104 N 23 L 1 M 9 Pass March 23, 2023 Pull Station Gym 104 N 23 L 1 M 10 Pass March 23, 2023 Pull Station West Exit N 23 L 1 M 8 Pass March 23, 2023 Pull Station Plaster Room 142 N 23 L 1 M 13 Pass March 23, 2023 Pull Station Main Entry South East N 23 L 1 M 11 Pass March 23, 2023 Pull Station Lounge 179 Exit North East N 23 L 1 M 12 Pass March 23, 2023 Pull Station Electrical Rm 186 Exit North N 23 L 1 M 1 Pass March 23, 2023 Pull Station Mail Room 188 N 23 L 1 M 7 Pass
EC.02.03.05 EP 3 Every 12 months, the hospital tests duct detectors, heat detectors, manual fire alarm boxes, and smoke detectors on the inventory. The results and completion dates are documented..
VA Hospital - WCHCS - Bldg 45 - Device List - March 23
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested Device Location No de Lo op Device Status Comments March 23, 2023 Smoke Detector Police 149 N 23 L 1 D 1 Pass March 23, 2023 Smoke Detector Electrical Rm 136 West Hall N 23 L 1 D 5 Pass March 23, 2023 Smoke Detector Electrical Rm 186 Exit North N 23 L 1 D 6 Pass March 23, 2023 Smoke Detector Mech Rm 187 Bldg 45 N 23 L 1 D 4 Pass
VA Hospital - WCHCS - Bldg 45 - Device List - March 23 EC.02.03.05 EP 3 Every 12 months, the hospital tests duct detectors, heat detectors, manual fire alarm boxes, and smoke detectors on the inventory. The results and completion dates are documented.
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested DEVICE LOCATION No de Lo op DeviceSHUTDOWN STATUS COMMENTS March 23, 2023 Duct Detector Mech Rm 187 DD North Hall Bldg 45 N 11 L 1 D 2 Yes PASS March 23, 2023 AHU relay HVAC Shutdown North Relay Bldg 45 N 11 L 1 M 2 PASS March 23, 2023 Duct Detector Mech Rm 187 DD North Hall Bldg 45 N 11 L 1 D 3 Yes PASS
EC.02.03.05 EP 3 Every 12 months, the hospital tests duct detectors, heat detectors, manual fire alarm boxes, and smoke detectors on the inventory. The results and completion dates are documented.
EC.02.03.05 EP 19 Every 12 months, the hospital tests automatic smoke-detection shutdown devices for air-handling equipment. The results and completion dates are documented.
VA - WCHCS - Bldg 45 - DUCT DETECTION - March 23
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested DEVICE LOCATION STATUS COMMENTS March 23, 2023 Tamper Switch Tamper #1 N 11 L 1 M 5 PASS 1 TURN March 23, 2023 Tamper Switch Tamper #2 N 11 L 1 M 6 PASS 1 TURN
VA WCHCS - Bldg 45 - Sprinkler - March 23 EC.02.03.05 EP 2 Every 6 months, the hospital tests vane-type and pressure-type water flow devices and valve tamper switches on the inventory. The results and completion dates are documented.
Note 2: Mechanical water-flow devices (including, but not limited to, water motor gongs) should be tested quarterly. The results and completion dates are documented.
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested DEVICE LOCATION STATUS COMMENTS March 23, 2023 Water Flow Switch MAIN RISER MECH 187 NORTH 1ST FLR N 11 L 1 M 4 PASS 53 SEC
VA WCHCS - Bldg 45 - Sprinkler - March 23 EC.02.03.05 EP 2 Every 6 months, the hospital tests vane-type and pressure-type water flow devices and valve tamper switches on the inventory. The results and completion dates are documented.
Note 2: Mechanical water-flow devices (including, but not limited to, water motor gongs) should be tested quarterly. The results and completion dates are documented.
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested Device Floor Room # / Corridor Location / Description No de Lo op Device Label Status Comments March 23, 2023 Speaker/Strobe Physical therapy Building 45 N 11 L 1 x x 49798976 Pass March 23, 2023 Speaker/Strobe Physical therapy Building 45 N 11 L 1 x x 49798983 Pass March 23, 2023 Speaker/Strobe Physical therapy Building 45 N 11 L 1 x x 49798984 Pass March 23, 2023 Strobe Physical therapy Building 45 N 11 L 1 x x 49798975 Pass March 23, 2023 Strobe Physical therapy Building 45 N 11 L 1 x x 49798977 Pass March 23, 2023 Strobe Physical therapy Building 45 N 11 L 1 x x 49798978 Pass March 23, 2023 Strobe Physical therapy Building 45 N 11 L 1 x x 49798979 Pass March 23, 2023 Strobe Physical therapy Building 45 N 11 L 1 x x 49798982 Pass March 23, 2023 Speaker/Strobe prosthetic Check In Building 45 N 11 L 1 x x 49798968 Pass March 23, 2023 Speaker/Strobe Prosthetic Check In Building 45 N 11 L 1 x x 49799008 Pass March 23, 2023 Speaker/Strobe Prosthetic Check In Building 45 N 11 L 1 x x 49799009 Pass March 23, 2023 Speaker/Strobe Outside Building 45 N 11 L 1 x x 49799205 Pass March 23, 2023 Speaker/Strobe Rm 109 Building 45 N 11 L 1 x x 49799047 Pass March 23, 2023 Strobe Rm 114 Building 45 N 11 L 1 x x 49798974 Pass March 23, 2023 Speaker/Strobe Rm 116 Building 45 N 11 L 1 x x 49799040 Pass March 23, 2023 Strobe By Rm 117 Building 45 N 11 L 1 x x 49799011 Pass March 23, 2023 Strobe By Rm 118 Building 45 N 11 L 1 x x 49798973 Pass March 23, 2023 Strobe Rm 118 Building 45 N 11 L 1 x x 49799041 Pass March 23, 2023 Speaker/Strobe By Rm 120 Building 45 N 11 L 1 x x 49798972 Pass March 23, 2023 Speaker/Strobe By Rm 121 Building 45 N 11 L 1 x x 49798970 Pass March 23, 2023 Speaker/Strobe By Rm 121 Building 45 N 11 L 1 x x 49799044 Pass March 23, 2023 Strobe Rm 121 Building 45 N 11 L 1 x x 49798969 Pass March 23, 2023 Speaker/Strobe By Rn 122 Building 45 N 11 L 1 x x 49799039 Pass March 23, 2023 Strobe Rm 122 Building 45 N 11 L 1 x x 49799038 Pass March 23, 2023 Speaker/Strobe By Rm123 Building 45 N 11 L 1 x x 49799035 Pass March 23, 2023 Strobe Rm 123 Building 45 N 11 L 1 x x 49799037 Pass March 23, 2023 Strobe Rm 124 Building 45 N 11 L 1 x x 49799036 Pass March 23, 2023 Speaker/Strobe By Rm 130 Building 45 N 11 L 1 x x 49799027 Pass March 23, 2023 Strobe Rm 130 Building 45 N 11 L 1 x x 49799031 Pass March 23, 2023 Strobe Rm 131 Building 45 N 11 L 1 x x 49799032 Pass March 23, 2023 Strobe Rm 132 Building 45 N 11 L 1 x x 49799030 Pass March 23, 2023 Speaker/Strobe By Rm 133 Building 45 N 11 L 1 x x 49799034 Pass March 23, 2023 Strobe Rm 133 Building 45 N 11 L 1 x x 49799033 Pass March 23, 2023 Strobe Rm 134 Building 45 N 11 L 1 x x 49799029 Pass March 23, 2023 Speaker/Strobe By Rm 136 Building 45 N 11 L 1 x x 49799028 Pass March 23, 2023 Speaker/Strobe By Rm 137 Building 45 N 11 L 1 x x 49799026 Pass March 23, 2023 Speaker/Strobe Rm 138 Building 45 N 11 L 1 x x 49799005 Pass March 23, 2023 Speaker/Strobe Rm 141 Building 45 N 11 L 1 x x 49798999 Pass March 23, 2023 Strobe Rm 142 Building 45 N 11 L 1 x x 49798996 Pass
VA WCHCS - Bldg 45 - Audibles - Device List - March 23
EC.02.03.05 EP 4 Every 12 months, the hospital tests visual and audible fire alarms, including speakers and door-releasing devices on the inventory. The results and completion dates are documented.
6786 S Revere Prky Suite 110 Centennial CO 80112 Phone (303) 986-5900
Date Tested Device Floor Room # / Corridor Location / Description No de Lo op Device Label Status Comments
VA WCHCS - Bldg 45 - Audibles - Device List - March 23
EC.02.03.05 EP 4 Every 12 months, the hospital tests visual and audible fire alarms, including speakers and door-releasing devices on the inventory. The results and completion dates are documented.
March 23, 2023 Speaker/Strobe Rm 143 Building 45 N 11 L 1 x x 49798997 Pass March 23, 2023 Speaker/Strobe By Rm 145 Building 45 N 11 L 1 x x 49799025 Pass March 23, 2023 Strobe Rm 145 Building 45 N 11 L 1 x x 49799004 Pass March 23, 2023 Strobe Rm 146 Building 45 N 11 L 1 x x 49799003 Pass March 23, 2023 Speaker/Strobe By Rm 148 Building 45 N 11 L 1 x x 49798993 Pass March 23, 2023 Strobe Rm 148 Building 45 N 11 L 1 x x 49798992 Pass March 23, 2023 Strobe Rm 148 Building 45 N 11 L 1 x x 49799006 Pass March 23, 2023 Speaker/Strobe By Rm 149 Building 45 N 11 L 1 x x 49799002 Pass March 23, 2023 Strobe Rm 152 Building 45 N 11 L 1 x x 49799007 Pass March 23, 2023 Speaker/Strobe By Rm 155 Building 45 N 11 L 1 x x 49798991 Pass March 23, 2023 Speaker/Strobe By Rm 155 Building 45 N 11 L 1 x x 49799023 Pass March 23, 2023 Speaker/Strobe By Rm 155 Building 45 N 11 L 1 x x 49799024 Pass March 23, 2023 Strobe By Rm 156 Building 45 N 11 L 1 x x 49799012 Pass March 23, 2023 Strobe Rm 159 Building 45 N 11 L 1 x x 49798988 Pass March 23, 2023 Strobe Rm 159 Building 45 N 11 L 1 x x 49798989 Pass March 23, 2023 Strobe Rm 161 Building 45 N 11 L 1 x x 49798990 Pass March 23, 2023 Speaker/Strobe By Rm 167 Building 45 N 11 L 1 x x 49798964 Pass March 23, 2023 Speaker/Strobe By Rm 167 Building 45 N 11 L 1 x x 49798965 Pass March 23, 2023 Speaker/Strobe By Rm 167 Building 45 N 11 L 1 x x 49798966 Pass March 23, 2023 Speaker/Strobe Rm 172 Building 45 N 11 L 1 x x 49798941 Pass March 23, 2023 Speaker/Strobe By Rm 174 Building 45 N 11 L 1 x x 49798942 Pass March 23, 2023 Speaker/Strobe By Rm 176 Building 45 N 11 L 1 x x 49798944 Pass March 23, 2023 Strobe Rm 176 Building 45 N 11 L 1 x x 49798936 Pass March 23, 2023 Strobe Rm 176 Building 45 N 11 L 1 x x 49798937 Pass March 23, 2023 Strobe Rm 176 Building 45 N 11 L 1 x x 49798940 Pass March 23, 2023 Speaker/Strobe By Rm 178 Building 45 N 11 L 1 x x 49798985 Pass March 23, 2023 Strobe By Rm 178 Building 45 N 11 L 1 x x 49798938 Pass March 23, 2023 Speaker/Strobe By Rm 179 Building 45 N 11 L 1 x x 49798962 Pass March 23, 2023 Speaker/Strobe Rm 179 Building 45 N 11 L 1 x x 49798998 Pass March 23, 2023 Speaker/Strobe By Rm 181 Building 45 N 11 L 1 x x 49798963 Pass March 23, 2023 Speaker/Strobe By Rm 185 Building 45 N 11 L 1 x x 49799010 Pass March 23, 2023 Speaker/Strobe By Rm 185 Building 45 N 11 L 1 x x 49799013 Pass March 23, 2023 Strobe By Rm 185 Building 45 N 11 L 1 x x 49799014 Pass March 23, 2023 Speaker/Strobe Rm 187 Building 45 N 11 L 1 x x 49799000 Pass March 23, 2023 Speaker/Strobe Rm 187 Building 45 N 11 L 1 x x 49799001 Pass