This is an architectural drawing set for a roof replacement project at the Chalmers P. Wylie Veterans Outpatient Clinic in Columbus, Ohio, managed by the U.S. Department of Veterans Affairs. The project involves the replacement of roofing systems on Building 1A, with work divided into multiple roof sections totaling approximately 4,260 square feet across Roof 7, Roof 14A, and Roof 14B.
The scope includes selective removal of the existing roofing system down to the substrate, application of a new roofing system to match existing specifications, and waterproofing and paver roof systems where applicable. The work requires preservation of existing roof drains, overflow drains, pipe vent penetrations, HVAC equipment, and lightning protection grounding terminals, with inspections and contractor discussion of any discovered issues during removal and installation. The drawing package is dated as Bid Documents from May 6, 2025, with Addendum 01 issued on April 27, 2026. The project is fully sprinklered and designed by FFE and HEAVY consultants, with the Architect/Engineer of Record stamp required. Work areas include biohazardous exhaust areas, roof access points, and high-powered radio frequency areas that must be carefully managed during construction.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A. MAINTAIN EXISTING R-VALUE AND INSULATION THICKNESS TO MATCH EXISTING IN ISOLATED REPLACEMENT AREAS AS IDENTIFIED ON DRAWINGS, UNLESS NOTED OTHERWISE. PROVIDE TAPERED INSULATION TO DIRECT WATER TO ROOF DRAINS.
MATCH ELEVATION WHERE TYING INTO EXISTING.
B. ALL EXISTING WALKWAY PADS SHALL BE REMOVED PRIOR TO REPLACEMENT/RESTORATION WORK. NEW WALKWAY LAYOUT IS SHOWN ON THE ROOF PLAN DRAWINGS AE101 THROUGH AE111. QUANTIFY TOTAL PRIOR TO BID.
C. REPLACE ALL MISSING, PLASTIC, OR BROKEN DRAIN BASKETS AND CLAMP RINGS ON EXISTING ROOF DRAINS. QUANTIFY TOTAL
PRIOR TO BID.
D. ELEVATION HEIGHT BASED ON GROUND FLOOR.
E. MATCH EXISTING ROOF SLOPE AT PARTIAL ROOF REPLACEMENT
F. MECHANICAL DUCTWORK AND PIPING ARE FOR REFERENCE ONLY. SIZING IS SCHEMATIC.
G. EXISTING ROOFING SYSTEM IS A SINGLE-PLY MEMBRANE OVER RIGID INSULATION UNLESS NOTED OTHERWISE. TPO ROOF SYSTEM EXTENSION ROOF 14 (A AND B). ALL OTHER EXISTING ROOFS USE A PVC ROOF SYSTEM.
H. ALL CONDENSING UNITS AND EQUIPMENT ON ROOF SUPPORTS NOT FLASHED INTO THE EXISTING ROOF SHALL BE DISCONNECTED AND TEMPORARILY REMOVED AND STORED WHILE ROOFING IS COMPLETED UNDER THE UNITS. PROTECT EQUIPMENT DURING THIS PERIOD. REFRIGERANT SHALL BE CAPTURED AND UTILITIES SERVING THIS EQUIPMENT WILL ALL BE
DISCONNECTED AND TEMPORARILY CAPPED.
I. CONTRACTOR SHALL USE CHARCOAL FILTRATION ON ALL AIR INTAKES TO MASK ODORS INTO THE BUILDING.
PROVIDE CARBON ACTIVATED FILTER MEDIA ROLLS OR BLANKETS TO COVER THE ENTIRE AIR HANDLING UNIT INTAKE. BLANKET OR ROLL SHALL BE A MINIMUM OF 3/8 INCH THICK AND CONTAIN A MINIMUM OF 90 GRAMS/SF OF GRANULAR ACTIVATED CARBON WITH AN INITIAL RESISTANCE OF 0.35 IN. WC. AT 150 FPM.
J. SEE ELECTRICAL DRAWINGS FOR NEW LIGHTNING PROTECTION SYSTEM.
K. PERMANENT FALL PROTECTION IS NOT INCLUDED IN THIS CONTRACT. ALL PERMANENT FALL PROTECTION WILL BE ADDRESSED IN A SEPARATE VA PROJECT. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR MEETING OSHA
REGULATIONS FOR JOB-SITE SAFETY DURING THE CONSTRUCTION PROJECT.
G E N E R A L N O T E S
L E G E N D
RESTORATION SCOPE
APPLICATION OF A FLUID APPLIED REHABILITATION SYSTEM OVER EXISTING ROOFING SYSTEM.
REPLACEMENT AND RESTORATION SCOPE
SELECTIVE REMOVAL OF EXISTING ROOFING SYSTEM DOWN TO THE DECK AND INSTALLATION OF NEW ROOFING SYSTEM TO MATCH EXISTING AND APPLICATION OF A FLUID-APPLIED REHABILITATION
SYSTEM.
NOT IN SCOPE
REPLACEMENT SCOPE
REMOVE EXISTING ROOF SYSTEM DOWN TO THE STRUCTURAL DECK. INSTALL FLUID-APPLIED
WATERPROOFING AND PAVER ROOF SYSTEM
BIOHAZARDOUS EXHAUST AREA
ROOF ACCESS POINT
HIGH-POWERED RADIO FREQUENCY AREA
PIPE VENT
ELEC. GROUNDING TERMINAL
ANCHOR POST
BOOT FLASHING
ROOF-TOP LADDER
RAISED GRATING
WALKWAY SYSTEM
SLIP-RESISTANCE
AGGREGATE IN FLUID-
APPLIED MEMBRANE
FOR WALKING PATHS
EXISTING RUBBER
WALKING MAT
M A
T C
H L
IN
E
M A
T C
H L
IN
E
1,135 SQ. FT. 2,775 SQ. FT.
ROOF 14A
2.01
2.02
2.05
2.142.15
2.13
2.14
2.13
A E
A E
AE142
Sim
AE142
Sim
AE142
Sim
AE141
Sim
AE141
Sim
AE141
Sim
AE141
Sim
AE142
Sim
AE141
Sim
AE142
Sim
AE141
Sim
AE142
Sim
AE142
Sim
450 SQ. FT.
ROOF 17B
ROOF 7
ROOF 17A
ROOF 14A
ROOF 14B
1A 3A 3B
1B
1C 1D
17A
17B
14B
14A
6 5
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Date:Revisions:No.
A u to d e s k D o c s /C o lu m b u s V
A
R e p la c e R o o f o n B ld g
A /F
F E
C o lu m b u s
R e p la c e
R o o f_ B
A
A
R C
H rv t
/2
/2
:4
:4
P
M
AE110
ENLARGED ROOF PLAN - ROOF
14A
05/06/2025 PRQ JLF
REPLACE ROOF BUILDING 1A 757-21-101
COLUMBUS, OHIO
BID DOCUMENTS
1A
CHALMERS P. WYLIE
VETERANS
OUTPATIENT CLINIC
Approved: Columbus VAMC
D R A W I N G N O T E S :
2.01 EXISTING ROOF DRAIN AND OVERFLOW DRAIN TO REMAIN. - TYPICAL
2.02 EXISTING PIPE VENT PENETRATION TO REMAIN. - TYPICAL
2.05 EXISTING HVAC EQUIPMENT TO REMAIN. - TYPICAL
2.13 UPON REMOVAL OF ROOFING SYSTEM, INSPECT CURB FOR ANY NOTICEABLE DAMAGE. - CONTACT VA AND A/E TO
DISCUSS ANY ISSUES DISCOVERED.
2.14 INSPECT EXISTING ROOF DRAIN AND OVERFLOW DRAIN DURING ROOF REPLACEMENT - CONTACT VA AND A/E TO
DISCUSS ANY ISSUES DISCOVERED.
2.15 INSPECT EXISTING LIGHTNING PROTECTION GROUNDING TERMINAL DURING ROOF REPLACEMENT - CONTACT VA AND
A/E TO DISCUSS ANY ISSUES DISCOVERED.
1/8" = 1'-0"
ENLARGED ROOF PLAN - 4
BID DOCUMENTS 05/06/2025
1 ADDENDUM 01 04/27/2026