07.06_AE106 - ENLARGED ROOF PLAN - ROOF 3B.pdf
PDF 2 MB Posted
- Solicitation number
- 36C25026B0011
About this file
This document is an architectural drawing set for a roof replacement project at the Chalmers P. Wylie Veterans Outpatient Clinic, a U.S. Department of Veterans Affairs facility located in Columbus, Ohio. The project involves replacing roofing systems on Building 1A, with bid documents dated May 6, 2025, and one addendum issued on April 27, 2026.
The scope of work encompasses removal of existing roof systems down to the structural deck and installation of new waterproofing and paver roof systems across multiple roof sections (Roofs 1A, 1D, 2, 3B, and 4), totaling approximately 1,217 square feet on the cooling platform. Work includes removal and relocation of existing HVAC equipment and condenser units, inspection of roof curbs upon removal, removal and storage of existing loose-laid rubber walking mats for reuse on resin storage sheds, installation of new walkway systems, and selective rehabilitation using fluid-applied coatings in designated restoration scopes. Key existing infrastructure to remain includes roof drains, overflow drains, air handling units, and temporary storage sheds. The project requires coordination with VA and the architect/engineer of record regarding any issues discovered during removal phases, with completion requirements for reinstallation of equipment after roof replacement completion.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UP
UP
UP
A. MAINTAIN EXISTING R-VALUE AND INSULATION THICKNESS TO MATCH EXISTING IN ISOLATED REPLACEMENT AREAS AS IDENTIFIED ON DRAWINGS, UNLESS NOTED OTHERWISE. PROVIDE TAPERED INSULATION TO DIRECT WATER TO ROOF DRAINS.
MATCH ELEVATION WHERE TYING INTO EXISTING.
B. ALL EXISTING WALKWAY PADS SHALL BE REMOVED PRIOR TO REPLACEMENT/RESTORATION WORK. NEW WALKWAY LAYOUT IS SHOWN ON THE ROOF PLAN DRAWINGS AE101 THROUGH AE111. QUANTIFY TOTAL PRIOR TO BID.
C. REPLACE ALL MISSING, PLASTIC, OR BROKEN DRAIN BASKETS AND CLAMP RINGS ON EXISTING ROOF DRAINS. QUANTIFY TOTAL
PRIOR TO BID.
D. ELEVATION HEIGHT BASED ON GROUND FLOOR.
E. MATCH EXISTING ROOF SLOPE AT PARTIAL ROOF REPLACEMENT
F. MECHANICAL DUCTWORK AND PIPING ARE FOR REFERENCE ONLY. SIZING IS SCHEMATIC.
G. EXISTING ROOFING SYSTEM IS A SINGLE-PLY MEMBRANE OVER RIGID INSULATION UNLESS NOTED OTHERWISE. TPO ROOF SYSTEM EXTENSION ROOF 14 (A AND B). ALL OTHER EXISTING ROOFS USE A PVC ROOF SYSTEM.
H. ALL CONDENSING UNITS AND EQUIPMENT ON ROOF SUPPORTS NOT FLASHED INTO THE EXISTING ROOF SHALL BE DISCONNECTED AND TEMPORARILY REMOVED AND STORED WHILE ROOFING IS COMPLETED UNDER THE UNITS. PROTECT EQUIPMENT DURING THIS PERIOD. REFRIGERANT SHALL BE CAPTURED AND UTILITIES SERVING THIS EQUIPMENT WILL ALL BE
DISCONNECTED AND TEMPORARILY CAPPED.
I. CONTRACTOR SHALL USE CHARCOAL FILTRATION ON ALL AIR INTAKES TO MASK ODORS INTO THE BUILDING.
PROVIDE CARBON ACTIVATED FILTER MEDIA ROLLS OR BLANKETS TO COVER THE ENTIRE AIR HANDLING UNIT INTAKE. BLANKET OR ROLL SHALL BE A MINIMUM OF 3/8 INCH THICK AND CONTAIN A MINIMUM OF 90 GRAMS/SF OF GRANULAR ACTIVATED CARBON WITH AN INITIAL RESISTANCE OF 0.35 IN. WC. AT 150 FPM.
J. SEE ELECTRICAL DRAWINGS FOR NEW LIGHTNING PROTECTION SYSTEM.
K. PERMANENT FALL PROTECTION IS NOT INCLUDED IN THIS CONTRACT. ALL PERMANENT FALL PROTECTION WILL BE ADDRESSED IN A SEPARATE VA PROJECT. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR MEETING OSHA
REGULATIONS FOR JOB-SITE SAFETY DURING THE CONSTRUCTION PROJECT.
G E N E R A L N O T E S
L E G E N D
RESTORATION SCOPE
APPLICATION OF A FLUID APPLIED REHABILITATION SYSTEM OVER EXISTING ROOFING SYSTEM.
REPLACEMENT AND RESTORATION SCOPE
SELECTIVE REMOVAL OF EXISTING ROOFING SYSTEM DOWN TO THE DECK AND INSTALLATION OF NEW ROOFING SYSTEM TO MATCH EXISTING AND APPLICATION OF A FLUID-APPLIED REHABILITATION
SYSTEM.
NOT IN SCOPE
REPLACEMENT SCOPE
REMOVE EXISTING ROOF SYSTEM DOWN TO THE STRUCTURAL DECK. INSTALL FLUID-APPLIED
WATERPROOFING AND PAVER ROOF SYSTEM
BIOHAZARDOUS EXHAUST AREA
ROOF ACCESS POINT
HIGH-POWERED RADIO FREQUENCY AREA
PIPE VENT
ELEC. GROUNDING TERMINAL
ANCHOR POST
BOOT FLASHING
ROOF-TOP LADDER
RAISED GRATING
WALKWAY SYSTEM
SLIP-RESISTANCE
AGGREGATE IN FLUID-
APPLIED MEMBRANE
FOR WALKING PATHS
EXISTING RUBBER
WALKING MAT
A E
M A
T C
H L
IN
E
M A
T C
H L
IN
E
A E
ROOF 3B
ROOF 2
ROOF 4
COOLING PLATFORM OVERHEAD
AHU
1,217 SQ. FT.
2.01
2.05
2.09
2.09
2.08
2.12
2.122.13
AE141
Sim
AE141
Sim
AE141
Sim
AE141
Sim
AE141
Sim
2.10
AE142
Sim
PLASTIC
STORAGE
SHED
AHU
PLASTIC
STORAGE
SHED
PLASTIC
STORAGE
SHED
AE141
Sim
AE141
Sim
AE142
Sim
AE142
Sim
AE142
Sim
2.59
2.59
1A 3A 3B
1B
1C 1D
17A
17B
14B
14A
6 5
ROOF 1D
ROOF 1B
ROOF 17A
ROOF 1A
ROOF 3B
ROOF 3A
ROOF 2
ROOF 6
R4
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Date:Revisions:No.
A u to d e s k D o c s /C o lu m b u s V
A
R e p la c e R o o f o n B ld g
A /F
F E
C o lu m b u s
R e p la c e
R o o f_ B
A
A
R C
H rv t
/2
/2
:4
:0
P
M
AE106
ENLARGED ROOF PLAN - ROOF 3B
05/06/2025 PRQ JLF
REPLACE ROOF BUILDING 1A 757-21-101
COLUMBUS, OHIO
BID DOCUMENTS
1A
CHALMERS P. WYLIE
VETERANS
OUTPATIENT CLINIC
Approved: Columbus VAMC
D R A W I N G N O T E S :
2.01 EXISTING ROOF DRAIN AND OVERFLOW DRAIN TO REMAIN. - TYPICAL
2.05 EXISTING HVAC EQUIPMENT TO REMAIN. - TYPICAL
2.08 REMOVE EXISTING ROOF WALKWAY PADS. INSTALL NEW WALKWAY SYSTEM. DRAWINGS SHOW NEW LAYOUT- TYPICAL
2.09 EXISTING TEMPORARY SHED TO REMAIN. TEMPORARY RELOCATION WILL BE REQUIRED DURING RESTORATION WORK.
2.10 EXISTING AIR HANDLING UNIT TO REMAIN.
2.12 REMOVE/RELOCATE CONDENSER DURING ROOF REPLACEMENT. INSPECT CURB(S) FOR ANY NOTICEABLE DAMAGE;
CONTACT VA AND A/E TO DISCUSS ANY ISSUES DISCOVERED. INSTALL EXISTING CONDENSER IN PREVIOUS LOCATION
AFTER ROOF REPLACEMENT.
2.13 UPON REMOVAL OF ROOFING SYSTEM, INSPECT CURB FOR ANY NOTICEABLE DAMAGE. - CONTACT VA AND A/E TO
DISCUSS ANY ISSUES DISCOVERED.
2.59 EXISTING LOOSE LAID RUBBER WALKING MATS. REMOVE AND STORE DURING REPLACEMENT/RESTORATION WORK.
INSTALL MATS FOR RESIN STORAGE SHEDS TO SIT ON. USE RUBBER WALKING MATS TO ALSO CREATE PATH FROM
GRATED WALKWAY SYSTEM TO THE RESIN STORAGE SHEDS. - TYPICAL
1/8" = 1'-0"
ENLARGED ROOF PLAN - ROOFS 2, 3B & 4
BID DOCUMENTS 05/06/2025
1 ADDENDUM 01 04/27/2026
| Sheets |
| AE106 - ENLARGED ROOF PLAN - ROOF 3B |
File details come from the government source that posted it. Updated .