This pre-solicitation notice is for a site preparation project at the Dayton VA Medical Center in Dayton, Ohio. The Department of Veterans Affairs Network Contracting Office 10 is seeking a Service-Disabled Veteran-Owned Small Business to completely prepare the site for a building operation including demolition and removal of existing structures. The contractor will be responsible for furnishing all labor, materials, and work to complete the project according to the statement of work, specifications, and drawings while coordinating closely with the contracting officer and contracting officer's representative. The project duration is 245 calendar days from notice to proceed. The solicitation documents will be posted on November 9, 2020 on SAM.gov with proposals due approximately 30 days later. The project value is between $1,000,000 and $5,000,000 under NAICS code 236220 with a small business size standard of $39.5 million. The service-disabled veteran-owned small business must perform a minimum of 25% of the construction work. Bid, payment and performance bonds will be required along with a mandatory site visit.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C-3.0
SITE DETAILS
CONCRETE SIDEWALK
AASHTO M147 AGGREGATE
COMPACTED SUBGRADE
BROOM FINISH
5'-0" MIN. OR AS SHOWN ON PLAN
1/4" EXPANSION JOINT MATERIAL
2% CROSS SLOPE
UNLESS NOTED
OTHERWISE ON PLAN
TYPE A OR B
6x6 - W1.4xW1.4 WWF
4" THICK TYPE B 4,000 PSI
PER VA SPECIFICAITONS
AT ALL STRUCTURES
PER SPECIFICATIONS
NOTE:
1. SURFACE TO BE SEALED PER VA SPECIFICATIONS.
2. SLOPE OF SUBGRADE SHALL FOLLOW SAME SLOPE AS
PAVEMENT ABOVE AS NOTED ON GRADING PLAN.
6x6 - W1.4xW1.4 WWF
COMPACTED SUBGRADE-
EXPANSION JOINT
4" T"
TYPE B, 4,000 PSI PER VA
SPECIFICATIONS
1/2" PREMOLDED JOINT FILLER
HOLD BACK 1/2" FROM SURFACE.
PROVIDE BACKER ROD AND JOINT
SEALANT
GRANULAR WHERE DIRECTED
TO REPLACE SOFT AND
YIELDING SUBGRADE
T/
2" (PER CONC. PAVEMENT DETAIL)
AS SHOWN ON DRAWINGS; SAW CUT.
CONTROL JOINT - 5' O.C. MAX. OR
6x6 - W1.4xW1.4 WWF
1"
COMPACTED SUBGRADE
CONTROL JOINT
NOTES:
1. 1/2" PREMOLDED EXPANSION JOINT PER PER VA SPECIFICATIONS - 40' O.C. MAX. OR AS SHOWN
ON DRAWINGS AT ALL CURBS, WALKS, WALLS AND OTHER FIXED OBJECTS.
2. CONTROL JOINT - 5' 0.C. MAX. OR AS SHOWN ON DRAWINGS.
3. CROSS SLOPE AT 1/8" PER FOOT MIN. TO DRAIN.
4. USE EDGING TOOL AT PERIMETER.
5. SIDEWALK PER VA SPECIFICATIONS.
6. SURFACE TO BE SEALED PER VA SPECIDICATIONS.
7. SLOPE OF SUBGRADE SHALL FOLLOW SAME SLOPE AS PAVEMENT ABOVE AS NOTED ON
GRADING PLAN.
4" T"
T/ 2"
(PER CONC. PAVEMENT DETAIL)
PAVEMENT JOINTS
JOINT SEALANT
FOAM BACKER
ROD
LEVELING COURSE (4" MIN.)
AASHTO M147 AGGREGATE
TYPE A OR B
LEVELING COURSE (4" MIN.)
TYPE B, 4,000 PSI PER VA
SPECIFICATIONS
AASHTO M147 AGGREGATE
TYPE A OR B
LEVELING COURSE (4" MIN.)
TYPICAL TRENCH DETAIL
(FLEXIBLE PIPE)
BEDDING
PIPE COVER
9" MIN.
O.D.
24" MAX. 72" DIA. & LARGER
12" MAX. 24" DIA. & LESS.
15" MAX. 27" to 66" DIA.
PREMIUM OR REGULAR BACKFILL
1/4 PIPE DIAMETER
6" MIN. - 12" MAX.
DIAMETER
1/4 PIPE
COMPACTED SUBGRADE
NOTES:
LATERAL CONNECTIONS TO HAVE A MINIMUM BEDDING DEPTH OF 3" COARSE AGGREGATE.
PIPE COVER SHALL CONSIST OF COARSE INTERLOCKING AGGREGATE NO. 57, 6, 67, 68, 7, 78, OR 8.
BEDDING SHALL CONSIST OF COARSE INTERLOCKING AGGREGATE NO. 57, 6, 67, 68, 7, 78, OR 8 FOR 60" OR SMALLER
DIAMETER PIPE. FOR 66" OR LARGER DIAMETER PIPE NO. 4 AGGREGATE MAY ALSO BE USED.
PREMIUM BACKFILL SHALL CONSIST OF COARSE INTERLOCKING AGGREGATE NO. 57, 6, 67, 68, 7, 78, 8, ODOT ITEM 304, OR
LIMESTONE SCREENINGS.
TRENCH WIDTH AND CONCRETE CRADLE WIDTH SHALL BE O.D. OF PIPE PLUS 9" ON EACH SIDE OF PIPE.
FOR CONCRETE AND DUCTILE IRON PIPE, PIPE COVER IS TO THE SPRINGLINE OR GREATER.
IN PAVED AREAS COARSE INTERLOCKING AGGREGATE TO THE TOP OF THE TRENCH ON ALL TYPES OF PIPE.
CHIEF ENGINEER
PHILIP P. KIRK
440.243.3305 f Cleveland, OH 44130
440.243.2000 t 7850 Freeway Circle
Date:Revisions: AuthorChecker09/16/2020
Project Director
552-CSI-162
4100 WEST THIRD STREET,
DAYTON, OHIO 45428
SITE PREP FOR PET/CT
REPLACEMENT
109876541 2 3
CONSULTANT STAMPARCHITECT/ENGINEER OF RECORD Phase
109876541 2
F
E
D
C
B
A
F
E
D
C
B
U.S. Department of Veterans Affairs
Management and Facilities Construction
Office of
FULLY SPRINKLERED
BID & CONSTRUCTION
(REVISED)
6/
/2
:3 9:
P
M Fi le P at h
A
Approved:
Drawing Title
DrawnCheckedIssue Date
Location
Project Title
Drawing Number
Building Number
Project Number
12-12-201935% SUBMISSION
02-24-202065% SUBMISSION
03-31-202065% RE-SUBMISSION
05-08-201995% SUBMISSION
06-12-2020BID & CONSTRUCTION
07-13-2020BID & CONSTRUCTION (REVISED)
09-16-2020SOLE SOURCE REVISION
02-25-2021ADDENDUM #2
SEDIMENT POLLUTANT CONTROLS (GENERAL NOTES):
1. PERIMETER SEDIMENT CONTROLS (I.E. SEDIMENT TRAPS, SILT FENCE, COMPOST
SOCKS, COMPOST BERMS, ETC… SHALL BE IMPLEMENTED AS THE FIRST STEP OF
GRADING AND WITHIN SEVEN DAYS FROM THE START OF GRUBBING ANS SHALL
CONTINUE TO FUNCTION UNTIL UPSLOPE AREAS DRAINING TO THEM ARE PERMANENTLY
STABILIZED, OR AS DIRECTED BY THE DESIGNATED AUTHORITY.
2. NO EROSION AND SEDIMENT CONTROL BMP'S SHALL BE REMOVED FROM THE SITE
PRIOR TO ADEQUATE PERMANENT STABILIZATION OF THE ASSOCIATED UPLAND
DRAINAGE AREAS AND WITHOUT FIRST OBTAINING AUTHORIZATION FROM THE
DESIGNATED AUTHORITY, UNLESS THEIR REMOVAL IS SPECIFICALLY PROVIDED FOR
WITHIN THE SITE'S APPROVED PLAN.
3. THERE SHALL BE NO SEDIMENT-LADEN OR TURBID DISCHARGES TO WATER
RESOURCES OR WETLANDS RESULTING FROM DEWATERING ACTIVITIES. IF TRENCH OR
GROUNDWATER CONTAINS SEDIMENT, IT MUST PASS THROUGH A SEDIMENT TRAP OR
OTHER EQUALLY EFFECTIVE SEDIMENT CONTROL DEVICE, PRIOR TO BEING DISCHARGED
FROM THE CONSTRUCTION SITE. ALTERNATIVELY, SEDIMENT MAY BE REMOVED BY
SETTLING IN PLACE OR BY DEWATERING INTO A SUMP PIT, FILTER BAG OR COMPARABLE
PRACTICE. GROUND WATER DEWATERING WHICH DOES NOT CONTAIN SEDIMENT OR
OTHER POLLUTANTS IS NOT REQUIRED TO BE TREATED PRIOR TO DISCHARGE.
HOWEVER, CARE MUST BE TAKEN WHEN DISCHARGING GROUND WATER TO ENSURE
THAT IT DOES NOT BECOME POLLUTANT-LADEN BY TRAVERSING OVER DISTURBED SOILS
OR OTHER POLLUTANT SOURCES.
4. STREETS DIRECTLY ADJACENT TO CONSTRUCTION ENTRANCES AND RECEIVING
TRAFFIC FROM THE DEVELOPMENT AREA, SHALL BE CLEANED DAILY TO REMOVE
SEDIMENT TRACKED OFF-SITE. IF APPLICABLE, THE CATCH BASINS ON THESE STREETS
NEAREST TO THE CONSTRUCTION ENTRANCES SHALL ALSO BE CLEANED WEEKLY.
BASED ON SITE CONDITIONS, THE ENGINEER, OR HIS DESIGNATED REPRESENTATIVE,
MAY REQUIRE ADDITIONAL BEST MANAGEMENT PRACTICES TO CONTROL OFF-SITE
TRACKING OF DUST.
5. IT SHALL BE THE RESPONSIBILITY OF THE DEVELOPER, OR REPRESENTATIVE, TO
PROVIDE INSPECTION OF ALL CONTROLS ON THE SITE AT LEAST ONCE EVERY SEVEN
CALENDAR DAYS, AND WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAN
ONE-HALF INCH OF RAIN PER 24 HOUR PERIOD. WHEN INPSECTIONS REVEAL THE NEED
FOR REPAIR, REPLACEMENT, OR INSTALLATION OF EROSION AND SEDIMENT CONTROL
BMP'S, THE FOLLOWING PROCEDURES SHALL BE FOLLOWED:
A. WHEN PRACTICES REQUIRE REPAIR OR MAINTENANCE: THE BMP SHALL
BE REPAIRED WITHIN 3 DAYS OF INSPECTION. EXCEPTION: SEDIMENT
PONDS SHALL BE REPAIRED OR MAINTAINED WITH 10 DAYS OF
INSPECTION.
B. WHEN PRACTICES FAIL TO PROVIDE THEIR INTENDED FUNCTION: A
MORE APPROPRIATE BMP SHALL BE SELECTED AND IMPLEMENTED
WITHIN 10 DAYS OF THE INSPECTION.
C. WHEN PRACTICES DEPICTED IN THE EROSION AND SEDIMENT CONTROL
PLAN ARE NOT INSTALLED: THE BMP SHALL BE INSTALLED WITHIN 10
DAYS OF THE INSPECTION. IF THE INSPECTION REVEALS THAT THE BMP
IS NOT NECESSARY, THE RECORD MUST CONTAIN AN EXPLANATION
FOR THE DECISION.
INSPECTION SHALL BE COMPLETED BY A QUALIFIED PROFESSIONAL IN EROSION AND
SEDIMENT CONTROL PRACTICES. SHOULD THE SITE BECOME DORMANT FOR AN
EXTENDED PERIOD OF TIME AND IS STABILIZED, OR RUNOFF IS UNLIKELY DUE TO
WEATHER CONDITIONS FOR EXTENDED PERIODS OF TIME (E.G., FROZEN GROUND) A
REDUCTION TO MONTHLY INSPECTIONS MAY BE GRANTED.
6. ALL EROSION AND SEDIMENT CONTROL PRACTICES SPECIFIED ON THIS PLAN
SHALL CONFORM WITH THE DETAILS AND SPECIFICATIONS OUTLINED IN THE CURRENT
VERSION OF THE OHIO DEPARTMENT OF NATURAL RESOURCES, "RAINWATER AND LAND
DEVELOPMENT" MANUAL, OR AS SPECIFIED BY THE ENGINEER, OR DESIGNATED
REPRESENTATIVE.
7. EROSION AND SEDIMENT CONTROL PRACTICES NOT ALREADY SPECIFIED ON THIS
PLAN MAY BE NECESSARY DUE TO UNFORESEEN ENVIRONMENTAL CONDITIONS AND/OR
CHANGES IN DRAINAGE PATTERNS CAUSED BY EARTH-MOVING ACTIVITY. ADDITIONAL
PRACTICES SHALL BE IMPLEMENTED AT THE DEVELOPER'S EXPENSE AS DIRECTED BY
THE ENGINEER, OR DESIGNATED REPRESENTATIVE.
8. NO STRUCTURAL SEDIMENT CONTROLS (SILT FENCE, SEDIMENT TRAPS, ETC.)
SHALL BE USED IN A WATER RESOURCE OR WETLAND, UNLESS THEIR USE IS
SPECIFICALLY PROVIDED FOR WITHIN THE SITE'S APPROVED PLAN.
9. SOIL STOCKPILES, TOPSOIL OR OTHERWISE, SHALL BE SITUATED AWAY FROM
STREETS, SWALES, OR OTHER WATERWAYS AND SHALL BE SEEDED AND/OR MULCHED
IMMEDIATELY.
10. ON-SITE PERSONNEL SHALL TAKE ALL NECESSARY MEASURES TO COMPLY WITH
APPLICABLE REGULATIONS REGARDING FUGITIVE DUST EMISSIONS, INCLUDING
OBTAINING NECESSARY PERMITS FOR SUCH EMISSIONS. THE ENGINEER, OR
DESIGNATED REPRESENTATIVE, MAY REQUIRE DUST CONTROLS INCLUDING, BUT NOT
LIMITED TO, THE USE OF WATER TRUCKS TO WET DISTURBED AREAS, TAPPING
STOCKPILES, TEMPORARY STABILIZATION OF DISTURBED AREAS, AND REGULATION OF
THE SPEED OF VEHICLES ON THE SITE.
11. ANY DISTURBED AREA NOT PAVED, SODDED, OR BUILT UPON SHALL HAVE A
MINIMUM OF 80% UNIFORM VEGETATIVE COVER PRIOR TO FINAL INSPECTION AND, IN THE
OPINION OF THE ENGINEER OR DESIGNATED REPRESENTATIVE, WILL BE MATURE
ENOUGH TO CONTROL EROSION SATISFACTORILY AND SURVIVE SEVERE WEATHER.
12. THE APPLICANT SHALL MAINTAIN FOR 3 YEARS FOLLOWING FINAL STABILIZATION,
THE RESULTS OF THESE INSPECTIONS, THE NAMES AND QUALIFICATIONS OF
PERSONNEL MAKING THE INSPECTIONS, THE DATES OF INSPECTIONS, MAJOR
OBSERVATIONS RELATING TO THE IMPLEMENTATION OF THE EROSION & SEDIMENT
CONTROL PLAN, A CERTIFICATION AS TO WHETHER THE FACILITY IS IN COMPLIANCE
WITH THE EROSION & SEDIMENT CONTROL PLAN, AND INFORMATION ON ANY INCIDENTS
OF NON-COMPLIANCE DETERMINED BY THESE INSPECTIONS.
NON-SEDIMENT POLLUTANT CONTROLS (GENERAL NOTES):
1. ALL SANITARY WASTE SHALL BE COLLECTED FROM PORTABLE UNITS A MINIMUM OF ONE TIME PER WEEK BY A LICENSED
SANITARY WASTE MANAGEMENT CONTRACTOR, AS REQUIRED BY LOCAL REGULATION.
2. THE FOLLOWING GOOD HOUSEKEEPING PRACTICES WILL BE FOLLOWED ON SITE DURING THE CONSTRUCTION PROJECT:
A. AN EFFORT WILL BE MADE TO STORE ONLY ENOUGH PRODUCT REQUIRED TO DO THE JOB.
B. ALL MATERIALS STORED ON SITE WILL BE STORED IN A NEAT, ORDERLY MANNER, IN THEIR APPROPRIATE
CONTAINERS, AND, IF POSSIBLE, UNDER A ROOF OR OTHER ENCLOSURE.
C. PRODUCTS WILL BE KEPT IN THEIR ORIGINAL CONTAINERS WITH THE MANUFACTURER'S LABEL. SUBSTANCES
WILL NOT BE MIXED WITH ONE ANOTHER UNLESS RECOMMENDED BY THE MANUFACTURER.
D. WHENEVER POSSIBLE, ALL OF A PRODUCT WILL BE USED UP BEFORE DISPOSING OF THE CONTAINER.
E. THE MANUFACTURER'S RECOMMENDATIONS FOR PROPER USE AND DISPOSAL WILL BE FOLLOWED.
F. THE SITE SUPERINTENDENT WILL INSPECT DAILY TO ENSURE PROPER USE AND DISPOSAL OF MATERIALS ON SITE.
3. IN ADDITION TO PREVIOUS NOTES, THE FOLLOWING PRACTICES WILL BE FOLLOWED FOR SPILL PREVENTION AND CLEAN-UP:
A. CONTRACTOR MUST CONTACT OHIO EPA AT 1-800-282-9378, THE LOCAL FIRE DEPARTMENT, AND THE LOCAL
EMERGENCY PLANNING COMMITTEE (LEPC) WITHIN 30 MINUTES OF A SPILL 25 GALLONS OR GREATER.
B. MANUFACTURER'S RECOMMENDED METHODS FOR SPILL CLEAN-UP WILL BE POSTED AND SITE PERSONNEL MADE AWARE OF THE PROCEDURES AND THE LOCATION OF THE INFORMATION AND CLEAN-UP SUPPLIES.
C. MATERIALS AND EQUIPMENT NECESSARY FOR SPILL CLEANUP WILL BE KEPT IN THE MATERIAL STORAGE AREA ON SITE. EQUIPMENT AND MATERIALS WILL INCLUDE, BUT NOT LIMITED TO: BROOMS, DUSTPANS, MOPS, RAGS, GLOVES, GOFFLES, CAT LITTER, SAND, SAWDUST, AND PLASTIC AND METAL TRASH CONTAINERS SPECIFICALLY
DESIGNATED FOR THIS PURPOSE.
D. ALL SPILLS WILL BE CLEANED UP IMMEDIATELY AFTER DISCOVERY.
E. THE SPILL AREA WILL BE KEPT WELL-VENTILATED AND PERSONNEL WILL WEAR APPROPRIATE PROTECTIVE
CLOTHING TO PREVENT INJURY FROM CONTACT WITH A HAZARDOUS SUBSTANCE.
F. SPILLS OF TOXIC OR HAZARDOUS MATERIALS WILL BE REPORTED TO THE APPROPRIATE STATE OR LOCAL
GOVERNMENT AGENCY, REGARDLESS OF SIZE.
G. THE SPILL PREVENTION PLAN WILL BE ADJUSTED TO INCLUDE MEASURES TO PREVENT THIS TYPE OF SPILL FROM REOCCURRING AND HOW TO CLEAN UP THE SPILL IF THERE IS ANOTHER ONE. A DESCRIPTION OF THE SPILL, WHAT CAUSED IT, AND THE CLEANUP MEASURES WILL ALSO BE INCLUDED.
H. THE SITE SUPERINTENDENT RESPONSIBLE FOR THE DAY-TO-DAY OPERATIONS WILL BE THE SPILL PREVENTION AND CLEANUP COORDINATOR. THEY WILL DESIGNATE SITE PERSONNEL WHO WILL RECEIVE SPILL PREVENTION AND CLEANUP TRAINING. THESE INDIVIDUALS WILL EACH BECOME RESPONSIBLE FOR A PARTICULAR PHASE OF PREVENTION AND CLEANUP. THE NAMES OF RESPONSIBLE SPILL PERSONNEL WILL BE POSTED IN THE MATERIAL
STORAGE AREA AND IN THE OFFICE TRAILER ON SITE.
ALLOW EASY
MOVEMENT OF
UNIT WITH GRATE
TO ENCLOSE GRATE
CLOSURE
WOVEN MONOFILAMENT
IP
STANDARD FABRIC IS A
FLAP FOLDS OVER
GRATE
DANDY BAG
DANDY BAG
LIFTING STRAPS
INLET PROTECTION IN EXISTING PAVEMENT
INSTALLATION
3. ROLL THE GRATE OVER SO THAT THE OPEN END IS UP
2. PLACE THE DANDY BAG OVER THE GRATE
4. PULL UP THE SLACK
1. STAND THE GRATE ON END
THE PATENTED DANDY BAG IS DESIGNED FOR USE WITH
FLAT GRATES (INCLUDING ROUND) AND MOUNTABLE CURBS TO
DETAIN SEDIMENT-LADEN STORM WATER. THE SUSPENDED
SOLIDS ARE ALLOWED TO SETTLE OUT OF THE SLOWED FLOW
PRIOR TO ENTERING THE DANDY BAG.
GRATE VELCRO
MAINTENANCE
INLET INSPECTION
TO INSPECT INLET, REMOVE DANDY BAG WITH GRATE INSIDE,
INSPECT CATCH BASIN AND REPLACE DANDY BAG BACK
INTO GRATE FRAME.
TO INSURE PROPER OPERATION REMOVE SILT, SEDIMENT, AND
DEBRIS FROM THE SURFACE AND THE VICINITY OF THE UNIT
WITH A SQUARE POINT SHOVEL OR STIFF BRISTLE BROOM AWAY
FROM ENVIRONMENTALLY SENSITIVE AREAS AND WATERWAYS
IN MANNER SATISFACTORY TO THE ENGINEER/INSPECTOR.
REMOVE FINE MATERIAL FROM INSIDE DANDY BAG AS
NEEDED. DISPOSE OF DANDY BAG NO LONGER IN USE AT
AN APPROPRIATE RECYCLING OR SOLID WASTE FACILITY.
8. HOLDING THE HANDLES, CAREFULLY PLACE THE
DANDY BAG WITH THE GRATE INSERTED INTO THE
CATCH BASIN FRAME
7. BE SURE THAT THE END OF THE GRATE IS COMPLETELY
COVERED BY THE FLAP OR THE DANDY BAG WILL NOT
WORK PROPERLY
6. PRESS THE VELCRO STRIPS TOGETHER
5. TUCK THE FLAP IN
ER-35N.T.S.
CONCRETE WASHOUT PIT DETAIL
10'
MIN. SANDBAG
AA
PLAN
LATH & FLAGGING
ON ALL SIDES
BERM
10 MIL
PLASTIC
LINING
10 MIL
PLASTIC LINING
BERM
SANDBAG
SECTION A-A
10'
MIN.
B B
PLAN
10 MIL
PLASTIC LINING
TWO-STACKED
2 X 12 ROUGH
WOOD FRAME
STAKE
(TYP)
10 MIL
PLASTIC LINING
WOOD FRAME SECURELY FASTENED
AROUND ENTIRE PERIMETER WITH
TWO STAKES
SECTION A-A
10'
MIN. STAKE (TYP.)
BB
STRAW BALE
(TYP.)
10 MIL
PLASTIC LINING PLAN
2"
1/8" DIA.
STEEL WIRE
STAPLE DETAIL
SECTION B-B
10 MIL
PLASTIC
LINING
STAPLES
(2 PER BALE) BINDING
WIRE
STRAW BALE
(TYP.)
WOOD OR METAL
STAKES (TWO PER
BALE)
NATIVE MATERIAL
(OPTIONAL)
Tb s-pr oj ec ts
\2
9\
-1
6\
Ca d-
Re vi t - T
BA
\C iv il\
-1
6_ C3
(D
ET
LS
).d w g
File details come from the government source that posted it. Updated .