This document contains responses to questions from contractors regarding Solicitation Number 36C24921R0010 from the Department of Veterans Affairs to renovate Building 34 at the James H. Quillen VA Medical Center in Mountain Home, Tennessee to correct facility deficiencies. The key project details are:
-
The solicitation involves renovating Building 34 to repair plaster ceilings, replace a skylight, repair water damage, remove and replace flooring, install missing gutters and downspouts, and remove exterior paneling. Finished surfaces are to be sealed with two coats of Sherwin-Williams satin or flat paint.
-
Contractors must submit questions by specifying the relevant specification, drawing number or section. Responses will not be provided without this reference information.
-
The response date for questions was January 27, 2021. Additional details on asbestos testing of flooring materials and revisions to demolition plans will be provided. Work on historical items and repairs to existing structures are included in the scope of work.
View the file
Other files
Show 40 more
Latest 50 of 58 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION (RFI)
36C24921R0010
PROJECT NUMBER: 621-18-102 Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents.
When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.
PROJECT TITLE: Renovate Bldg. 34 to Correct FCA
Deficiencies
PROJECT LOCATION: James H. Quillen VA Medical
Center
P.O. Box 4000
Mt. Home, TN 37684
SUBMITTED BY: City/State:
PHONE NO.:
TO: Dewayne L. Knowles
Dewayne.Knowles@va.gov
Diana K. Grube
Diana.Grube@va.gov
RFI NO.: 52-60 DATE:01-20-21 SPEC/DWG. REFERENCE:
REPLY NEEDED BY:
INFORMATION NEEDED:
52. Sheet 34-FX-001 shows the existing Water Site Plan around Building 34, the Symbol list on the drawing shows existing to remain line type as a lighter colored line type and new work line type as a darker line. Is the underground dark lines on the Water Site Plan part of this contract? If so, could the VA provide a scale and Civil Drawings to accommodate the work?
53. The existing skylight in the attic may have to be removed and replaced to allow access for new equipment. During the Site Visit existing conditions show extensive water damage to the existing wood structure supporting the skylight.
Does the VA intend for the General Contractor to have this repaired?
54. The Existing skylight has caused severe water damage to the existing conditions within the Plenum Return Grille
Room. Does the VA intend for the General Contractor to have this repaired?
55. Sheet 34-AD-105 shows note 9 in Room E104 Museum. To replace and repair plaster ceiling as required. There is several locations in this room with Flakey Paint and possible Plaster repairs. Should the GC account for the entire room in their repair, as it wasn't possible to quantify the locations during the site visit. Can the VA confirm if the paint is LEAD based?
56. In Room E104 Museum, will the historical items be removed prior to Building turnover?
57. In Room E104 Museum, an existing Beam seems to show water damage with flakey paint. Does the VA intend for the General Contractor to have this repaired?
58. There is not a Finish Schedule provided in the Contract Documents, after repairing the plater ceiling in Room E104 and E101 does the VA intend for the General Contractor to Re-paint the ceiling? If so, can the VA provide a detailed Finish Schedule.
59. Sheet 34-AD-105, Room E144 Storage, has an existing tile floor not shown to be removed. This is where the new walls are being built. Does the VA intend for the General Contractor to remove this floor? If so, can the VA confirm if this floor has been testes for Asbestos?
60. Sheet 34-A-102, Site Visit showed that an existing down spout is missing from the North-East Corner of Area A, Room E116 Kitchen. The Drawing doesn't indicate replacing the existing gutter or down spout in this area. Does the VA intend for the General Contractor to account for this in their base bid?
12. Sheet 34-AD-105, Room E110 Carpenter Shop. Does the VA inl Contractor to remove the paneling on the exterior wall and columns that are to remain in place?
mailto:Dewayne.Knowles@va.gov mailto:Dewayne.Knowles@va.gov mailto:diana.grube@va.gov mailto:diana.grube@va.gov
REPLY:
52. Same as question 48 (GLMV)
53. Same as question 49
54. Same as question 50
55. Same as question 51
56. Yes
57. Yes, existing beam is intended to be repaired. (GLMV)
58. Seal repaired/patched plaster with two coats of Sherwin-Williams satin, flat, finish. (GLMV)
59. Demolition floor plan to be updated to show where floor is to be removed. Reference Asbestos Abatement
Plans for materials containing asbestos. (GLMV)
60. Yes, install new gutter and downspout where missing. Include this in base bid of project. (GLMV)