This Statement of Proposal Items outlines the pricing structure for the renovation of Historic Building 4 at a VA facility, with a contract completion time of 450 calendar days after Notice to Proceed. The work is divided into two main proposal items: Site Work (Item I) covering existing conditions, earthwork, exterior improvements, and utilities; and Building Renovation (Item II) encompassing comprehensive building systems including concrete, masonry, metals, thermal protection, openings, fire suppression, HVAC, electrical, and communications.
Three deduct alternates are specified: Alternate 1 reduces the performance period by 115 days and covers basement finishes; Alternate 2 reduces the period by 30 days and involves replacing wood plank with ACT; and Alternate 3 reduces the period by 7 days and covers sealed concrete in basement and utility areas. The offer must be valid for 120 calendar days after the due date. All alternates are to be deducted from Proposal Item II (Building Renovation), and bidders must provide total pricing for Items I and II, along with separate pricing for each deduct alternate.
View the file
Other files for this federal contract opportunity
Show all 50
Z2AA - Renovate Historic Building 4 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C246R0030 0003 Statement of Proposal Items
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within one-hundred and twenty (120) calendar days after the date offers are due.
Contract completion time: Four Hundred and Fifty (450) calendar days after Notice to Proceed (NTP)
PROPOSAL ITEM I (SITE WORK):
Work includes all labor, material, equipment, and supervision to perform all work required of the following divisions in coordination with all associated drawings:
02 Existing Conditions, 31 Earthwork, 32 Exterior Improvements, and 33 Utilities
PROPOSAL ITEM II (BUILDING RENOVATION):
Work includes all labor, material, equipment, and supervision to perform all work required of the following divisions in coordination with all associated drawings:
02 Existing Conditions, O3 Concrete, 04 Masonry, O5 Metals, O6 Wood Plastics and Composites, 07 Thermal and Moisture Protection, 08 Openings, 10 Specialties, 12 Furnishings, 14 Conveying Equipment, 21 Fire Suppression, 22 Plumbing, 23 Heating Ventilation and Air Conditioning, 26 Electrical, 27 Communications, and 28 Electronic Safety and Security.
PROPOSAL TOTAL ITEMS I, II: $_______________________________________
PROPOSAL ALTERNATES: PROPOSAL ALTERNATES ARE TO BE DEDUCTED FROM PROPOSAL ITEM II – BUILDING RENOVATION.
PROPOSAL ITEM III (DEDUCT ALT 1): $ - _____________________________
Period of Performance (- 115 Calendar days)
Work includes all labor, material, equipment and supervision to perform the required Basement Finishes.
PROPOSAL ITEM IV (DEDUCT ALT 2): $ -______________________________
Period of Performance (- 30 Calendar days)
Work includes all labor, material, equipment and supervision to perform the required Replace Wood Plank for ACT
PROPOSAL ITEM V (DEDUCT ALT 3): $ ________________________________
Period of Performance ( - 7 Calendar days )
Work includes all labor, material, equipment and supervision to perform the required for Sealed Concrete in Basement and Utility Areas