INSTRUCTIONS CONDITIONS AND OTHER STATEMENTS TO BIDDERS-OFFERORS .docx

DOCX document 36 KB Posted

Attached to
Z2AA - Renovate Historic Building 4
Solicitation number
36C24624R0030
Issued by

About this file

This is an Instructions to Bidders document for VA solicitation 36C24624R0030, a renovation project of Historic Building 4 at a VA facility. The solicitation is a 100% SDVOSB set-aside with proposals due January 23, 2025 at 3:00 PM Eastern, requiring both hard copy and electronic submissions to the VA RPO East office in Fayetteville, NC.

The procurement uses a Best Value Tradeoff approach with technical factors significantly more important than price. The estimated cost range is $5-10 million with a 450-day completion timeline. Key requirements include submission of technical approach (experience on 5 similar $5M+ hospital projects completed within 7 years), management plan, key personnel resumes (Project Manager, Site Superintendent, SSHO), past performance, and pricing details. Additional requirements include OSHA safety certifications (10-hour for employees, 30-hour for competent person), TB testing documentation, EMR rating ≤ 1.0, and no more than three serious or one repeat/willful OSHA violation in three years. The project involves complete renovation of a historic building for administrative space, including elevator addition, stairwell upgrades, and new mechanical/electrical systems, with required compliance with VA Physical Security and Historic Preservation requirements.

View the file

Other files

File Type Posted
36C24625C0027_1 Award Notice.docx DOCX document
230923 Direct-Digital Control System Connect to Existing N4.pdf PDF
36C24624R0030 0006.pdf PDF
1_b H - Renovate Building 4 IFC pages 12-14.pdf PDF
1_a G - Renovate Building 4 IFC pages 2-3.pdf PDF
1_a G - Renovate Building 4 IFC pages 4-6.pdf PDF
1_a G - Renovate Building 4 IFC pages 7-10.pdf PDF
1_a G - Renovate Building 4 IFC page 1.pdf PDF
5_Mech - Renovate Building 4 IFC pages 110-128.pdf PDF
Specification Section 00 01 15 - LIST OF DRAWING SHEETS 01 21 25.pdf PDF
6_Elec - Renovate Building 4 IFC pages 129-155.pdf PDF
3_Arch - Renovate Building 4 IFC pages 36-85.pdf PDF
2_C - L and S - Renovate Building 4 IFC pages 15-35.pdf PDF
36C24624R0030 0005.docx DOCX document
4_FP and P - Renovate Building 4 IFC pages 86-109.pdf PDF
Drawings.zip ZIP file
36C24624R0030 0004.docx DOCX document
36C24624R0030 0003.docx DOCX document
233400 - HVAC FANS.pdf PDF
230923 - DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC.pdf PDF
Proposal Item II Cost Breakdown.xlsx XLSX spreadsheet
233700 - AIR OUTLETS AND INLETS.pdf PDF
232300 - REFRIGERANT PIPING.pdf PDF
230711 - HVAC AND BOILER PLANT INSULATION.pdf PDF
Statement of Proposal Items - 0003.docx DOCX document
233100 - HVAC DUCTS AND CASINGS.pdf PDF
237200 - AIR TO AIR ENERGY RECOVERY EQUIPMENT.pdf PDF
PL902 - PLUMBING DOMESTIC WATER ISOMETRICS.pdf PDF
Asbestos Reinspection Report - August 2019.pdf PDF
Building 4 and 16 LBP Results.pdf PDF
Proposal Item I Cost Breakdown.xlsx XLSX spreadsheet
014529 - TESTING LABORATORY SERVICES.pdf PDF
234000 - HVAC AIR CLEANING DEVICES.pdf PDF
238200 - CONVECTION HEATING AND COOLING UNITS.pdf PDF
Proposal Item III Cost Breakdown.xlsx XLSX spreadsheet
230512 - GENERAL MOTOR REQUIREMENTS FOR HAVAC AND STEAM GENERATION EQUIPMENT.pdf PDF
Fayetteville - Temp Fence.pdf PDF
230511 - COMMON WORK RESULTS FOR HVAC.pdf PDF
238216 - AIR COILS.pdf PDF
232113 - Hydronic Piping.pdf PDF
230541 - NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.pdf PDF
Proposal Item IV Cost Breakdown.xlsx XLSX spreadsheet
Asbestos - Lead Paint Survey 12-31-2020.pdf PDF
238143 - AIR SOURCE UNITARY HEAT PUMPS.pdf PDF
230593 - TESTING ADJUSTING AND BALANCING FOR HVAC.pdf PDF
230800 - COMMISSIONING OF HVAC SYSTEMS.pdf PDF
Proposal Item V Cost Breakdown.xlsx XLSX spreadsheet
238129 - VARIABLE REFRIGERANT FLOW HVAC SYSTEMS.pdf PDF
Geotech Report_Fayetteville Bldg 4 Renovation.pdf PDF
36C24624R0030 0002.docx DOCX document
Show 40 more

Latest 50 of 64 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24624R0030 0003

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

SUBMISSION OF PROPOSALS

The bidder shall submit the following in response to this Invitation for Bids:

(a) A completed and signed Standard Form 1442.

(b) A completed copy of the Representations and Certifications (See FAR 52.204-8 Annual Representations and Certifications (JAN 2025)).

(c) A fully executed bid bond.

(d) Documentation of their safety record.

(e) All forms and/or certifications as directed in the solicitation, including the specifications.

NOTE: ONE HARD AND ELECTRONIC COPY OF PROPOSALS ARE TO BE DELIVERED TO:

DERTMENT OF VETERANS AFFAIRS RPO EAST, NETWORK CONTRACTING OFFICE 6 201 HAY STREET, SUITE 305 FAYETTEVILLE, NC 28301 ATTN: WAYNE GOODMOND

PROPOSAL DUE DATE: JANUARY 23, 2025 – 3:00 PM EASTERN

BASIS FOR AWARD: This is a competitive Best Value Tradeoff (Tradeoff) source selection in which technically acceptable competing Offerors will be assigned a Technical Risk Rating Assessment Rating and will then be evaluated for Price fairness and reasonableness. All evaluation factors other than price, when combined, are significantly more important than price alone. The government reserves the right to award a contract to other than the lowest priced offer if the lowest priced Offeror is determined to have a Technical Risk Rating of “Moderate” or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision, where the perceived benefits of the higher priced proposal, and the rationale for tradeoffs, shall be documented in the contract file in accordance with FAR 15.406.

(A) GENERAL INSTRUCTIONS:

1. All proposal preparation cost will be the sole responsibility of the Offeror. The Government will not reimburse any firm for their proposal preparation cost.

2. The price, technical response and past performance of each Offeror will be evaluated independently. Offerors shall separately document each of the three factors. Each of the three offer sections shall therefore be labeled with the Offerors name, business address, and VA Solicitation Number.

3. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including these instructions, the terms and conditions, representations and certifications, and technical and past performance requirements. Failure to meet a requirement may result in an offer being ineligible for award. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale.

The offer shall consist of two (2) separate parts:

• Volume I

· TECHNICAL APPROACH - Offerors are required to submit for each of sub factors:

· SUBFACTOR I

· Experience

· MANAGEMENT

· SUBFACTOR II

· Key Personnel

· Safety Plan

· PAST PERFORMANCE

· SUBFACTOR III

· Past Project Performance

• Volume II - PRICE PR0P0SAL

(B) SPECIFIC INSTRUCTIONS

1. VOLUME I - TECHNICAL APPROACH

Subfactor I - EXPERIENCE

The offeror shall Submit five (5) construction projects that best demonstrates the offeror’s experience on projects that are similar in size, scope, and complexity to this RFP. The projects must demonstrate an offeror’s recent and relevant construction experience as a prime construction contractor directly responsible to the owner and managing multiple subcontractors. Projects relevant to this requirement are construction work at a fully operational hospital or medical facility with a minimum value of $5,000,000 that were 100% completed no more than seven (7) years prior to the issuance of this RFP.

Projects submitted must include the following information:

· Project Title, Project Location (Physical Address), and contract ID number if applicable

· Project owner name and contact information (mailing address, phone number, and email address)

· A description of the scope of work that fully outlines all work accomplished. Indicate whether or not the offerors company was the prime contractor and what work was performed by the prime contractor.

· Project prime contractor and major subcontractors

· Project statistics, including start and completion dates (original vs. actual) and project cost (original vs. actual). If original vs. actual completion dates and project cost differ, shall provide an explanation as to why they differ (list mods, titles, and amounts).

2. VOLUME 1 – MANAGEMENT APPROACH

Subfactor II – MANAGEMENT PLAN Offerors shall provide a detailed management plan that thoroughly indicates their ability to manage this project per federal safety requirements. This plan must cover the firm’s management structure, accident prevention and safety plan and explanations of all key personnel in the firm and their role as it would relate to this project, detailed descriptions of the firm’s corporate approach to safety, quality control, accident prevention and site security. Delineate the approximate percentage of work the prime contractor will perform and the approximate percentage of work the subcontractors (collectively) will perform. How the firm’s management interacts with the VA contract and projects personnel.

Subfactor II – KEY PERSONNEL AND SAFETY PLAN The Offeror shall provide a resume for each of the following key personnel: Project Manager, Site Superintendent and Site Safety and Health Officer (SSHO) that will be working on the project. Also provide information on any major subcontractors. For each resume, the information must clearly indicate the persons years of experience and ability to handle projects of similar scope and complexity. Include company name; the name of the individual; relevant listing of experience; qualifications such as specialized training, education, experience, durations etc. For any subcontractors identified, provide a resume for that company, identify any key personnel that will be assigned to the contract resulting from this solicitation, and the relevant experience of both the company and any key personnel that were identified. The VA will use the information provided to evaluate, among other things, specialized experience and competence.

Subfactor III – PAST PERFORMANCE

Offerors will be required to submit the information on past performance for all projects provided under experience.

If a completed past performance evaluation is available in the Past Performance Information Retrieval System (PPIRS), it shall be submitted with the proposal for each project referenced for Past Performance. If there is not a completed past performance evaluation available in PPIRS, then the Offeror shall submit a Past Performance Questionnaire (PPQ) for each project referenced for Experience. The Offeror shall notify their client that the PPQ shall be submitted via email to the Government’s point of contact, Wayne.Goodmond@va.gov. If the offeror is unable to obtain a completed PPQ from a client for a project before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project.

2. VOLUME II - PRICE PROPOSAL.

The offeror shall submit the following in response to this Request for Proposals:

(a) A completed and signed Standard Form 1442. Contractor must acknowledge all amendments with submission of proposal.

(b) A completed copy of the Representations and Certifications (See FAR 52.204-8 Annual Representations and Certifications (JAN 2025)).

(c) A fully executed bid bond.

(d) Itemized Schedule of Values Cost breakdown NOTE 1: Offerors must submit an itemized breakdown of costs (Attachment A) to include an Itemized Schedule of Values Cost breakdown for Proposal Item I, II, III, IV, and V in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs, overhead and profit and shall cover all work involved in accordance with (IAW) Statement of Work (SOW). If Itemized Schedule of Values Cost breakdown is not provided, offerors' proposal may be deemed non-compliant.

NOTE 2: Copies of all subcontractor quotes are required.

All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record with their bid.

1. A self-certification on company letterhead that the bidder has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. Bidders shall submit copies of their OSHA logs (OSHA Form 300A) for the past three years with their bid. If the firm has been in business for less than three years, they shall submit copies of their OSHA logs for the period of time they have been in business.

2. Information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.

Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

NOTE: Failure to submit this documentation with the proposal shall be grounds for the proposal to be considered non-compliant.

DESCRIPTION OF WORK: See “Statement of Work”.

COST RANGE: $5,000,000.00 - $10,000,000.00

NAICS: The NAICS Code for this procurement is 236220, Commercial and Institutional Building Construction, with a maximum small business size standard of $45 million.

COMPLETION TIME: All work shall be completed within Four Hundred and Fifty (450) calendar days from receipt of the Notice to Proceed.

SDVOSB SET-ASIDE: This procurement is 100% set-aside for Service-Disabled, Veteran-Owned Small Business (SDVOSB). Bids are solicited only from SDVOSB concerns and bids received from concerns that are not SDVOSB concerns shall be rejected. In order to be considered, the firm must be shown in the www.veterans.certify.sba.gov website as verified at the time of submission of their bid.

CONTRACTOR RESPONSIBILITY: Contractor shall be required to complete all contract work and schedule a final inspection within the specified contract performance period. Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a Contractor-caused delay, the Contractor shall be in default status. If the Government determines it to be in the best interest of the Government to allow the Contractor to continue to perform contract work, the Contractor shall provide equitable consideration to the Government for additional time granted for completion of contract work. Such agreement shall not be deemed a waiver of the Government’s right to terminate this contract in the event the Contractor fails to complete the contract work (including scheduling of the final inspection) on or before the completion date.

REQUIRED CERTIFICATION: THE CERTIFICATION CITED AT 852.219-75, VA NOTICE OF LIMITATIONS ON SUBCONTRACTING – CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) – This certification is required to be completed and accompany your submitted bid. Failure to complete may cause your bid to be determined non-Responsive.

TRAINING: All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.

TB TESTING:

In accordance with VHA Directive 2011-036, CEOSH Construction Safety Guidebook, 2012 1.1.1 VHA Policy, CDC 2005 Guidelines for Preventing the Transmission of Mycobacterium tuberculosis in Health-Care Settings.

(a) The contractor must provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the worksite and been found have negative TB screening reactions. Contractors will be required to show documentation of negative TB screening reactions for any additional workers who are added after the 90-day requirement before they will be allowed to work on the work site.

NOTE: This can be the Center for Disease Control (CDC) and Prevention and two-step skin testing or a Food and Drug Administration (FDA)-approved blood test.

(b) Contract employees manifesting positive screening reactions to the tuberculin must be examined according to current CDC guidelines prior to working on VHA property.

(c) Subsequently, if the employee is found without evidence of active (infectious) pulmonary TB, a statement documenting examination by a physician must be on file with the employer (construction contractor), noting that the employee with a positive tuberculin screening test is without evidence of active (infectious) pulmonary TB.

(d) If the employee is found with evidence of active (infectious) pulmonary TB, the employee would require treatment with a subsequent statement to the fact on file with the employer before being allowed to return to work on VHA property.

PRE-PROPOSAL CONFERENCE: NO ADDITIONAL CONFERENCES WILL BE CONDUCTED!!

KEYS: All keys provided the Contractor for use during the project shall be returned to the Contracting Officer's Representative (COR) at completion of the work or upon request. No keys shall be reproduced by the Contractor. There shall be a charge of $10.00 for each key that is lost or not returned to the COR. Payment shall be made to the VA Medical Center, Fayetteville, North Carolina upon receipt of a Bill of Collection.

PREPARATION OF BIDS/OFFERS/PROPOSALS: Neither the VAMC nor the VISN 6 NCO will pay for any costs incurred in preparation and submission of bids or proposals.

PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

The C&A requirements do not apply and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.

VETS 4212: As legislatively mandated under 38 U.S. Code Section 4212, codified at 41 CFR 61-300, contractors and subcontractors who enter into, or modify a contract or subcontract with the federal government, and whose contract meets the criteria set forth in the above legislation / regulations, are required to report annually on their affirmative action efforts in employing veterans. Data reported through form VETS-4212 is used by OFCCP in compliance evaluations. Submission of the VETS 4212 reporting information can be done electronically at: https://www.dol.gov/agencies/vets/programs/vets4212. Award cannot be made unless the awardee has filed their VETS 4212 report. Therefore, all offerors are encouraged to file every year.

SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Bidders are encouraged to ensure that they are registered in SAM prior to submitting their bid.

RENOVATION SITE VISUAL CAN BE SEEN AT THE LOCATIONS LISTED BELOW: THIS DOES NOT ABSOLVE PROPOSERS OF VISITING THE SITE.

Basement, 1st Floor and 2nd Floor https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmy.matterport.com%2Fshow%2F%3Fm%3DCXuvDrQt3Zx&data=05%7C01%7C%7Cef83d5f28c0e485fc7a508dbb94140f9%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638307462133036048%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=FhN2%2Fa1immJzMpuszaCMWG31fJ97xGNz1%2Fy4%2BC6EuKE%3D&reserved=0 Note: Rooms 203 and 205 were not scanned. See pictures for those two rooms.

Attic https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmy.matterport.com%2Fshow%2F%3Fm%3DB5btLfBr1UH&data=05%7C01%7C%7Cef83d5f28c0e485fc7a508dbb94140f9%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638307462133036048%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=7InSrfeUXzWSI81eI6EjCoVeUCs4X3XwWwDSLI23YpQ%3D&reserved=0

Outside https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmy.matterport.com%2Fshow%2F%3Fm%3DLLnN6KvfvLs&data=05%7C01%7C%7Cef83d5f28c0e485fc7a508dbb94140f9%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638307462133036048%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=o8DUDUkq4YE76sL%2FM2aiauL5q2SWbt9APZxSq2VqklQ%3D&reserved=0

File details come from the government source that posted it. Updated .