This is a technical specification section (23 37 00) for Air Outlets and Inlets, part of the renovation project for Historical Building 4. The document details requirements for HVAC air distribution components including diffusers, registers, and grilles.
The specification outlines materials and performance requirements for supply, return, and exhaust air devices. Key requirements include: ceiling diffusers must be suitable for surface mounting with off-white finish and square/round neck connections; supply registers must have double deflection type with horizontal face bars and opposed blade dampers; materials must be steel or aluminum with aluminum construction required for shower stall exhaust registers; and devices must comply with Air Diffusion Council Code 1062GRD and NFPA 90A standards. The document provides detailed specifications for mounting, finish requirements, pressure drop limitations (maximum 37 Pa at design flow), and noise control criteria. Installation must coordinate with other trades and protect equipment during construction, with final testing and balancing required per referenced sections.
View the file
Other files for this federal contract opportunity
Show all 50
Z2AA - Renovate Historic Building 4 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovation of Historical Building 4
Project #565 20 101
02-01-20
AIR OUTLETS AND INLETS
23 37 00 - 1
SECTION 23 37 00
AIR OUTLETS AND INLETS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Air Outlets and Inlets: Diffusers, Registers, and Grilles.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.
B. Section 08 90 00, LOUVERS and VENTS.
C. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS.
D. Section 23 05 11, COMMON WORK RESULTS FOR HVAC and STEAM GENERATION.
E. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and
EQUIPMENT.
F. Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC.
1.3 QUALITY ASSURANCE
A. Refer to Article, QUALITY ASSURANCE, in Section 23 05 11, COMMON WORK
RESULTS FOR HVAC.
B. Fire Safety Code: Comply with NFPA 90A.
1.4 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, and SAMPLES.
B. Manufacturer's Literature and Data:
1. Air intake/exhaust hoods.
2. Diffusers, registers, grilles and accessories.
C. Coordination Drawings: Refer to article, SUBMITTALS, in Section 23 05
11, COMMON WORK RESULTS FOR HVAC.
1.5 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. Air Diffusion Council Test Code:
1062 GRD-2015...........Certification, Rating, and Test Manual 4th
Edition
C. American Society of Civil Engineers (ASCE):
ASCE7-2017..............Minimum Design Loads for Buildings and Other
Structures
D. American Society for Testing and Materials (ASTM):
02-01-20
AIR OUTLETS AND INLETS
23 37 00 - 2
A167-99 2009............Standard Specification for Stainless and
Heat-Resisting Chromium-Nickel Steel Plate, Sheet and Strip
B209- 2014..............Standard Specification for Aluminum and
Aluminum-Alloy Sheet and Plate
E. National Fire Protection Association (NFPA):
90A-2021................Standard for the Installation of Air
Conditioning and Ventilating Systems
F. Underwriters Laboratories, Inc. (UL):
181-2013................UL Standard for Safety Factory-Made Air Ducts and Connectors
PART 2 - PRODUCTS
2.1 EQUIPMENT SUPPORTS
Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
2.2 AIR OUTLETS AND INLETS
A. Materials:
1. Steel or aluminum Exhaust air registers located in shower stalls shall be constructed from aluminum. Provide manufacturer's standard gasket.
2. Exposed Fastenings: The same material as the respective inlet or outlet. Fasteners for aluminum may be stainless steel.
3. Contractor shall review all ceiling drawings and details and provide all ceiling mounted devices with appropriate dimensions and trim for the specific locations.
B. Performance Test Data: In accordance with Air Diffusion Council Code
1062GRD. Refer to Section 23 05 41, NOISE and VIBRATION CONTROL FOR
HVAC PIPING and EQUIPMENT for NC criteria.
C. Air Supply Outlets:
1. Ceiling Diffusers (CD-1): Suitable for surface mounting, exposed
T-bar or special tile ceilings, off-white finish, square or round neck connection as shown on the drawings. Provide plaster frame for units in plaster ceilings.
a. Square, louver, fully adjustable pattern: Round neck, surface mounting unless shown otherwise on the drawings. Provide equalizing or control grid and volume control damper.
b. Perforated face type: Manual adjustment for one-, two-, three-, or four-way horizontal air distribution pattern without change of air volume or pressure. Provide equalizing or control grid and
02-01-20
AIR OUTLETS AND INLETS
23 37 00 - 3 opposed blade over overlapping blade damper. Perforated face diffusers for VAV systems shall have the pattern controller on the inner face, rather than in the neck and designed to discharge air horizontally at the ceiling maintaining a Coanda effect.
c. Slot diffuser/plenum:
1) Diffuser: Frame and support bars shall be constructed of heavy gauge extruded aluminum. Form slots or use adjustable pattern controllers, to provide stable, horizontal air flow pattern over a wide range of operating conditions.
2) Galvanized steel boot lined with 13 mm (1/2 inch) thick fiberglass conforming to NFPA 90A and complying with UL 181 for erosion. The internal lining shall be factory-fabricated, anti-microbial, and non-friable.
3) Provide inlet connection diameter equal to duct diameter shown on drawings or provide transition coupling if necessary. Inlet duct and plenum size shall be as recommended by the manufacturer.
4) Maximum pressure drop at design flow rate: 37 Pa
(0.15 inch W.G.)
2. Supply Registers: Double deflection type with horizontal face bars and opposed blade damper with removable key operator.
a. Margin: Flat, 30 mm (1-1/4 inches) wide.
b. Bar spacing: 20 mm (3/4 inch) maximum.
c. Finish: Off white baked enamel for ceiling mounted units. Wall units shall have a prime coat for field painting, or shall be extruded with manufacturer's standard finish.
3. Supply Grilles: Same as registers but without the opposed blade damper.
D. Return and Exhaust Registers and Grilles: Provide opposed blade damper without removable key operator for registers.
1. Finish: Off-white baked enamel for ceiling mounted units. Wall units shall have a prime coat for field painting, or shall be extruded aluminum with manufacturer's standard aluminum finish.
2. Standard Type: Fixed horizontal face bars set at 30 to 45 degrees, approximately 30 mm (1-1/4 inch) margin.
3. Perforated Face Type: To match supply units.
4. Grid Core Type: 13 mm by 13 mm (1/2 inch by 1/2 inch) core with 30 mm (1-1/4 inch) margin.
02-01-20
AIR OUTLETS AND INLETS
23 37 00 - 4
5. Linear Type: To match supply units.
6. Door Grilles: Are furnished with the doors.
7. Egg Crate Grilles: Aluminum or Painted Steel 1/2 by 1/2 by 1/2 inch grid providing 90% free area.
a. Heavy extruded aluminum frame shall have countersunk screw mounting. Unless otherwise indicated, register blades and frame shall have factory applied white finish.
b. Grille shall be suitable for duct or surface mounting as indicated on drawings. All necessary appurtenances shall be provided to allow for mounting.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Comply with provisions of Section 23 05 11, COMMON WORK RESULTS FOR
HVAC AND STEAM GENERATION, particularly regarding coordination with other trades and work in existing buildings.
B. Protection and Cleaning: Protect equipment and materials against physical damage. Place equipment in first class operating condition, or return to source of supply for repair or replacement, as determined by the CxA and COR. Protect equipment during construction against entry of foreign matter to the inside and clean both inside and outside before operation and painting.
3.2 TESTING, ADJUSTING AND BALANCING (TAB)
Refer to Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC.
3.3 OPERATING AND PERFORMANCE TESTS
Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.