This appears to be pages 4-6 of the IFC (Issued for Construction) drawings for the renovation of Building 4, related to solicitation 36C24624R0030. The document details a major renovation project for a historic Building 4 at a VA facility, requiring complete modernization for administrative and office space. The project includes adding an elevator accessible to all levels, code-compliant stairwells for life safety egress, and comprehensive updates to mechanical, plumbing, electrical, and fire protection systems.
The design requires Revit Building Information Modeling (LOD 300 or higher) and must comply with VA Physical Security and Resiliency Design Manual requirements for Mission Critical structures. Historic preservation requirements from National and State Historic Preservation Office must be followed for exterior renovations. The work includes asbestos and lead abatement, utility relocations, and requires careful management of pedestrian and vehicle traffic. The contractor must submit detailed mobilization plans addressing temporary utilities, fencing, parking, signage, materials storage, and dumpster placement before beginning work, with oversight from a Site Superintendent, SSHO, and Quality Control Manager.
View the file
Other files
Show 40 more
Latest 50 of 64 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /F a y e tt e v ill e N
C V
A
B ld g
R e n o v a ti o n /F
F E
F a y e tt e v ill e
R e n o v a te
B
A rc h rv t
/2
/2
:5
:1
P
M
GI004
SECOND FLOOR AXONOMETRIC
DRAWINGS
07/24/2023 SS KT
RENOVATE HISTORIC BUILDING 4 565-20-101
2300 RAMSEY STREET, FAYETTEVILLE, NC 28301
ISSUED FOR
CONSTRUCTION
FAYETTEVILLE
VA MEDICAL
CENTER Approved: FAYETTEVILLE VA MEDICAL CENTER
3D SECOND FLOOR AXON
No. Revisions: Date:
REV 0 07/24/2023
Steve Image
GENERAL SYMBOLS
SCALE:
B2
VIEW NAME
1/8" = 1'-0"
A4
EARTH
EARTH GRAVEL
CONCRETE
METALS
BRICK
CMU
TILE
STONE
WOOD
GYPSUM
GLASS
INSULATION
REGULAR
STEEL ALUMINUM
FACE COMMON
CMU
CERAMIC
MARBLE LIMESTONE
FINISH BLOCKING
PLASTER OR GWB
LARGE SCALE SMALL SCALE
BATT OR
LOOSE
RIGID
SURFACE
DETAIL TITLE
BUILDING SECTION
WALL SECTION
EXTERIOR / INTERIOR
ELEVATION
INTERIOR MULTI-VIEW
ELEVATION
MATERIALS REFERENCE
DETAIL SECTION
AE402
C4
AE201
A1
AE305
SIM
A1
AE305
SIM
A1
AE305
SIM
AE505
C3
A3
ELEVATION NUMBER
SHEET ON WHICH
ELEVATION IS DRAWN
ELEVATION NUMBER
SHEET ON WHICH
ELEVATION IS DRAWN
ROOM NUMBER
DOOR NUMBER
KEYNOTE
WALL TYPE
REVISION NUMBER
ELEVATION INDICATION
COLUMN GRID
IDENTIFICATION
NORTH ARROW
WINDOW NUMBER
A1
EQUIPMENT TAG
D
NTRUE
NORTH
MATCHLINE
FINISH , FINISH MATERIAL FINISH EXTENTS
SPRAY FOAM
B505E
1t
S
1t
ROOM NAME
A505B
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /F a y e tt e v ill e N
C V
A
B ld g
R e n o v a ti o n /F
F E
F a y e tt e v ill e
R e n o v a te
B
A rc h rv t
/2
/2
:5
:1
P
M
GI005
GENERAL NOTES, SYMBOLS AND
ABBREVIATIONS
07/24/2023 SS KT
RENOVATE HISTORIC BUILDING 4 565-20-101
2300 RAMSEY STREET, FAYETTEVILLE, NC 28301
ISSUED FOR
CONSTRUCTION 4
FAYETTEVILLE
VA MEDICAL
CENTER Approved: FAYETTEVILLE VA MEDICAL CENTER
A
A/C AIR CONDITIONING
AB ANCHOR BOLT / AIR BLENDER
ABS ACRYLONITRILE-BUTADIENE-STYRENE
AC ALTERNATING CURRENT / AIR COMPRESSOR
ACP ASBESTOS CEMENT PIPE
ACU AIR CONDITIONING UNIT
AD AREA DRAIN
ADA AMERICANS WITH DISABILITIES ACT
ADJ ADJACENT / ADJUSTABLE
ADR ACCESS DOOR
AFF ABOVE FINISH FLOOR
AHJ AUTHORITY HAVING JURISDICTION
AHU AIR HANDLING UNIT
AL ALUMINUM
ALT ALTERNATE
APC ACOUSTICAL PANEL CEILING
APPROX APPROXIMATELY
APT APARTMENT
ARCH ARCHITECT(URAL)
ASPH ASPHALT
ATB AIR TERMINAL BOX
ATC ACOUSTICAL TILE CEILING
ATD AIR TRANSFER DUCT
ATU AIR TERMINAL UNIT
AUX AUXILIARY
AVG AVERAGE
AWT ACOUSTICAL WALL TREATMENT
AZ AZIMUTH
B
BB BALLED AND BURLAPPED
BD BOARD
BDD BACK DRAFT DAMPER
BE BOTTOM ELEVATION
BL BUILDING LINE
BLDG BUILDING
BLKG BLOCKING
BM BENCH MARK / BEAM
BR BARE ROOT
BRG BEARING
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNIT PER HOUR
C
C/C CENTER TO CENTER
CAB CABINET
CB CIRCUIT BREAKER / CATCH BASIN
CC COOLING UNIT
CE COVER ELEVATION
CEM CEMENT
CFM CUBIC FEET PER MINUTE
CG CORNER GUARD
CH CHILLER
CI CURB INLET / CAST IRON
CIP CAST IRON PIPE
CJ CONTROL JOINT OR CONTRACTION JOINT
CKT CIRCUIT
CL CENTER LINE
CLG CEILING
CLO CLOSET
CLR CLEAR
CM CENTIMETER
CMH CUBIC METER PER HOUR
CMP CORRUGATED METAL PIPE
CMU CONCRETE MASONRY UNIT
CO CLEANOUT / CARBON MONOXIDE
CO2 CARBON DIOXIDE
COL COLUMN
COMB COMBINATION / COMBINE
COMP COMPRESSIBLE
CONC CONCRETE
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTINUOUS / CONTINUATION
CONTR CONTRACTOR
CORR CORRIDOR
CP CEMENT PIPE
ABBREVIATIONS
1. THE GENERAL CONTRACTOR SHALL VERIFY ALL EXISTING DIMENSIONS AND FIELD CONDITIONS PRIOR TO DEMOLITION AND CONSTRUCTION. IF PROVIDED, THE GENERAL CONTRACTOR SHALL EXAMINE EXISTING BUILDING DOCUMENTS. THE CONTRACTOR SHALL BRING ANY DISCREPANCIES TO THE IMMEDIATE ATTENTION OF
THE CONTRACTING OFFICER REPRESENTATIVE (C.O.R.).
2. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF EXISTING ITEMS TO REMAIN DURING DEMOLITION AND CONSTRUCTION.
3. MAINTAIN EXIT EGRESS PATHS TO EXISTING EXIT DOORS AT ALL TIMES DURING CONSTRUCTION.
4. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF ALL CONSTRUCTION ROUTES BEYOND THE AREAS OF WORK AND THE ROUTES MUST BE
RETURNED TO THEIR ORIGINAL CONDITION AT THE END OF THE PROJECT.
5. IF CONSTRUCTION NOISE IS ANTICIPATED, SUBMIT A WRITTEN REQUEST TO THE C.O.R. FOR THE SCHEDULED TIME OF CONSTRUCTION ACTIVITIES. THE CONTRACTING OFFICER REPRESENTATIVE RESERVES THE RIGHT TO DISCONTINUE NOISY CONSTRUCTION AT ANY TIME. NO RADIOS SHALL BE PERMITTED AT ANY TIME IN WORK
AREAS ADJACENT TO OCCUPIED SPACES.
6. REFER TO GENERAL REQUIREMENTS SPECIFICATION SECTION 01 00 00 REGARDING PROCESS FOR DISRUPTION/SHUT DOWN OF EXISTING SERVICES AND UTILITIES.
7. THE GENERAL CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PREVENT DAMAGE TO THE VA’S AREAS ADJACENT TO NEW CONSTRUCTION OR AREAS WHERE VARIOUS SYSTEM CONNECTIONS OR EXTENSIONS ARE REQUIRED. IN THESE AREAS, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR DAMAGE CAUSED BY LACK OF SUFFICIENT PROTECTION FROM THE WEATHER AND FROM THE RESULTS OF ALL CONSTRUCTION ACTIVITY INCLUDING BUT NOT LIMITED TO DUST AND WATER.
8. REFER TO SAFETY REQUIREMENTS SPECIFICATION 01 35 26 FOR SAFETY REQUIREMENTS RELATED TO HOT WORK, OPEN FLAMES, WELDING RODS AND TORCHES.
9. DO NOT OVERLOAD THE EXISTING BUILDING STRUCTURE. MAINTAIN STRUCTURAL INTEGRITY OF ALL STRUCTURAL FRAMING MEMBERS AND SYSTEMS AT ALL TIMES.
10. REFER TO GENERAL REQUIREMENTS SPECIFICATION 01 00 00 FOR DISPOSAL AND RETENTION OF MATERIALS AND EQUIPMENT FROM DEMOLITION WORK. REMOVAL OF A PARTICULAR ITEM IS TO INCLUDE ALL RELATED ITEMS. REFER TO DEMOLITION DRAWINGS FOR MORE INFORMATION.
11. FOR ALL REMOVALS, THE GENERAL CONTRACTOR SHALL COORDINATE WITH ALL TRADES.
12. THE CONTRACTOR SHALL PROVIDE TEMPORARY SUPPORT FOR ITEMS NOT DEMOLISHED OR REMOVED AS REQUIRED UNTIL PERMANENT SUPPORT IS PROVIDED IN THE
FINAL CONSTRUCTION.
13. PENETRATIONS THROUGH EXISTING ROOF STRUCTURE FOR NEW WORK MUST BE COORDINATED WITH THE EXISTING STRUCTURE SUCH THAT CRITICAL STRUCTURAL
MEMBERS ARE NOT DAMAGED.
14. FIELD VERIFY SIZE, DIMENSIONS AND COORDINATE LOCATIONS OF PENETRATIONS AFFECTING EXISTING CONSTRUCTION.
15. PENETRATIONS THROUGH EXISTING FIRE RATED CONSTRUCTION MUST BE PROPERLY CLOSED AND FIRE SAFE’D TO ACHIEVE THE REQUIRED FIRE RATING BY THE END
OF CONSTRUCTION OPERATIONS FOR EACH DAY.
16. REMOVE ALL DEBRIS PROPERLY FROM THE SITE. LOAD DEBRIS DIRECTLY ONTO TRUCKS OR INTO DUMPSTERS FOR REMOVAL. DISPOSE OF DEBRIS LEGALLY. DO NOT BURN DEBRIS ON THE SITE. DO NOT ALLOW DEBRIS TO ENTER SEWERS. DO NOT ALLOW PILED DEBRIS TO ENDANGER STRUCTURES, BLOCK EXISTS OR ROADWAYS.
COMBUSTIBLE WASTE WHICH COULD CREATE A FIRE HAZARD SHALL NOT BE PERMITTED TO ACCUMULATE IN OR AROUND THE CONSTRUCTION SITE.
17. ALL WORK SHALL BE DONE IN ACCORDANCE WITH APPLICABLE CODES AND FEDERAL AUTHORITIES, RULES AND REGULATIONS.
18. THESE DOCUMENTS SHOW DESIGN INTENT WITH MINIMUM CONSTRUCTION REQUIREMENTS AND MINIMUM QUALITY OF WORK EXPECTED. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR ALL MEANS, METHODS AND TECHNIQUES FOR CONSTRUCTION AND EXPECTED QUALITY.
19. REFER TO RELEVANT MANUFACTURERS INSTALLATION INSTRUCTIONS WHERE APPLICABLE.
20. UNLESS OTHERWISE NOTED, MATERIALS AND EQUIPMENT SHALL BE INSTALLED PER THE APPLICABLE PROVISIONS OF THESE DOCUMENTS AND
MANUFACTURERS INSTRUCTIONS.
21. ALL MATERIALS UTILIZED ON THIS PROJECT SHALL BE NEW UNLESS OTHERWISE NOTED TO BE SALVAGED AND REFURBISHED. MATERIAL QUALITY
IS EXPECTED TO MEET OR EXCEED APPLICABLE INDUSTRY STANDARDS.
22. WHERE SPECIFIED PRODUCTS OR MANUFACTURER’S BASIS OF DESIGN ARE NOT NOTED, THE CONTRACTOR IS REQUIRED TO NOTIFY THE
CONTRACTING OFFICER REPRESENTATIVE TO OBTAIN A MINIMUM STANDARD OF QUALITY.
23. COORDINATE ALL WORK WITH ALL OTHER DISCIPLINES, INCLUDING, BUT NOT LIMITED TO MECHANICAL, ELECTRICAL, PLUMBING AND SITE/CIVIL DRAWINGS. EXACT SIZE AND LOCATION OF ROOF, WALL AND FLOOR OPENINGS SHOWN ON ARCHITECTURAL DRAWINGS SHALL BE VERIFIED WITH
THE ASSOCIATED CONTRACTORS PRIOR TO CONSTRUCTION.
24. ALL PENETRATIONS THROUGH FIRE RATED CONSTRUCTION MUST BE FIRE SAFE’D TO MEET THE FIRE RATING OF THE STRUCTURE BEING
PENETRATED. TIGHTLY SEAL AND CAULK ALL PENETRATIONS.
25. DO NOT SCALE DRAWINGS, DIMENSIONS SHALL GOVERN.
26. ALL PLAN DIMENSIONS ARE TAKEN TO FINISH FACE OF PARTITION UNLESS SHOWN OR OTHERWISE NOTED.
27. EXPOSED EXTERNAL CORNERS OF BLOCK MASONRY WALLS SHALL BE BULLNOSE.
28. ALL PARTITIONS SHALL EXTEND FROM FLOOR TO UNDERSIDE OF DECK ABOVE UNLESS NOTED OTHERWISE.
29. EXTEND ALL SOUND RATED PARTITIONS TO UNDER SIDE OF DECK. APPLY ACOUSTIC SEALANT IN ALL VOIDS ABOVE TRACK ON BOTH SIDES OF
PARTITION.
30. REFER TO FIRE PROTECTION PLANS FOR LOCATIONS OF FIRE RATED PARTITIONS.
31. ALL CONCEALED WOOD SHALL BE FIRE RETARDANT TREATED.
32. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL EQUIPMENT INSTALLATION AND VERIFYING ALL REQUIRED ROUGH OPENINGS AND ROUGH-IN DIMENSIONS WITH THE EQUIPMENT MANUFACTURER AND CONTRACTING OFFICER REPRESENTATIVE PRIOR TO
CONSTRUCTION.
33. WHERE EXISTING SURFACES ARE TO BE RE-FINISHED OR ARE TO SERVE AS SUBSTRATE FOR THE ATTACHMENT OR APPLICATION OF NEW MATERIALS OR CONSTRUCTION, PREPARE EXISTING SURFACES AS NECESSARY TO RECEIVE THE NEW MATERIALS FOR A LEVEL AND SMOOTH
FINISH.
G E N E R A L N O T E S
34. FIELD VERIFY SIZES AND DIMENSIONS OF ALL EXISTING UTILITIES IMPACTING NEW CONSTRUCTION. DETERMINE EXACT SIZE AND LOCATION OF
PENETRATION WITHIN NEW CONSTRUCTION, TIGHTLY SEAL AND CAULK.
35. UNLESS OTHERWISE NOTED, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING ALL EXISTING SALVAGED STOCK BEFORE ORDERING
NEW MATERIAL.
36. CONTROL JOINTS SHALL BE PROVIDED ABOVE DOORS AT EACH SIDE IN STUD AND GWB PARTITIONS.
37. EXPANSION JOINTS AT ALL FLOORS, CEILINGS AND WALLS THAT ARE EXPOSED TO VIEW SHALL BE COVERED WITH EXPANSION JOINT COVERS
APPROPRIATE FOR FINISHED SURFACES.
38. ALL COLUMNS WITHIN FINISHED SPACES SHALL BE FINISHED WITH SAME MATERIALS SCHEDULED AT WALLS UNLESS OTHERWISE SHOWN OR
DETAILED.
39. PROVIDE ALL WALL AND FLOOR OPENINGS FOR MECHANICAL AND ELECTRICAL ITEMS. ALL OPENINGS LARGER THAN 16 INCHES WIDE IN MASONRY
PARTITIONS SHALL HAVE LINTELS AS SCHEDULED IN STRUCTURAL DRAWINGS.
40. PROVIDE FIRE RATING LABELS ON DOORS AND FRAMES WHERE SCHEDULED.
41. HOLLOW METAL FRAMES SHALL BE ANCHORED TO THE STRUCTURAL FLOOR WITH A MINIMUM OF TWO ANCHOR BOLTS.
42. ALL WALL HUNG CASEWORK, GRAB BARS AND EQUIPMENT ATTACHED TO WALLS SHALL BE ANCHORED TO FIRE RATED WOOD BLOCKING ANCHORED BETWEEN STUDS UNLESS OTHERWISE NOTED. BLOCKING SHALL BE CONTINUOUS AND LOCATED AT BOTTOM AND TOP OF EQUIPMENT.
43. ELEVATION 100'-0" ON THE ARCHITECTURAL DRAWINGS = 195.65' ON THE CIVIL ENGINEERING DRAWINGS
CPT CARPET
CR CRASH RAIL
CS CONCRETE SEALER
CSF CUBIC FEET PER SECOND
CT CERAMIC TILE / COOLING TOWER
CTB CERAMIC TILE BASE
CTF CERAMIC TILE FLOOR
CTR CENTER
CTW CERAMIC TILE WALL
CU CONDENSING UNIT
CUH CABINET UNIT HEATER
CUYD CUBIC YARD
CW COLD WATER
D
D DRAIN / DIFFUSER
DA DENTAL AIR
DBL DOUBLE
DEPR DEPRESSED
DEPT DEPARTMENT
DET DETAIL
DF DRINKING FOUNTAIN
DIA DIAMETER
DIAG DIAGONAL
DIFF DIFFUSER
DIP DUCTILE IRON PIPE
DISC DISCONNECT
DISP DISPENSER
DIST DISTRIBUTION
DK DECK
DL DEAD LOAD
DN DOWN
DO DITTO
DPR DAMPER
DR DOOR
DS DOWNSPOUT
DV DENTAL VACUUM
DWG DRAWING
DWL DOWEL
DWP DOMESTIC WATER PUMP
E
EA EACH / EXHAUST AIR
ECT ENTRY CARPET TILE
EF EACH FACE / EXHAUST FAN
EJ EXPANSION JOINT
EL ELEVATION
ELEC ELECTRIC(AL)
ELEV ELEVATOR
EMBED EMBEDMENT
EMD ESTIMATED MAXIMUM DEMAND
EMT ELECTRICAL METAL TUBING
ENG ENTRANCE GRATING
EP EPOXY PAINT
EQ EQUAL
EQUIP EQUIPMENT
ET EXPANSION TANK / EPOXY TERRAZZO
ETB EPOXY TERRAZZO INTEGRAL COVE BASE
EVAC MEDICAL GAS EVACUATION
EW EACH WAY
EWC ELECTRICAL WATER COOLER
EWH ELECTRICAL WATER HEATER
EXH EXHAUST
EXP EXPOSED
EXPN EXPANSION
EXST EXISTING
EXT EXTERIOR
F
F FIRE MAIN
FA FIRE ALARM
FCU FAN COIL UNIT
FD FLOOR DRAIN / FIRE DAMPER
FD / SD COMBINATION FIRE AND SMOKE DAMPER
FDC FIRE DEPARTMENT CONNECTION
FDN FOUNDATION
FDR FEEDER
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FF&E FURNITURE, FIXTURE, AND EQUIPMENT
FH FIRE HYDRANT
FHC FIRE HOSE CABINET
FIN FINISH
FIX FIXTURE
FL FLOOR
FM FORCE MAIN / FACTORY MUTUAL
FP FIREPROOFING / FIRE PUMP
FPM FEET PER MINUTE
FR FIRE RATED
FRP FIBERGLASS REINFORCED PLASTIC
FS FLOW SWITCH
FT FEET
FTG FOOTING
FVC FIRE VALVE CABINET
G
G GAS / GRILLE
GA GAGE
GALV GALVANIZED
GB GRAB BAR
GBD GRAVITY BACKDRAFT DAMPER
GEN GENERATOR
GFRC GLASS FIBER REINFORCED CONCRETE
GI GALVANIZED IRON
GL GLASS
GLB GLASS BLOCK
GLP GLASS PANEL
GLT GLASS TILE
GP GLAZED PAINT
GPM GALLONS PER MINUTE
GR GRADE
GRV GRAVITY ROOF VENTILATOR
GT GROUT
GWB GYPSUM WALLBOARD
GYP GYPSUM
H
HB HOSE BIBB
HC HEATING COIL
HDNR HARDENER
HDW HARDWARE
HDWD HARDWOOD
HK1E HOOK ONE END
HK2E HOOK TWO ENDS
HM HOLLOW METAL
HNDRL HANDRAIL
HORIZ HORIZONTAL
HP HORSEPOWER
HPT HIGH POINT
HR HOUR
HS HIGH STRENGTH
HT HEIGHT
HTG HEATING
HTR HEATER
HVAC HEATING, VENTILATING AND AIR CONDITIONING
HW HOT WATER
HWC HOT WATER CIRCULATING
HZ HERTZ
I
IA INSTRUMENT AIR
IC INTERCOM
ID INSIDE DIAMETER
IE INVERT ELEVATION
IF INSIDE FACE
IN INCH
INSUL INSULATION
INT INTERIOR
J
JAN JANITOR
JB JUNCTION BOX
JP JOCKEY PUMP
JST JOIST
JT JOINT
K
KC MIL THOUSAND CIRCULAR MILS
KCJ KEYED CONSTRUCTION JOINT
KIT KITCHEN
KPA KILOPASCALS
KS KITCHEN SINK
KV KILOVOLT
KVA KILOVOLT AMPERE
KW KILOWATTS
L
L LITER
LA LABORATORY AIR
LAB LABORATORY
LAM LAMINATE
LAV LAVATORY
LBS POUNDS
LF LINEAR FEET
LIN LINEAR
LINO LINOLEUM
LL LIVE LOAD
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LMU LIGHTWEIGHT MASONRY UNITS
LONG LONGITUDINAL
LPM LITERS PER MINUTE
LT LIGHT
LT WT LIGHT WEIGHT
LTG LIGHTING
LV LABORATORY VACUUM
LVL LEVEL
LVT LUXURY VINYL TILE
M
M METER
M2 SQUARE METER
M3 CUBIC METER
MA MEDICAL AIR
MAINT MAINTENANCE
MAR MARBLE
MAS MASONRY
MAT MATERIAL
MAX MAXIMUM
MB METAL BASE
MBH 1000 BTUH
MDO MEDIUM DENSITY OVERLAY
MECH MECHANICAL
MET METAL
MFR MANUFACTURER
MG MOTOR GENERATOR / MEDICAL GAS
MH MANHOLE
MIN MINIMUM
MLO MAIN LUGS ONLY
MM MILLIMETER
MO MASONRY OPENING
MP METAL PANEL
MT METAL TRANSITION
MTD MOUNTED
MTG MOUNTING
MULL MULLION
MV MEDICAL VACUUM
N
N NITROGEN
N2O NITROUS OXIDE
NEC NATIONAL ELECTRICAL CODE
NFPA NATIONAL FIRE PROTECTION
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NPE NONYLPHENOL ETHOXYLATES
NTS NOT TO SCALE
O
O/S OFFSET
OA OUTSIDE AIR
OBD OPPOSED BLADE DAMPER
OC ON CENTER
OD OUTSIDE DIAMETER
OF OUTSIDE FACE
OPNG OPENING
OPP OPPOSITE
OX OXYGEN
OZ OUNCE
P
P PAINT / PUMP / PENDANT
PA PASCAL
PART PARTITION
PAVT PAVEMENT
PC POINT OF CURVATURE / PRIVACY CURTAIN
PCF POUNDS PER CUBIC FOOT
PED PEDESTAL
PERP PERPENDICULAR
PHC PREHEAT COIL
PHVAC PLUMBING, HEATING, VENTILATING AND AIR
CONDITIONING
PI POINT OF INTERSECTION
PIV POST INDICATOR VALVE
PKG PARKING
PL PLASTIC LAMINATE / PROPERTY LINE / PLATE
PLAS PLASTER
PLBG PLUMBING
PLF POUNDS PER LINEAR FOOT
PLYWD PLYWOOD
PNL PANEL
POL CONC POLISHED CONCRETE
PR PAIR
PRF POURED RESINOUS FLOORING
PROJ PROJECTION
PRV PRESSURE REGULATING VALVE
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT POINT OF TANGENCY
PTB PORCELAIN TILE BASE
PTF PORCELAIN TILE FLOOR
PTVC POINT OF VERTICAL CURVATURE
PTW PORCELAIN TILE WALL
PVC POLYVINYL CHLORIDE
PVI POINT OF VERTICAL INTERSECTION
PVT POINT OF VERTICAL TANGENCY
Q
QTB QUARRY TILE BASE
QTF QUARRY TILE FLOOR
QZP QUARTZ POLYMER
R
R RADIUS / REGISTER
RA RETURN AIR
RAF RAISED ACCESS FLOORING
RB RESILIENT BASE
RCP REINFORCED CONCRETE PIPE
RD ROOF DRAIN
REF REFERENCE
REFL REFLECTED
REG REGISTER
REINF REINFORCED
REQD REQUIRED
REV REVERSE / REVISION
RF RETURN FAN
RGS RIGID GALVANIZED STEEL
RH ROOF HOOD / RELATIVE HUMIDITY / REHEAT
RHC REHEAT COIL
RM ROOM
RO ROUGH OPENING
ROW RIGHT OF WAY
RS RESILIENT SHEET
RT RESILIENT TILE
S
S STAIR / STAIN / SURFACE / SANITARY
SA SUPPLY AIR / SOUND ATTENUATOR
SAN SANITARY
SCH SCHEDULE
SD SMOKE DAMPER / SUB DRAIN / STORM SEWER
SECT SECTION
SF SUPPLY FAN
SHT SHEET
SIM SIMILAR
SOG SLAB-ON-GRADE
SP SUMP PUMP
SPEC SPECIFICATIONS
SQ SQUARE
SS SERVICE SINK / SANITARY SEWER
SSM SOLID SURFACE MATERIAL
SSO STORM SEWER OVERFLOW
SST STAIR TREAD
SSTL STAINLESS STEEL
STA STATION
STD STANDARD
STE STANDARD TAPERED END
STIFF STIFFENER
STIR STIRRUP
STL STEEL
STOR STORAGE
STR STRUCTURAL
SUSP SUSPENDED
SW SWITCH
SWGR SWITCHGEAR
SYM SYMMETRICAL
T
T TREAD
T&B TOP AND BOTTOM
T&G TONGUE AND GROOVE
TC TOP OF CURB
TE TOP ELEVATION
TEL TELEPHONE
TEMP TEMPERATURE
TERR TERRAZZO
TLT TOILET
TOPO TOPOGRAPHY
TOS TOP OF STEEL
TOW TOP OF WALL
TP TOP OF PAVEMENT
TRANS TRANSVERSE
TS TRANSITION STRIP
TYP TYPICAL
U
UC UNDERCUT
UG UNDERGROUND
UH UNIT HEATER
UNO UNLESS NOTED OTHERWISE
UR URINAL
UV UNIT VENTILATOR
V
V VOLT
VAV VARIABLE AIR VOLUME
VC VERTICAL CURVE
VCP VITRIFIED CLAY PIPE
VCT VINYL COMPOSITION TILE
VERT VERTICAL
VEST VESTIBULE
VFD VARIABLE FREQUENCY DRIVE
VTR VENT THROUGH ROOF
VWC VINYL WALL COVERING
W
W WATT / WATER
W/ WITH
W/O WITHOUT
WAGD WASTE ANESTHESIA GAS DISPOSAL
WC WATER CLOSET / WALL COVERING
WD WOOD
WDB WOOD BASE
WDF WOOD FLOOR
WDP WOOD PANEL
WDW WINDOW
WDWF WINDOW FILM
WGD WALL GUARD
WH WATER HEATER / WALL HYDRANT
WP WEATHERPROOF
WPFG WATERPROOFING
WS WATER STOP
WT WEIGHT / WINDOW TREATMENT
WWF WELDED WIRE FABRIC
X
XFMR TRANSFORMER
Y
YD YARD
YH YARD HYDRANT
No. Revisions: Date:
REV 0 07/24/2023
CODE SUMMARY
DESCRIPTION OF BUILDING:
LOCATED AT 2300 RAMSEY STREET, FAYETTEVILLE, NC, THE FAYETTEVILLE VETERANS AFFAIRS MEDICAL CENTER (VAMC) IS A GENERAL MEDICINE, SURGERY, AND MENTAL HEALTH FACILITY.
THE SYSTEM IS IN NEED OF CONSOLIDATED EXECUTIVE LEADERSHIP OFFICE SPACE CURRENTLY
LOCATED THROUGH THE MAIN HOSPITAL BUILDING.
HISTORIC NURSES QUARTERS BUILDING 4 HAS BEEN SELECTED TO HOUSE THE LEADERSHIP
OFFICE SPACE CONSOLIDATION AND WILL UNDERGO FULL REMODEL OF THE BASEMENT, FIRST
FLOOR AND SECOND FLOOR OF THE EXISTING STRUCTURE.
BUILDING 4 IS A CONTRIBUTING BUILDING OF THE FAYETTEVILLE (NC) VETERANS
ADMINISTRATION HOSPITAL HISTORIC DISTRICT AS CLASSIFIED BY THE NATIONAL PARK SERVICE / NATIONAL REGISTER OF HISTORIC PLACES. THE BUILDING WAS DESIGNED AND CONSTRUCTED IN 1939 IN THE COLONIAL REVIVAL STYLE AND FEATURES CLASSICAL REVIVAL ARCHITECTURAL
DECORATIVE DETAILS SUCH AS A GENERALLY SYMMETRICAL FACADE, A CORNICE WITH
DENTILS, A STONE WATER TABLE, AND BRICK QUOINS. A BRICK PORTICO IS ATTACHED TO THE
NORTH AND SOUTH OF THE BUILDING AND HAS FIVE ARCHED BREEZEWAY OPENINGS THAT
WERE ENCLOSED WITH NEW WALLS IN 1975.
BUILDING 4 IS A 2 STORY ABOVE GRADE AND 1 STORY BELOW GRADE, CONCRETE-FRAMED
BUILDING WITH MASONRY EXTERIOR WALL. IT HAS GONE THROUGH MODERNIZATION AND
RENOVATION OVER THE YEARS AND IS BEING USED AS BUSINESS OFFICES.
PROPOSED RENOVATION IS TO RENOVATE BUILDING 4 FOR THE EXECUTIVE TEAM'S OFFICE USE (BUSINESS). IT WILL BE GUTTED, INCLUDING ALL UTILITY SYSTEMS, STAIRWELLS. ITS EXISTING
BUILDING ENVELOPE WILL GO THROUGH MINOR ADJUSTMENT TO COMPLY WITH CURRENT
PHYSICAL SECURITY AND RESILIENCY DESIGN MANUAL AND ACCESSIBILITY.
A NEW ISOLATED SCREENING VESTIBULE BUILDING WILL BE LOCATED ON THE EAST OF THE
BUILDING. THE SCREENING VESTIBULE BUILDING IS A 2 STORY ABOVE GRADE AND 1 BASEMENT
LEVEL STEEL FRAMED STRUCTURE. IT HOUSES A NEW STAIR, A HYDRAULIC IN GROUND
ELEVATOR, SCREENING LOBBY, AND ELEVATOR MACHINE ROOM. THE SCREEN VESTIBULE
BUILDING WILL SERVE AS BUILDING 4'S PRIMARY ENTRANCE FOR ITS OCCUPANTS.
BUILDINGS ORIGINAL CONSTRUCTED USE
BUILDING 4 NURSES QUARTERS: 1939
AUTHORITY HAVING JURISDICTION:
U.S. DEPARTMENT OF VETERANS AFFAIRS
APPLICABLE CODES & STANDARDS
• NFPA 101 LIFE SAFETY CODE 2021
• NFPA NATIONAL FIRE CODES, WITH EXCEPTION OF NFPA 5000 AND NFPA 900
• OCCUPATIONAL , SAFETY, AND HEALTH ADMINISTRATION (OSHA) STANDARDS
• VA SEISMIC DESIGN REQUIREMENTS, H-18-8
• NFPA 70, NATIONAL ELECTRIC CODE; 2020
• NFPA 72, NATIONAL FIRE ALARM AND SIGNALING CODE; 2019
• ASHRAE 90.1, ENERGY STANDARD; 2013 AND 2016
• ASME A17.1, ELEVATOR CODE; 2013
• ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING VA
SUPPLEMENT, BARRIER FREE DESIGN GUIDE (PG-18-13), AMERICAN DISABILITY ACT 2010
• VA SUSTAINABLE DESIGN MANUAL
• PHYSICAL SECURITY RESILIENCY DESIGN MANUAL 2020
• VA SEISMIC DESIGN REQUIREMENT
PROJECT CLASSIFICATION
BUILDING 4: LEVEL 3 ALTERATION, HISTORIC PROPERTY
SCREENING VESTIBULE - ADDITION
BUILDING HEIGHT & AREA LIMITATIONS - FULLY SPRINKLERED
CONSTRUCTION TYPE III (200)
OCCUPANCY: BUSINESS
ALLOWABLE STORIES = 5, ACTUAL = 2
ALLOWABLE AREA = 19,000, ACTUAL = 15,527 SF
OCCUPANCIES ARE DEFINED ON THE FOLLOWING FLOORS:
BASEMENT - BUSINESS (B)
LEVEL 1 - BUSINESS (B)
LEVEL 2 - BUSINESS (B)
CONSTRUCTION TYPE
EXISTING: TYPE III (200)
PROPOSED: TYPE III (200)
OCCUPANCY CLASSIFICATION
EXISTING OCCUPANCY: BUSINESS, GROUP B
PROPOSED OCCUPANCY: BUSINESS, GROUP B
FIRE-RESISTANCE RATING REQUIREMENTS FOR BUILDING ELEMENTS (NFPA 220 TABLE 4.1.1)
EXTERIOR BEARING WALLS 2-HOUR RATING
INTERIOR BEARING WALLS 0-HOUR RATING
COLUMNS 0-HOUR RATING
BEAMS, GIRDERS, TRUSSES, AND ARCHES 0 HOUR RATING
FLOOR-CEILING CONTRUCTION 0-HOUR RATING
ROOF-CEILING CONSTRUCTION 0-HOUR RATING
INTERIOR BEARING WALLS 0-HOUR RATING
EXTERIOR NONBEARING WALLS 0-HOUR RATING
RISK CATEGORY
EXISTING: 2
PROPOSED: 4 PER VA SEISMIC DESIGN REQUIREMENT, MISSION CRITICAL FACILITY
VERTICAL OPENINGS
FLOOR OPENINGS TO COMPLY WITH SECTION 8.6.5
ENCLOSURES CONNECTING FOUR OR MORE STORIES IN NEW CONSTRUCTION SHALL BE 2-
HOUR FIRE BARRIERS. - N/A
OTHER ENCLOSURES IN NEW CONSTRUCTION SHALL BE 1-HOUR FIRE BARRIERS
INTERIOR FINISHES
INTERIOR EXIT STAIRWAYS, EXIT RAMPS, AND EXIT PASSAGEWAYS
B (BUSINESS) = CLASS B
CORRIDORS
B (BUSINESS) = CLASS C
ROOMS AND ENCLOSED SPACES
B (BUSINESS) = CLASS C
MEANS OF EGRESS
MINIMUM NUMBER OF EXITS
ABOVE GROUND LEVELS: 2 REQUIRED
ABOVE GROUND LEVELS: 2 PROVIDED
MINIMUM WIDTH OF DOOR CLEARANCE
32" REQUIRED
32" MINIMUM PROVIDED
MAXIMUM COMMON PATH OF EGRESS TRAVEL DISTANCE
B (BUSINESS) = 100'
EXIT ACCESS TRAVEL DISTANCE
B (BUSINESS) = 300' MAX
DEAD END CORRIDORS
B (BUSINESS) = 50' MAX
MINIMUM CORRIDOR WIDTH
ALL LEVELS: 44" REQUIRED
44" MINIMUM PROVIDED
CORRIDOR FIRE RESISTANCE RATING
B (BUSINESS) = 0-HOURS
FIRE PROTECTION SYSTEMS
FULLY SPRINKLERED IN ACCORDANCE WITH NFPA 13
AUTOMATIC WET STANDPIPES LOCATED IN EGRESS STAIRWELLS
FIRE ALARM SYSTEM WITH VOICE EVACUATION THROUGHOUT IN ACCORDANCE WITH NFPA 72
ELEVATOR LOBBIES ARE NOT REQUIRED ON AND ABOVE GROUND FLOORS DUE TO FULLY
SPRINKLERED BUILDING.
PORTABLE FIRE EXTINGUISHERS IN COMPLIANCE WITH NFPA 10 FOR CLASS A
PROVIDE ONE EXTINGUISHER INSTALLED PER FLOOR
ENERGY CODE COMPLIANCE
ENERGY CODE COMPLIANCE IS IN ACCORDANCE WITH ASHRAE 90.1, PER THE 2018
INTERNATIONAL ENERGY CONSERVATION CODE THE COMPLIANCE PATH IS ENVELOPE TRADE
OFF (USING ENERGY MODELING)
CONTRACTOR IS REQUIRED TO PROVIDE CONTINUOUS INSULATION AT ENTIRE
BUILDING ENCLOSURE IN COMPLIANCE WITH ENERGY CODE.
OCCUPANCY LOAD CALCULATION
LEVEL
LEVEL B
LEVEL 1
LEVEL 2
TOTAL
4,784 SF
5,412 SF
5,331 SF
15,527 SF
B (BUSINESS) 32 PERSONS
B (BUSINESS)
B (BUSINESS)
36 PERSONS
36 PERSONS
104 PERSONS
150 SF / PERSONS
150 SF / PERSONS
150 SF / PERSONS
PLUMBING FIXTURE ANALYSIS
TOTAL # OCCUPANCY
104 PERSONS
1/25 PERSON FOR FIRST 50
& 1/50 REMAINDER
4 REQUIRED 2 REQUIRED
9 PROVIDED
WATER CLOSETS
7 PROVIDED
1/40 PERSON FOR FIRST 80
& 1/80 REMAINDER
LAVATORY
1/100 PERSONS
DRINKING FOUNTAIN
2 REQUIRED
4 POVIDED
1 PER BUILDING
SERVICE SINKS
1 REQUIRED
1 POVIDED
AREA OCCUPANCY TYPE OCCUPANT LOAD FACTOR OCCUPANT #
GROSS BUILDING AREA TABLE
LEVEL
LEVEL B
LEVEL 1
LEVEL 2
TOTAL
3,866
4,494
4,407
12,767
4,784
5,412
5,331
15,527
EXISTING (SQFT) PROPOSED (SQFT) TOTAL
2,760
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /F a y e tt e v ill e N
C V
A
B ld g
R e n o v a ti o n /F
F E
F a y e tt e v ill e
R e n o v a te
B
A rc h rv t
/2
/2
:5
:2
P
M
GI006
BUILDING CODE SUMMARY
07/24/2023 SS KT
RENOVATE HISTORIC BUILDING 4 565-20-101
2300 RAMSEY STREET, FAYETTEVILLE, NC 28301
ISSUED FOR
CONSTRUCTION 4
FAYETTEVILLE
VA MEDICAL
CENTER Approved: FAYETTEVILLE VA MEDICAL CENTER
No. Revisions: Date:
REV 0 07/24/2023
File details come from the government source that posted it. Updated .