Proposal Item III Cost Breakdown.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Z2AA - Renovate Historic Building 4 Federal contract opportunity
- Solicitation number
- 36C24624R0030
About this file
This is a cost breakdown spreadsheet template for Proposal Item III related to the renovation of Historic Building 4 at the VA facility in Fayetteville, NC (Project #565-20-101). The spreadsheet is structured to capture detailed cost estimates across 21 construction divisions including General Requirements, Existing Conditions, Concrete, Masonry, Metals, Wood and Plastic, Thermal & Moisture Protection, Doors and Windows, Finishes, Specialties, Equipment, Furnishings, Special Construction, Conveying Equipment, Fire Suppression, Plumbing, HVAC, Electrical, Communications, Electronic Safety & Security, Earthwork, Exterior Improvements, and Utilities.
The template requires bidders to input labor and material costs for each division separately, with automatic calculations for division totals. The spreadsheet also includes fields for overhead percentage, profit percentage, and bond percentage, which are multiplied against the division subtotals to calculate the final proposal cost. All formulas are built into the template to automatically calculate totals and subtotals based on the contractor's inputs.
View the file
Other files for this federal contract opportunity
Show all 50
Z2AA - Renovate Historic Building 4 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer
Proposal Item III Cost Breakdown
Project Number: 565-20-101 Edward L Roy: VA assigned project #
| Date: | |
| Project Title | Renovate Historic Bldg. 4 |
Edward L Roy: VA assigned Project Title
| Project Location | Fayetteville, NC | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | ||
| Division 2 | Existing Conditions | - 0 | ||
| Division 3 | Concrete | - 0 | ||
| Division 4 | Masonry | - 0 | ||
| Division 5 | Metals | - 0 | ||
| Division 6 | Wood and Plastic | - 0 | ||
| Division 7 | Thermal & Moisture Protect | - 0 | ||
| Division 8 | Doors and Windows | - 0 | ||
| Division 9 | Finishes | - 0 | ||
| Division 10 | Specialties | - 0 | ||
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | ||
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | ||
| Division 22 | Plumbing | - 0 | ||
| Division 23 | HVAC | - 0 | ||
| Division 26 | Electrical | - 0 | ||
| Division 27 | Communications | - 0 | ||
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | ||
| Division 32 | Exterior Improvements | - 0 | ||
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| ERROR:#VALUE! | ||
| Profit % | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | ERROR:#VALUE! | |
| Bond % |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| ERROR:#VALUE! | ||
| Overhead/Profit Subtotals : | ERROR:#VALUE! |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Proposal Item Cost $ - 0 $ - 0 ERROR:#VALUE!
File details come from the government source that posted it. Updated .