238200 - CONVECTION HEATING AND COOLING UNITS.pdf

PDF 27 KB Posted

Attached to
Z2AA - Renovate Historic Building 4 Federal contract opportunity
Solicitation number
36C24624R0030
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This is a technical specification document (Section 23 82 00) detailing requirements for convection heating and cooling units as part of the renovation of Historic Building 4 at a VA facility. The specification covers unit heaters and wall-mounted unit heaters, including their construction, components, and installation requirements.

The document outlines detailed specifications for horizontal and vertical discharge unit heaters with steel sheet casings, propeller-type fans, and electric heating elements using nickel chromium alloy resistance wire. Wall-mounted units must include recessed wall boxes, ribbed steel front covers, and finned-tube heating elements with integral controls. Installation requirements include proper support, cross-bracing, and coordination with commissioning agents. The contractor must provide manufacturer training, operational testing, and commissioning documentation. All units must comply with relevant ANSI/AHRI standards, NFPA requirements, and UL listings.

View the file

Other files for this federal contract opportunity

Other files attached to Z2AA - Renovate Historic Building 4, newest first.
File Type Posted
36C24625C0027_1 Award Notice.docx DOCX document
230923 Direct-Digital Control System Connect to Existing N4.pdf PDF
1_a G - Renovate Building 4 IFC page 1.pdf PDF
1_b H - Renovate Building 4 IFC pages 12-14.pdf PDF
1_a G - Renovate Building 4 IFC pages 2-3.pdf PDF
1_a G - Renovate Building 4 IFC pages 4-6.pdf PDF
1_a G - Renovate Building 4 IFC pages 7-10.pdf PDF
2_C - L and S - Renovate Building 4 IFC pages 15-35.pdf PDF
4_FP and P - Renovate Building 4 IFC pages 86-109.pdf PDF
36C24624R0030 0005.docx DOCX document
3_Arch - Renovate Building 4 IFC pages 36-85.pdf PDF
5_Mech - Renovate Building 4 IFC pages 110-128.pdf PDF
6_Elec - Renovate Building 4 IFC pages 129-155.pdf PDF
Drawings.zip ZIP file
36C24624R0030 0004.docx DOCX document
Proposal Item V Cost Breakdown.xlsx XLSX spreadsheet
Asbestos - Lead Paint Survey 12-31-2020.pdf PDF
Geotech Report_Fayetteville Bldg 4 Renovation.pdf PDF
230593 - TESTING ADJUSTING AND BALANCING FOR HVAC.pdf PDF
238129 - VARIABLE REFRIGERANT FLOW HVAC SYSTEMS.pdf PDF
230923 - DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC.pdf PDF
238143 - AIR SOURCE UNITARY HEAT PUMPS.pdf PDF
230800 - COMMISSIONING OF HVAC SYSTEMS.pdf PDF
INSTRUCTIONS CONDITIONS AND OTHER STATEMENTS TO BIDDERS-OFFERORS .docx DOCX document
Proposal Item I Cost Breakdown.xlsx XLSX spreadsheet
Fayetteville - Temp Fence.pdf PDF
230541 - NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.pdf PDF
230512 - GENERAL MOTOR REQUIREMENTS FOR HAVAC AND STEAM GENERATION EQUIPMENT.pdf PDF
014529 - TESTING LABORATORY SERVICES.pdf PDF
234000 - HVAC AIR CLEANING DEVICES.pdf PDF
232300 - REFRIGERANT PIPING.pdf PDF
36C24624R0030 0003.docx DOCX document
Proposal Item II Cost Breakdown.xlsx XLSX spreadsheet
Proposal Item III Cost Breakdown.xlsx XLSX spreadsheet
Proposal Item IV Cost Breakdown.xlsx XLSX spreadsheet
PL902 - PLUMBING DOMESTIC WATER ISOMETRICS.pdf PDF
232113 - Hydronic Piping.pdf PDF
233400 - HVAC FANS.pdf PDF
238216 - AIR COILS.pdf PDF
36C24624R0030 0002.docx DOCX document
Statement of Work - Renovate Historic Building 4.pdf PDF
Specifications - Renovate Building 4 Issued For Construction.pdf PDF
Wage Determination.pdf PDF
STRUCTRAL DRAWING SET.pdf PDF
PLUMBING DRAWING SET.pdf PDF
MECHANICAL DRAWING SET.pdf PDF
LANDSCAPE DRAWING SET.pdf PDF
FIRE PROTECTION DRAWING SET.pdf PDF
ELECTRICAL DRAWING SET.pdf PDF
CIVIL DRAWING SET.pdf PDF
Show all 50

Z2AA - Renovate Historic Building 4 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovation of Historical Building 4

Project #565 20 101

03-01-20

CONVECTION HEATING AND COOLING UNITS

23 82 00 - 1

SECTION 23 82 00

CONVECTION HEATING AND COOLING UNITS

PART 1 - GENERAL

1.1 DESCRIPTION

This section specifies unit heaters.

1.2 RELATED WORK

A. Section 01 00 00, GENERAL REQUIREMENTS.

B. Section 01 09 00, GENERAL COMMISSIONING REQUIREMENTS

C. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES

D. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL

COMPONENTS: Seismic restraints for equipment.

E. Section 23 05 11, COMMON WORK RESULTS FOR HVAC: General mechanical requirements and items, which are common to more than one section of

Division 23.

F. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and

EQUIPMENT: Noise requirements.

G. Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC: Flow rates adjusting and balancing.

H. Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS: Requirements for commissioning, systems readiness checklists, and training.

I. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC: Valve operators.

J. Section 23 31 00, HVAC DUCTS and CASINGS: Ducts and flexible connectors.

K. Section 23 82 16, AIR COILS: Additional coil requirements.

1.3 QUALITY ASSURANCE

Refer to Paragraph, QUALITY ASSURANCE, in Section 23 05 11, COMMON WORK

RESULTS FOR HVAC. Provide guarantee in accordance with FAR clause

52.246-21

1.4 SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, and SAMPLES.

B. Manufacturer's Literature and Data:

1. Unit heaters.

2. Wall Mounted Unit Heaters.

C. Certificates:

1. Compliance with Article, QUALITY ASSURANCE.

2. Compliance with specified standards.

03-01-20

CONVECTION HEATING AND COOLING UNITS

23 82 00 - 2

D. Operation and Maintenance Manuals: Submit in accordance with Article, INSTRUCTIONS, in Section 01 00 00, GENERAL REQUIREMENTS.

E. Completed System Readiness Checklists provided by the Commissioning

Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS.

1.5 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

B. American National Standards Institute / Air Conditioning, Heating and

Refrigeration Institute (ANSI/AHRI):

440-2019................Performance Rating of Room Fan Coils

National Fire Protection Association (NFPA):

90A-2018................Standard for the Installation of Air

Conditioning and Ventilating Systems

70-2017.................National Electrical Code

C. Underwriters Laboratories, Inc. (UL):

181-2013................Standard for Factory-Made Air Ducts and Air

Connectors

1995-2015...............Heating and Cooling Equipment

PART 2 - PRODUCTS

2.1 UNIT HEATERS

A. General: Horizontal or vertical discharge type for electric heating medium, as indicated.

B. Casing: Steel sheet, phosphatized to resist rust and finished in baked enamel. Provide hanger supports.

C. Fan: Propeller type, direct driven by manufacturer's standard electric motor. Provide resilient mounting. Provide fan guard for horizontal discharge units.

D. Discharge Air Control:

1. Horizontal discharge: Horizontal, adjustable louvers.

2. Vertical discharge: Radial louver diffuser.

E. Electric Units: UL listed, factory wired to terminal strips for field connection of power and control wiring.

1. Heating elements: Nickel chromium alloy resistance wire embedded in a magnesium oxide insulating refractory and sealed in corrosion

03-01-20

CONVECTION HEATING AND COOLING UNITS

23 82 00 - 3 resisting metallic sheath with fins. Three phase heaters shall have balanced phases.

2. Thermal cutout: Manual reset type, which disconnects elements, and motor in the event normal operating temperatures are exceeded.

3. Magnetic contactor: Factory installed with low voltage relay for remote pilot duty thermostat operation.

F. Controls: Provide field installed remote wall mounted line voltage electric space thermostats to control the unit fan.

2.2 WALL-MOUNTED UNIT HEATERS

A. General: Electric heat, fan driven, thermostatic control, UL listed.

B. Enclosure:

1. Wall box: Not less than 1.3 mm (l8 gage) steel, recessed type.

2. Ribbed 1.6 mm (l6 gage) steel front cover.

3. Closely spaced discharge louvers.

4. Concealed screws for locking trim frame to front cover.

5. Finished in baked enamel of manufacturer’s standard color with satin finish anodized aluminum trim frame.

C. Heating Elements: Steel sheath enclosed finned-tube type.

D. Integral Controls:

l. Two-pole terminal block.

2. Built-in fan delay switch.

3. Automatic reset line voltage internal thermal overheats protection.

4. Built-in thermostat comfort control with adjustment range between -1 to 32 degree C (30-90 degrees F), and manually set "No Heat" position; tamper resistant adjustment by inserting screwdriver through front cover louvers.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Work shall be installed as shown and according to the manufacturer’s diagrams and recommendations.

B. Handle and install units in accordance with manufacturer's written instructions.

C. Support units rigidly so they always remain stationary. Cross-bracing or other means of stiffening shall be provided as necessary. Method of support shall be such that distortion and malfunction of units cannot occur.

D. Install fiberglass blanket insulation with a minimum R value of 8 above hydronic radiant panels.

03-01-20

CONVECTION HEATING AND COOLING UNITS

23 82 00 - 4

3.2 OPERATIONAL TEST

Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.

3.3 STARTUP AND TESTING

A. The Commissioning Agent will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and Commissioning Agent. Provide a minimum of 7 calendar days prior notice.

3.4 COMMISSIONING

A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the

System Readiness Checklist provided by the Commissioning Agent.

B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00 –

COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.

3.5 DEMONSTRATION AND TRAINING

A. Provide services of manufacturer’s technical representative for four hours to instruct VA personnel in operation and maintenance of units.

B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS.

- - - E N D - - -