230800 - COMMISSIONING OF HVAC SYSTEMS.pdf

PDF 28 KB Posted

Attached to
Z2AA - Renovate Historic Building 4 Federal contract opportunity
Solicitation number
36C24624R0030
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This is a technical specification section (23 08 00) detailing the commissioning requirements for HVAC systems as part of the renovation of Historical Building 4 for the Department of Veterans Affairs. The document outlines the specific requirements for commissioning HVAC systems, including coordination with related work sections, documentation procedures, and testing protocols.

The specification requires the contractor to complete Pre-Functional Checklists, coordinate with the Commissioning Agent (CxA), conduct systems functional performance testing, and provide training for VA personnel. Key requirements include providing 7 calendar days notice for testing, completing contractor tests prior to Systems Functional Performance Testing, and submitting training agendas and trainer resumes. The contractor must coordinate with the CxA throughout construction for inspections and testing verification, with specific emphasis on documentation accuracy and compliance with industry standards from organizations including ASHRAE, AABC, NEBB, and SMACNA.

View the file

Other files for this federal contract opportunity

Other files attached to Z2AA - Renovate Historic Building 4, newest first.
File Type Posted
36C24625C0027_1 Award Notice.docx DOCX document
230923 Direct-Digital Control System Connect to Existing N4.pdf PDF
36C24624R0030 0006.pdf PDF
1_b H - Renovate Building 4 IFC pages 12-14.pdf PDF
1_a G - Renovate Building 4 IFC page 1.pdf PDF
Specification Section 00 01 15 - LIST OF DRAWING SHEETS 01 21 25.pdf PDF
2_C - L and S - Renovate Building 4 IFC pages 15-35.pdf PDF
4_FP and P - Renovate Building 4 IFC pages 86-109.pdf PDF
36C24624R0030 0005.docx DOCX document
INSTRUCTIONS CONDITIONS AND OTHER STATEMENTS TO BIDDERS-OFFERORS .docx DOCX document
Proposal Item I Cost Breakdown.xlsx XLSX spreadsheet
Fayetteville - Temp Fence.pdf PDF
230541 - NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT.pdf PDF
230512 - GENERAL MOTOR REQUIREMENTS FOR HAVAC AND STEAM GENERATION EQUIPMENT.pdf PDF
014529 - TESTING LABORATORY SERVICES.pdf PDF
234000 - HVAC AIR CLEANING DEVICES.pdf PDF
232300 - REFRIGERANT PIPING.pdf PDF
Statement of Proposal Items - 0003.docx DOCX document
Building 4 and 16 LBP Results.pdf PDF
Asbestos Reinspection Report - August 2019.pdf PDF
230711 - HVAC AND BOILER PLANT INSULATION.pdf PDF
230511 - COMMON WORK RESULTS FOR HVAC.pdf PDF
233100 - HVAC DUCTS AND CASINGS.pdf PDF
237200 - AIR TO AIR ENERGY RECOVERY EQUIPMENT.pdf PDF
233700 - AIR OUTLETS AND INLETS.pdf PDF
Proposal Item V Cost Breakdown.xlsx XLSX spreadsheet
Asbestos - Lead Paint Survey 12-31-2020.pdf PDF
Geotech Report_Fayetteville Bldg 4 Renovation.pdf PDF
230593 - TESTING ADJUSTING AND BALANCING FOR HVAC.pdf PDF
238129 - VARIABLE REFRIGERANT FLOW HVAC SYSTEMS.pdf PDF
230923 - DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC.pdf PDF
238143 - AIR SOURCE UNITARY HEAT PUMPS.pdf PDF
36C24624R0030 0003.docx DOCX document
Proposal Item II Cost Breakdown.xlsx XLSX spreadsheet
Proposal Item III Cost Breakdown.xlsx XLSX spreadsheet
36C24624R0030 0002.docx DOCX document
11-19-2024 Site Visit Attendance.pdf PDF
36C24624R0030 0001.docx DOCX document
Statement of Work - Renovate Historic Building 4.pdf PDF
STRUCTRAL DRAWING SET.pdf PDF
ARCHITECTURAL DRAWING SET.pdf PDF
36C24624R0030_1.docx DOCX document
Specifications - Renovate Building 4 Issued For Construction.pdf PDF
Wage Determination.pdf PDF
PLUMBING DRAWING SET.pdf PDF
MECHANICAL DRAWING SET.pdf PDF
LANDSCAPE DRAWING SET.pdf PDF
FIRE PROTECTION DRAWING SET.pdf PDF
ELECTRICAL DRAWING SET.pdf PDF
CIVIL DRAWING SET.pdf PDF
Show all 50

Z2AA - Renovate Historic Building 4 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovation of Historical Building 4

Project #565 20 101

02-01-20

COMMISSIONING OF HVAC SYSTEMS

23 08 00 - 1

SECTION 23 08 00

COMMISSIONING OF HVAC SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 23.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A

Commissioning Agent (CxA) will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 33 00 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

C. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

D. Section 23 05 41 NOISE AND VIBRATION CONTROL for HVAC PIPING AND

EQUIPMENT.

E. Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

F. Section 23 09 23 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.

1.3 SUMMARY

A. This Section includes requirements for commissioning the HVAC systems of the related subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in Division 23 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00

GENERAL COMMISSIONING REQUIREMENTS and of Division 23, is required in cooperation with the VA and the Commissioning Agent.

02-01-20

COMMISSIONING OF HVAC SYSTEMS

23 08 00 - 2

B. The Facility HVAC systems commissioning will include the systems listed in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the

Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP

DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

1.7 APPLICABLE PUBLICATIONS

A. The following publications form a part of this specification to the extent indicated by the reference thereto. In text the publications are referenced to by the acronym of the organization.

B. Department of Veterans Affairs (VA):

PG 18-10 2007...........Mission Critical Facilities - DRAFT

PG 18-10 2007...........Life-Safety Protected Facilities - DRAFT

C. American Society of Heating, Refrigerating and Air Conditioning

Engineers, Inc. (ASHRAE):

HANDBOOK 2019...........HVAC Applications ASHRAE Handbook, Chapter 39, Testing, Adjusting, and Balancing, Chapter 44, HVAC Commissioning and Chapter 49, Sound and

Vibration Control

HANDBOOK 2017...........HVAC Fundamentals ASHRAE Handbook, Chapter 8, Sound and Vibration

D. Associated Air Balance Council (AABC):

7th Edition 2016........AABC National Standards for Total System

Balance

E. National Environmental Balancing Bureau (NEBB):

9th Edition 2019........Procedural Standards for Testing, Adjusting, Balancing of Environmental Systems

3rd Edition 2015 .......Procedural Standards for the Measurement of

Sound and Vibration

2rd Edition 2019 ... Standard for Whole Building Technical

Commissioning of New Construction

02-01-20

COMMISSIONING OF HVAC SYSTEMS

23 08 00 - 3

F. Sheet Metal and Air Conditioning Contractors National Association

(SMACNA):

006-2006................HVAC Duct Construction Standard – Metal and

Flexible Duct

3rd Edition 2005 ... HVAC Systems Testing, Adjusting and Balancing

PART 2 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

Commissioning of HVAC systems will require inspection of individual elements of the HVAC systems construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and the Commissioning plan to schedule HVAC systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The

Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. Refer to Sections 23 05 41 NOISE

AND VIBRATION CONTROL for HVAC PIPING AND EQUIPMENT, Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC and Section 23 09 23 DIRECT-

DIGITAL CONTROL SYSTEM FOR HVAC requirements. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning

Agent may spot check a sample of completed checklists. If the

Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission.

If the Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the

Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS for submittal requirements for Pre-

Functional Checklists, Equipment Startup Reports, and other commissioning documents.

02-01-20

COMMISSIONING OF HVAC SYSTEMS

23 08 00 - 4

3.3 CONTRACTORS TESTS

Contractor tests as required by other sections of Division 23 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected

Contractor tests at the sole discretion of the Commissioning Agent.

Contractor tests shall be completed prior to scheduling Systems

Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING:

The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the

COR. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing.

The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional requirements.

3.5 TRAINING OF VA PERSONNEL

Training of the VA operation and maintenance personnel is required in cooperation with the COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

The instruction shall be scheduled in coordination with the VA COR after submission and approval of formal training plans. Refer to

Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and Division 23

Sections for additional Contractor training requirements.

----- END -----