MANHOLES 19529-02 VA Hospital of Philedelphia 11.17.22.pdf

PDF 15 MB Posted

Attached to
Z1DA--642-22-104 | Upgrade Substation Building 2 Phase 1 for Philadelphia VAMC
Solicitation number
36C24426R0088
Issued by

About this file

This is a cable maintenance final report documenting electrical testing and engineering services performed at the VA Hospital of Philadelphia on November 13, 2022.

The report documents inspection of seven underground cable manholes—four normal power distribution manholes and three emergency power distribution manholes—conducted by Potomac Testing, Inc. (PTI) for A Design Group LLC. All inspections occurred during a two-hour power shutdown window (06:00-08:00 for normal power; 09:00-11:00 for emergency power) with cable technicians observing and commenting on manhole and medium-voltage cable conditions. The normal power manholes contained XLP 1/0 15kV cables rated at 220mils with 133% insulation, featuring twelve feeders per manhole with varying numbers of splices (ranging from one to four sets) and spare pipes (ranging from four to eleven). The emergency power manholes contained newer EPR 4/0 15kV cables rated at 220mils with 133% insulation, installed in 2012, featuring three to six feeders with junction bars and load break elbows instead of splices. All normal power manholes showed some water and mud accumulation; emergency power manholes remained dry. The report concludes that cable conditions are suitable for continued service, though the normal power cables are well past the manufacturer's 30-year life expectancy. Field engineer Mervin Gray conducted the inspection. PTI Reference No. 19529-02.

View the file

Other files

File Type Posted
2024-12-03_HAZARDOUS AND UNIVERSAL WASTE POLICY.pdf PDF
2024-12-03_HAZARDOUS MATERIALS AND WASTE MANAGEMENT PLAN.pdf PDF
ALL-31-SINGLE-LINES-ONE-FILE-012325.pdf PDF
FMS 138-54 Hot Work Policy.doc DOC document
Confined Space Entry Program.pdf PDF
Electrical Safety Program.pdf PDF
7714_D_2017-04-06 ASBESTOS MANAGEMENT PROGRAM.pdf PDF
VHA Dir 7714 Asbestos Management Program.pdf PDF
Fire and Smoke Barrier Pentration Permit.pdf PDF
Safety Coordination Meeting Safety Policies for SOW Project 642-22-104.pdf PDF
B6-SUB-PRIMARY-NORMAL-324-371-DWG-FINAL-070623.pdf PDF
Inspection Final RAC Blank Master.docx DOCX document
SAFE PRACTICES FOR WORKING WITH LIVE ELECTRICAL POWER.pdf PDF
36C24426R0088 0004.pdf PDF
RFI 2 Upgrade Substation 36C24426R0088.docx DOCX document
B02-SUB-3.pdf PDF
FMS SOP 138-44 Fire and Smoke Barrier Penetration Policy.pdf PDF
B02-SUB-2.pdf PDF
B6-SITE-POWER-WITH-MANHOLES-DWG-FINAL-070623.pdf PDF
2024-12-03_Green Procedure Program.pdf PDF
FIRE SYSTEM permit 2021 blank.pdf PDF
VHA ICRA-1.2 Oct 1 2024.pdf PDF
B02-SUB-1.pdf PDF
Blank Above Ceiling Permit.pdf PDF
Asbestos Control Regulation.pdf PDF
Building 2_LS_SB_G_B FOR REFERENCE ONLY.pdf PDF
INFECTION PREVENTION AND CONTROL POLICY BEHAVIORAL HEALTH SERVICES.pdf PDF
Fire Plan.pdf PDF
FMS SOP 138-54 Hot Work Policy.pdf PDF
Safety and Health During Construction.pdf PDF
B02-SUB-4.pdf PDF
36C24426R0088 0003.pdf PDF
36C24426R0088 0003.pdf PDF
Attachment 1 RFI 1 Upgrade Substation 642-22-104.docx DOCX document
Attachment 3 General Decision Number PA20260003 10012026.docx DOCX document
Attachment 1 RFI 1 Upgrade Substation 642-22-104.docx DOCX document
Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docx DOCX document
36C24426R0088 0003.pdf PDF
36C24426R0088 0002.docx DOCX document
36C24426R0088 0001.docx DOCX document
S04 Pre-Bid Sign-In Sheet 36C24426R0088 - 642-22-104 - Upgrade Substation.pdf PDF
Substations Upgrade Building 2-Phase 1_Bid Documents_Specification_10-21-24.pdf PDF
Substations Upgrade Building 2-Phase 1 Combined Drawings.pdf PDF
36C24426R0088_1.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .