FMS SOP 138-44 Fire and Smoke Barrier Penetration Policy.pdf

PDF 76 KB Posted

Attached to
Z1DA--642-22-104 | Upgrade Substation Building 2 Phase 1 for Philadelphia VAMC
Solicitation number
36C24426R0088
Issued by

About this file

This is a Standard Operating Procedure (SOP) document establishing fire and smoke barrier penetration policy for the Department of Veterans Affairs Medical Center in Philadelphia.

The policy requires contractors and in-house maintenance personnel to obtain permits from Facilities Management's Safety Office before conducting any work above ceilings or penetrating vertical and horizontal walls or floor assemblies, including electrical, security, data/voice, and mechanical work. Permits are issued on a job-by-job basis except for multiple work areas within a single project. All holes and spaces in fire or smoke barriers must be repaired in accordance with Underwriters Laboratories (UL) standards as soon as feasible after work completion using HILTI FIRESTOP or an UL-approved equivalent product, with submission of data for approval of alternative products. Sleeves must be solidly set in barriers with approved materials filling the space between items. All permits must be certified by the worker, submitted to the Facilities Management representative, and returned to the Safety Office within 24 hours. The Facilities Managers representative is responsible for administering the program and conducting final inspections, while the Safety Office approves and files permits and performs regular inspections of fire and smoke barriers. Contractors and personnel must comply with the policy, notify Facilities Management during work if questions arise, and schedule final inspections upon completion, with contact information provided for the Safety Manager at extension 6109 or Facilities Management at (215) 823-5811. The policy references NFPA 101, NFPA 80, NFPA 90A, and HILTI Fire stop Systems Guide standards.

View the file

Other files

File Type Posted
2024-12-03_HAZARDOUS AND UNIVERSAL WASTE POLICY.pdf PDF
2024-12-03_HAZARDOUS MATERIALS AND WASTE MANAGEMENT PLAN.pdf PDF
ALL-31-SINGLE-LINES-ONE-FILE-012325.pdf PDF
FMS 138-54 Hot Work Policy.doc DOC document
Confined Space Entry Program.pdf PDF
Electrical Safety Program.pdf PDF
7714_D_2017-04-06 ASBESTOS MANAGEMENT PROGRAM.pdf PDF
VHA Dir 7714 Asbestos Management Program.pdf PDF
Fire and Smoke Barrier Pentration Permit.pdf PDF
Safety Coordination Meeting Safety Policies for SOW Project 642-22-104.pdf PDF
B6-SUB-PRIMARY-NORMAL-324-371-DWG-FINAL-070623.pdf PDF
Inspection Final RAC Blank Master.docx DOCX document
SAFE PRACTICES FOR WORKING WITH LIVE ELECTRICAL POWER.pdf PDF
36C24426R0088 0004.pdf PDF
RFI 2 Upgrade Substation 36C24426R0088.docx DOCX document
B02-SUB-3.pdf PDF
B02-SUB-2.pdf PDF
B6-SITE-POWER-WITH-MANHOLES-DWG-FINAL-070623.pdf PDF
2024-12-03_Green Procedure Program.pdf PDF
FIRE SYSTEM permit 2021 blank.pdf PDF
MANHOLES 19529-02 VA Hospital of Philedelphia 11.17.22.pdf PDF
VHA ICRA-1.2 Oct 1 2024.pdf PDF
B02-SUB-1.pdf PDF
Blank Above Ceiling Permit.pdf PDF
Asbestos Control Regulation.pdf PDF
Building 2_LS_SB_G_B FOR REFERENCE ONLY.pdf PDF
INFECTION PREVENTION AND CONTROL POLICY BEHAVIORAL HEALTH SERVICES.pdf PDF
Fire Plan.pdf PDF
FMS SOP 138-54 Hot Work Policy.pdf PDF
Safety and Health During Construction.pdf PDF
B02-SUB-4.pdf PDF
36C24426R0088 0003.pdf PDF
36C24426R0088 0003.pdf PDF
Attachment 1 RFI 1 Upgrade Substation 642-22-104.docx DOCX document
Attachment 3 General Decision Number PA20260003 10012026.docx DOCX document
Attachment 1 RFI 1 Upgrade Substation 642-22-104.docx DOCX document
Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docx DOCX document
36C24426R0088 0003.pdf PDF
36C24426R0088 0002.docx DOCX document
36C24426R0088 0001.docx DOCX document
S04 Pre-Bid Sign-In Sheet 36C24426R0088 - 642-22-104 - Upgrade Substation.pdf PDF
Substations Upgrade Building 2-Phase 1_Bid Documents_Specification_10-21-24.pdf PDF
Substations Upgrade Building 2-Phase 1 Combined Drawings.pdf PDF
36C24426R0088_1.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Corporal Michael J. Cresenz Facility Management Support

Dept. of Veterans Affairs Medical Center Standard Operating Procedure

Philadelphia, PA 19104 No. 138-44 May 2018

FIRE AND SMOKE BARRIER (CEILING TILE)

PENETRATION POLICY

1. PURPOSE: To provide a fire-safe environment of care and to protect patients, personnel, visitors, and property from fire, smoke and other products of combustion by maintaining the integrity of smoke and fire barriers. A permit will be required for all above ceiling work including removal of ceiling tiles and penetrations of any vertical and horizontal partitions and floor assemblies.

2. POLICY:

A. Contractors and in-house maintenance personnel shall obtain a permit from Facilities Management’s Safety Office before beginning work that requires above ceilings or penetrations of any vertical or horizontal walls or floor assemblies. This includes all electrical, security, data/voice and mechanical, etc.

work above ceilings. Work permits will not be issued on a blanket basis, except as related to multiple work areas in a single job (e.g., cable and electrical conduit penetrating several fire walls).

B. Holes and spaces in fire or smoke barriers shall be repaired in accordance with Underwriters Laboratories (UL), a trusted source of product compliance testing guides for fire and smoke assemblies as soon as feasible after work is completed.

C. All permits shall be closed out daily and submitted to the Safety Office within 24 hours.

3. RESPONSIBILITES:

A. The Facilities Managers representative will:

1. Administer the Fire and Smoke Barrier Penetration Policy and

Permit Program.

2. Conduct final inspections of work areas before closing out permits.

3. Regularly inspect smoke and fire barriers, ceilings, and floors to verify continuity and complete repairs as necessary.

FMS SOP NO. 138-44 May 2018

4. Regularly inspect door assemblies and other protective devices

(e.g., fire shutters, dampers) installed within smoke and fire barriers to verify proper operation and complete repairs as necessary.

5. Facilities Management Representative is dependent on the following:

IMS and FITS Permits Safety Office

Construction Personnel Project Engineer

Maintenance Personnel Shop Foreman

B. The Safety Office shall:

1. Be responsible for approving and filing permits.

2. Regularly inspect smoke and fire barriers, ceilings, and floors to verify continuity and complete repairs as necessary for FITS and Police

Service Contractors.

3. Perform random checks of completed permits outside of FITS and

Police Service Contractors.

C. All Service Lines and Sections Contractors and PVAMC personnel who are conducting above ceiling work and/or penetrating barriers shall:

1. Comply with provisions of this policy.

2. Notify Facilities Management during work if there are questions regarding repairs and after repairs are completed to schedule a final inspection. Contact the Safety Manager at (215) 823-5800 at extension

6109 or the main number for Facilities Management (215) 823-5811.

4. PROCEDURES:

A. Permits will be obtained from Facilities Management/Safety Office, Building #5.

B. All holes and spaces in fire and smoke barriers will be protected as follows:

1. Filled per HILTI Company Manufacturer’s Manual with HILTI

FIRESTOP or equal capable of maintaining the fire resistance of the smoke or fire barrier, (submit data for approval if equivalent product is to be used). All requirements for floor and wall assemblies’ wall/ floor penetrations must be met in accordance with an Underwriter Laboratory

(UL) fire stop product.

FMS SOP NO. 138-44 May 2018

2. Sleeves, where required, shall be solidly set in the smoke or fire barrier and the space between the items shall be filled with an approved material capable of maintaining the fire resistance of the smoke or fire barrier.

3. Upon completion of work and all penetrations are filled in accordance with this policy, ceiling tile shall be seated properly on the drop ceiling.

4. Permit shall be certified by the worker and submitted to the

Facility Management representative and returned to the Safety Office for recordkeeping within 24 hours.

5. REFERENCES:

A. National Fire Protection Association (NFPA) 101, Life Safety Code

(Latest Edition)

B. NFPA 80, Fire Doors and Fire Windows (Latest Edition)

C. NFPA 90A, Installation of Air Conditioning and Ventilating Systems

(Latest Edition)

D. HILTI Fire stop Systems Guide

6. RESCISSION: Medical Center Memorandum No. 138-36 dated May 2011.

Replaced by this FMS Memorandum 138-44.

7. REVIEW DATE: May 2021.

William England

Chief Engineer, FMS