31-Sec 02 41 16 Demolition.pdf

PDF 82 KB Posted

Attached to
2201256.01 - Whistlestop Park
Solicitation number
US.160528
Issued by
Montgomery County, Pennsylvania

About this file

This is a demolition specification document prepared for Montgomery Township in Pennsylvania as part of the Whistlestop Park rehabilitation project. Section 02 41 16 outlines the complete removal and disposal requirements for existing site features, including designated structures (baseball fields, play equipment, asphalt trails, border timbers, stormsewers, yard drains, stone, and a train structure), trees, and brush in accordance with the construction sequence shown in the project plans. The contractor must submit demolition and removal procedures and schedule if proposing methods that deviate from those outlined in Section 01 11 13 of the contract documents. The work requires careful execution to minimize interference with adjacent areas while maintaining protected egress and access, with temporary barriers and security devices to be provided as necessary. Dust control measures must be implemented throughout the demolition phase, and all utilities must be located and verified prior to work commencement, with active utilities either protected or properly disconnected and capped as appropriate.

Execution of demolition work must follow an orderly and careful process with protection of existing structures and features that are to remain. Demolished materials must be removed from the site immediately as work progresses, except where items are designated for re-installation or retention, which must be handled to prevent damage. Contaminated, vermin-infested, or dangerous materials encountered during demolition must be removed and properly disposed of. Excavated subsurfaces require careful backfilling and grading to proposed ground level in accordance with Section 31 23 33 specifications to ensure proper drainage. Tree removal includes complete removal of stumps and root masses, which shall not be buried on the property; tree removal areas must be backfilled with clean topsoil to proposed grade and subsequently seeded and mulched. The specification explicitly prohibits setting fires to structures and burning of debris except with written permission from local fire or police authorities and in compliance with State Air Pollution Control Commission regulations.

View the file

Other files

File Type Posted
13-Doc 00 43 13 - Bid Bond (penal sum form).pdf PDF
50-Doc 00 65 19.16 Contractors Release of Liens.pdf PDF
54-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
48-Sec 32 18 23.13-Natural Grass Sports Field Construction.pdf PDF
41-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
26-Doc 00 91 13 - 01 Appendix I - Cover.pdf PDF
29-Doc 00 73 00 06 - Appendix C - Cover.pdf PDF
38-Doc 00 73 00 12- Appendix F - Cover.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
69-Doc 00 73 00 15 - Appendix G - Other DCED Requirements.pdf PDF
55-Doc 00 73 00 03 - Appendix A 2026-02-02 - prevailing wages whistlestop SN26-00920.pdf PDF
7-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
67-Sec 32 93 02 Exterior Planting.pdf PDF
77-Sec 33 44 15 Boxes and Endwalls.pdf PDF
28-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
78-06 FINAL Site Drawings - Gilmore 2026-03-12.pdf PDF
47-Sec 01 57 14 Erosion Control Blanket.pdf PDF
17-Doc 00 62 76 - C-620 Appl for Payment 2007.pdf PDF
19-Sec 31 20 00 Earthwork.pdf PDF
21-Doc 00 61 13.16 - Payment Bond.pdf PDF
76-Doc 00 73 00 17 - Appendix H - DCNR Signage Policy.pdf PDF
40-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
46-Sec 01 33 00 - Submittals.pdf PDF
12-Doc 00 73 00 13 - Appendix F - Nondiscrimination-Sexual Harassment Provisions.pdf PDF
43-Doc 00 45 10 - BIDDERS ACKNOWLEDGEMENT FORM.pdf PDF
9-Doc 00 73 00 08 - Appendix D - Cover.pdf PDF
51-Sec 31 23 16.26 Rock Removal.pdf PDF
75-Sec 32 92 00 Finish Grading Seeding and Sodding.pdf PDF
27-Sec 33 44 14 Storm Inlets Catch Basins Endwalls End Sections.pdf PDF
56-Sec 31 11 00 Clearing and Grubbing.pdf PDF
35-Doc 00 73 00 11- Appendix E - Americans with Disabilities Act.pdf PDF
62-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
65-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
34-Doc 00 65 19.13 - Contractors Affidavit.pdf PDF
58-Sec 32 18 23.53-Acrylic Color Coat - Generic.pdf PDF
3-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
57-Sec 32 12 00 - Asphalt Paving.pdf PDF
20-Doc 00 73 00 09 - Appendix D - Architectural Barriers Act.pdf PDF
10-Doc 00 61 19 - Maintenance Bond.pdf PDF
71-Doc 00 73 00 07 - Appendix C - State Contractor Responsibility Program.pdf PDF
52-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
2-Doc 00 41 00 - Bid Form.pdf PDF
14-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
22-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT - 2024.pdf PDF
25-Doc 01 01 01 - Appendix J Technical Specs Cover Sheet.pdf PDF
59-Doc 00 41 00 - BID FORM - EBID.pdf PDF
30-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
36-Doc 00 73 00 10- Appendix E - Cover.pdf PDF
45-Doc 00 73 00 1 - SUPPLEMENTARY CONDITIONS.pdf PDF
60-Doc 00 73 00 05 - Appendix B - Public Works Employment Verification Form.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEMOLITION

02 41 16-1

SECTION 02 41 16

PART 1 - GENERAL

1.01 WORK INCLUDED

A. Remove and dispose of all items shown on the Drawings in accordance with the construction sequence provided on the plans including the following:

1. Remove and dispose of designated structures and associated facilities, including the existing baseball fields, play equipment, existing asphalt trail and border timbers, existing stormsewer and yard drains, stone, and the existing train structure.

2. Remove and dispose of designated trees and brush.

1.02 RELATED WORK

A. Section 01 11 13: Summary of Work.

B. Section 01 70 00: Contract Closeout: Project record documents.

1.03 SUBMITTALS

A. Submit demolition and removal procedures and schedule under provisions of Section 01 33 00 if Contractor proposes to use procedures and schedule which are not in accordance with those procedures and schedule presented in the Work Sequence portion of Section 01 11 13.

1.04 EXISTING CONDITIONS

A. Conduct demolition to minimize interference with adjacent areas. Maintain protected egress and access at all times.

B. Provide, erect, and maintain temporary barriers and security devices as required.

C. Satisfactorily prevent or control dust resulting from demolition.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01 PREPARATION

A. Locate existing active utilities and verify whether each utility will remain in service and therefore require protection or is part of the demolition and removal activity.

B. Protect existing items which are not indicated to be altered.

C. Prior to starting work, make arrangements with the proper authorities for turning off and disconnecting utilities in conjunction with demolition activities. Disconnect, remove, and cap designated utility services within demolition areas. Mark location of disconnected utilities.

Identify and indicate capping locations on Project Record Documents.

02 41 16-2

3.02 EXECUTION

A. Demolish in an orderly and careful manner. Protect any existing structures and features to remain from damage.

B. Do not disturb existing pavement areas that are to remain unless it becomes necessary to do so in order to complete other work.

C. Do not, under any circumstances, set fire to structures. Burning of debris shall not be allowed except by written permission of local police or fire authorities and unless the burning conforms with State Air pollution Control Commissions regulations. Do not begin burning until a copy of the written permission has been received by the Engineer.

D. Except where noted otherwise, immediately remove demolished materials from site.

E. Remove materials to be re-installed or retained in manner to prevent damage.

F. Remove, store, and protect materials and equipment for re-installation as necessary and/or as noted.

G. Remove and promptly dispose of contaminated, vermin infested, or dangerous materials encountered.

H. Remove demolished materials from site as work progresses. Upon completion of work, leave areas of work in clean condition.

I. Carefully backfill excavated subsurfaces, and grade to the proposed ground level. Backfill in accordance with specification Section 31 23 33 Excavation, Backfill and Compaction and grade to ensure proper drainage.

J. Remove trees in the following manner:

1. Tree removal includes removal of stumps/root mass. Removed stumps/root mass shall not be buried on property. Tree removal area shall be backfilled with clean topsoil to proposed grade followed by seeding and mulching.

END OF SECTION