21-25-26-02-20 SUBSTITUTION REQUEST FORM.pdf

PDF 108 KB Posted

Attached to
HODGE ELEMENTARY REFRIGERATOR
Solicitation number
25-26-02-20
Issued by
Los Angeles County, Anaheim City, California

About this file

This is a Substitution Request Form issued by Azusa Unified School District (AUSD) in California for use during the bidding and construction process for a walk-in refrigerator project at Victor Hodge Elementary School, located at 700 W. 11th Street, Azusa, CA 91702. The form provides a structured process for contractors to propose alternative materials, equipment, or components as substitutes for items specified in the original project specifications and drawings. Contractors submitting substitution requests must provide comprehensive documentation including complete descriptions, catalog numbers, specification data, and laboratory testing results for the proposed items. The form requires detailed analysis of how the substitution would impact the project, including effects on dimensions, electrical systems, mechanical systems, structural elements, and architectural components, as well as how the substitution would affect other construction trades.

The form establishes specific requirements for substitution approval, including manufacturer warranty information, UL or other required listings and ratings for the proposed assembly, and any weight differences compared to the specified item. Contractors submitting substitutions must agree to pay all architectural and engineering costs associated with reviewing, testing, or revising drawings and specifications necessitated by the substitution, as well as any additional construction costs resulting from acceptance. The form provides space for price adjustments or credits to the contract price resulting from the substitution. AUSD reviews and approves, rejects, or conditionally accepts substitution requests, with dated notation and remarks provided by the district. Submissions include contractor information, contact details, and authorized signatures from corporate officers.

View the file

Other files

File Type Posted
13-25-26-02-20 - NOTICE INVITING BIDDERS.pdf PDF
12-25-26-02-20 - LIST OF CURRENT MODERNIZATION PROJECTS AS PRIME CONTRACTOR.pdf PDF
16-25-26-02-20 CONTRACTOR CERTIFICATION OF BACKGROUND CHECKS.pdf PDF
3-25-26-02-20 - BID BOND.pdf PDF
14-25-26-02-20 - PAYMENT BOND.pdf PDF
19-Pre-Qualification Questionnaire Blank.pdf PDF
22-25-26-02-20 CHECKLIST OF MANDATORY BID FORMS.pdf PDF
11-25-26-02-20 - INSURANCE DOCUMENTS ENDORSEMENTS.pdf PDF
4-25-26-02-20 - BID FORM.pdf PDF
2-25-26-02-20 - AGREEMENT FORM.pdf PDF
7-25-26-02-20 - DISABLED VETERAN BUSINESS ENTERPRISE PARTICIPATION STATEMENT.pdf PDF
15-25-26-02-20 - PERFORMANCE BOND.pdf PDF
24-HODGE ELEMENTARY WRITTEN SPECIFICATIONS.pdf PDF
23-WALLS AND FLOORS SPECIFICATIONS.docx DOCX document
17-25-26-02-20 LIST OF K-12 REFERENCES.pdf PDF
20-25-26-02-20 CERTIFICATION OF NON-DEBARMENT OR SUSPENSION.pdf PDF
8-25-26-02-20 - DVBE CONTRACTOR CLOSE OUT.pdf PDF
6-25-26-02-20 - DESIGNATION OF SUB-CONTRACTORS.pdf PDF
9-25-26-02-20 - ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION.pdf PDF
27-25-26-02-20 Hodge Walk-In Refrigerator Project Manual.pdf PDF
26-Bidders Acknowledgement of Project Manual 04.10.pdf PDF
10-25-26-02-20 - GUARANTEE.pdf PDF
18-25-26-02-20 NON-COLLUSION DECLARATION.pdf PDF
5-25-26-02-20 - CASHIERS CHECK.pdf PDF
25-HODGE ELEMENTARY REFRIGERATOR DIAGRAMS.pdf PDF
1-25-26-02-20 - INSTRUCTION TO BIDDERS.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YYAzusa Unified School District

SUBSTITUTION REQUEST FORM

(Add additional sheets as necessary to provide adequate information)

Specified Item

Specification Section Paragraph No. Drawing & Detail(s) No.

Proposed Substitution (Attach complete description, Catalog #s, Specification Data, Lab test, etc.)

1. Will Substitution effect dimensions indicated on Drawings?______(Yes)______(No)

2. Will Substitution effect Electrical, Mechanical, Structural Frame, Architecture, etc?______(Yes)______(No)

3. Is weight greater/lesser than specified item?_____(Yes)_____(No)_____ by how much?______________

4. What effect will substitution have on other trades?_____________________________________________

5. Difference between proposed and specified item?_____________________________________________

6. Manufacturer’s guarantee/warranty: same________ different________ Explain_____________________

7. Provide UL, WHI, (or other) Listing/Rating of proposed assembly._________________________________

8. If Substitution request is accepted, the owner will receive a credit of: $____________________________, which will be an adjustment to the contract price.

The undersigned agrees to pay all Architectural and Engineering costs, if required, to review, test or revise the drawings or specifications caused by this substitution, and further agrees to pay any and all additional construction costs created by acceptance of this substitution.

Submitted by:__________________________________

Firm:_________________________________________

Address:__________________________________________

AUSD Review Date:_______/_______/______

Accepted__________________ Not Accepted ______________

Accepted as noted __________

Remarks Phone:_________________Fax:_________________email:_______________

Signature:____________________________________Corporate Officer

Printed Name:_______________________________________________

Date:________________

File details come from the government source that posted it. Updated .