This is a Guarantee document for the Azusa Unified School District related to a Class B General Building Contractor project for the installation of a walk-in refrigerator at Victor Hodge Elementary School, located at 700 W. 11th Street, Azusa, CA 91702. The guarantee establishes that work has been completed in accordance with contract documents, drawings, and specifications. The contractor and its surety are obligated to repair or replace any defective work in materials or workmanship within one year from the Notice of Completion, with ordinary wear and tear and unusual abuse or neglect excepted. The District retains the right to perform repairs at the contractor's expense if defects are not addressed within ten calendar days of written notification, or within forty-eight hours for emergencies, with joint and several liability for all associated costs.

The document outlines mandatory bid submission requirements including a List of Completed Projects, Designation of Subcontractors Form, references from K-12 public school districts, information on current and completed modernization projects as prime contractor within the last ten years, Disabled Veteran Business Enterprise participation statement, payment and performance bonds, insurance documents with specific endorsements, and contractor certifications regarding background checks. The contract includes comprehensive provisions addressing supervision, labor and materials, permits, submittals, shop drawings, cleaning, safety, insurance with minimum coverage limits of $2,000,000 aggregate and $1,000,000 per occurrence, workers' compensation, builder's risk insurance, wage rates, apprentices, and project labor agreement requirements. The file also references District authority to conduct stop work orders, enforce change order procedures, withhold payments for nonconforming work, and terminate contracts for cause or convenience.

View the file

Other files

File Type Posted
27-25-26-02-20 Hodge Walk-In Refrigerator Project Manual.pdf PDF
26-Bidders Acknowledgement of Project Manual 04.10.pdf PDF
18-25-26-02-20 NON-COLLUSION DECLARATION.pdf PDF
5-25-26-02-20 - CASHIERS CHECK.pdf PDF
25-HODGE ELEMENTARY REFRIGERATOR DIAGRAMS.pdf PDF
1-25-26-02-20 - INSTRUCTION TO BIDDERS.pdf PDF
22-25-26-02-20 CHECKLIST OF MANDATORY BID FORMS.pdf PDF
11-25-26-02-20 - INSURANCE DOCUMENTS ENDORSEMENTS.pdf PDF
4-25-26-02-20 - BID FORM.pdf PDF
2-25-26-02-20 - AGREEMENT FORM.pdf PDF
7-25-26-02-20 - DISABLED VETERAN BUSINESS ENTERPRISE PARTICIPATION STATEMENT.pdf PDF
15-25-26-02-20 - PERFORMANCE BOND.pdf PDF
24-HODGE ELEMENTARY WRITTEN SPECIFICATIONS.pdf PDF
13-25-26-02-20 - NOTICE INVITING BIDDERS.pdf PDF
12-25-26-02-20 - LIST OF CURRENT MODERNIZATION PROJECTS AS PRIME CONTRACTOR.pdf PDF
16-25-26-02-20 CONTRACTOR CERTIFICATION OF BACKGROUND CHECKS.pdf PDF
3-25-26-02-20 - BID BOND.pdf PDF
14-25-26-02-20 - PAYMENT BOND.pdf PDF
19-Pre-Qualification Questionnaire Blank.pdf PDF
23-WALLS AND FLOORS SPECIFICATIONS.docx DOCX document
17-25-26-02-20 LIST OF K-12 REFERENCES.pdf PDF
20-25-26-02-20 CERTIFICATION OF NON-DEBARMENT OR SUSPENSION.pdf PDF
8-25-26-02-20 - DVBE CONTRACTOR CLOSE OUT.pdf PDF
21-25-26-02-20 SUBSTITUTION REQUEST FORM.pdf PDF
6-25-26-02-20 - DESIGNATION OF SUB-CONTRACTORS.pdf PDF
9-25-26-02-20 - ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Guarantee Azusa USD

GUARANTEE

Guarantee for . We hereby guarantee that the , which we have installed in has been done in accordance with the Contract Documents, including without limitation, the drawings and specifications, and that the work as installed will fulfill the requirements included in the bid documents. The undersigned and its surety agrees to repair or replace any or all such work, together with any other adjacent work, which may be displaced in connection with such replacement, that may prove to be defective in workmanship or material within a period of One ( 1 ) year from the date of the Notice of Completion of the above-mentioned structure by the Azusa Unified School District, ordinary wear and tear and unusual abuse or neglect excepted.

In the event the undersigned or its surety fails to comply with the above-mentioned conditions within a reasonable period of time, as determined by the District, but not later than ten (10) days after being notified in writing by the District or within forty eight (48) hours in the case of an emergency or urgent matter, the undersigned and its surety authorizes the District to proceed to have said defects repaired and made good at the expense of the undersigned and its surety, who will pay the costs and charges therefor upon demand. The undersigned and its surety shall be jointly and severally liable for any costs arising from the District’s enforcement of this Guarantee.

Countersigned

(Proper Name) (Proper Name)

By:

By:

(Signature of Subcontract or Contractor) (Signature of General Contractor if for Subcontractor)

Representatives to be contacted for service:

Name:

Address:

Phone Number:

NOTICE INVITING BIDS
Class B – General Building Contractor
INSTRUCTIONS TO BIDDERS
Azusa Unified School District Business Department
ATTN: Purchasing Supervisor
CHECKLIST OF MANDATORY BID FORMS
BID FORM
17. LIST OF COMPLETED PROJECTS (MANDATORY TO BE SUBMITTED WITH THE BID).
DESIGNATION OF SUBCONTRACTORS
DESIGNATION OF SUBCONTRACTORS FORM
INFORMATION REQUIRED OF BIDDER
List of References K-12 Public School Districts
List of Current Modernization Projects as Prime Contractor
List of Completed Modernization Projects as Prime Contractor
in the Last Ten (10) Years
(Use only when not using a Bid Bond)
DISABLED VETERAN BUSINESS ENTERPRISE (DVBE) PARTICIPATION STATEMENT
AGREEMENT FORM
PAYMENT BOND
PERFORMANCE BOND
GUARANTEE
ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION
INSURANCE DOCUMENTS & ENDORSEMENTS
DISABLED VETERAN BUSINESS ENTERPRISE (DVBE) CONTRACTOR CLOSE-OUT STATEMENT
CONTRACTOR CERTIFICATION REGARDING BACKGROUND CHECKS
ATTACHMENT A:
CONTRACTOR CERTIFICATION REGARDING BACKGROUND CHECKS
ARTICLE 1 DEFINITIONS
1.1 BASIC DEFINITIONS
1.2 EXECUTION, CORRELATION AND INTENT
1.3 OWNERSHIP AND USE OF ARCHITECT’S DRAWINGS, SPECIFICATIONS AND OTHER DOCUMENTS
ARTICLE 2 DISTRICT
2.1 INFORMATION AND SERVICES REQUIRED OF THE DISTRICT
WARNING: DISTRICT DOES NOT WARRANT THE SOILS AT THE PROJECT SITE. CONTRACTOR HAS REVIEWED AND IS FAMILIAR WITH THE REQUIREMENTS OF THE SOILS INVESTIGATION REPORT. CONTRACTOR UNDERSTANDS THAT PLANS, DRAWINGS AND SPECIFICATIONS SUPERSEDE THE SOILS REPOR...
2.2 DISTRICT’S RIGHT TO CARRY OUT THE WORK DUE TO PARTIAL DEFAULT IN A SPECIFIC SEGREGATED AREA OF WORK (48 HOUR NOTICE TO CURE AND CORRECT)
3.2 SUPERVISION
3.3 LABOR AND MATERIALS
3.4 WARRANTY
3.5 TAXES
3.6 PERMITS, FEES AND NOTICES
3.7 SUBMITTALS REQUIRED AT THE COMMENCEMENT OF THE PROJECT
3.8 DOCUMENTS, SAMPLES, AND COMPUTER AT THE SITE
3.9 SUBMITTALS INCLUDING SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
3.10 SUBSTITUTIONS
3.11 INTEGRATION OF WORK
3.12 CLEANING UP
3.13 ACCESS TO WORK
3.14 ROYALTIES AND PATENTS
3.15 INDEMNIFICATION
3.16 SUBMISSION OF DAILY REPORTS
3.17 AS-BUILT DRAWINGS AND ANNOTATED SPECIFICATIONS
3.18 EQUIPMENT MANUALS
3.19 DIR REGISTRATION
4.2 ARCHITECT’S ADMINISTRATION OF THE CONTRACT
4.3 PROJECT INSPECTOR
4.4 STOP WORK ORDER
4.5 RESPONSIBILITY FOR ADDITIONAL CHARGES INCURRED BY THE DISTRICT FOR PROFESSIONAL SERVICES
4.6 DISPUTES AND CLAIMS
ARTICLE 5 SUBCONTRACTORS
CONTRACTOR IS AWARE THAT THIS CONTRACT MAY BE SPLIT INTO SEVERAL PHASES BASED ON DOCUMENTATION PROVIDED WITH THIS BID OR DISCUSSED AT THE JOB WALK. CONTRACTOR HAS MADE ALLOWANCE FOR ANY DELAYS OR DAMAGES WHICH MAY ARISE FROM COORDINATION WITH CONTRACT...
6.2 CONSTRUCTIVE OWNERSHIP OF PROJECT SITE AND MATERIAL
6.3 DISTRICT’S RIGHT TO CLEAN UP
ARTICLE 7 CHANGES IN THE WORK
CONTRACTOR UNDERSTANDS, ACKNOWLEDGES, AND AGREES THAT THE REASON FOR THIS NOTICE REQUIREMENT IS SO THAT DISTRICT MAY HAVE AN OPPORTUNITY TO ANALYZE THE WORK AND DECIDE WHETHER THE DISTRICT SHALL PROCEED WITH THE CHANGE ORDER OR ALTER THE PROJECT SO TH...
7.2 CHANGE ORDERS (“CO”)
7.3 CONSTRUCTION CHANGE DOCUMENT (CCD Category A, and CCD Category B) and IMMEDIATE CHANGE DIRECTIVE (ICD)
7.4 REQUEST FOR INFORMATION (“RFI”)
7.5 REQUEST FOR PROPOSAL (“RFP”)
7.6 CHANGE ORDER REQUEST (“COR”)
7.7 COST OF CHANGE ORDERS
8.2 HOURS OF WORK
8.3 PROGRESS AND COMPLETION
8.4 EXTENSIONS OF TIME - LIQUIDATED DAMAGES
ARTICLE 9 PAYMENTS AND COMPLETION
9.2 COST BREAKDOWN
9.3 PROGRESS PAYMENTS
9.4 APPLICATIONS FOR PROGRESS PAYMENTS
9.5 STOP NOTICE CLAIMS AND WARRANTY OF TITLE
9.6 DECISIONS TO WITHHOLD PAYMENT
9.7 NONCONFORMING WORK
9.8 SUBCONTRACTOR PAYMENTS
9.9 COMPLETION OF THE WORK
9.10 PARTIAL OCCUPANCY OR USE
9.11 COMPLETION AND FINAL PAYMENT
9.12 SUBSTITUTION OF SECURITIES
10.2 SAFETY OF PERSONS AND PROPERTY
10.3 EMERGENCIES
10.4 HAZARDOUS MATERIALS
11.2 WORKERS’ COMPENSATION INSURANCE
11.3 BUILDER’S RISK/ “ALL RISK” INSURANCE
11.4 FIRE INSURANCE
11.5 AUTOMOBILE LIABILITY
11.6 OTHER INSURANCE
11.7 PROOF OF INSURANCE
11.8 COMPLIANCE
11.9 WAIVER OF SUBROGATION
11.10 PERFORMANCE AND PAYMENT BONDS
4-343. Duties of the Contractor.
12.2 SPECIAL NOTICE OF AMERICAN’S WITH DISABILITIES ACT
12.3 UNCOVERING OF WORK
12.4 CORRECTION OF WORK
ARTICLE 13 MISCELLANEOUS PROVISIONS
13.2 SUCCESSORS AND ASSIGNS
13.3 WRITTEN NOTICE
13.4 RIGHTS AND REMEDIES
13.5 TESTS AND INSPECTIONS
13.6 TRENCH EXCAVATION
13.7 WAGE RATES, TRAVEL, AND SUBSISTENCE
13.8 RECORDS OF WAGES PAID
13.9 APPRENTICES
13.10 ASSIGNMENT OF ANTITRUST CLAIMS
13.11 STATE AND DISTRICT CONDUCTED AUDITS
13.12 STORM WATER POLLUTION PREVENTION
13.13 PROJECT LABOR AGREEMENT
14.2 TERMINATION BY THE DISTRICT FOR CAUSE
14.3 TERMINATION OF CONTRACT BY DISTRICT (CONTRACTOR NOT AT FAULT)
14.4 REMEDIES OTHER THAN TERMINATION
ARTICLE 15 DEBARMENT
15.2 BOARD FINDING
15.3 HEARING AND PRESENTATION OF EVIDENCE
ARTICLE 3 – THE CONTRACTOR
ARTICLE 8 – TIME
ARTICLE 11 – INSURANCE AND BONDS
ARTICLE 13.13 – PROJECT LABOR AGREEMENT
IMMEDIATE CONSTRUCTION CHANGE DIRECTIVE NO.
CERTIFICATE OF SUBSTANTIAL COMPLETION
Aggregate
Each Occurrence
$2,000,000
$1,000,000
Pollution Liability
INSURANCE SUBMITTALS FORM
11.1.1 Specific Insurance Requirements

File details come from the government source that posted it. Updated .