This document includes an environmental management system site-specific training presentation and information on a related federal contract opportunity. The training presentation covers Seymour Johnson Air Force Base's environmental management system, including what an EMS is, why it is used, its relationship to ISO 14001, the EMS cycle, keys to success, environmental aspects and impacts, the base's high priority aspects, employee roles and responsibilities, environmental policy, and the duty to conform.

The related federal contract opportunity is a solicitation for a Simplified Acquisition of Base Engineer Requirements indefinite-delivery/indefinite-quantity multiple award contract at Seymour Johnson Air Force Base, North Carolina. The contract scope includes maintenance, repair, alteration, and minor construction projects. The response due date for site visits is August 30, 2022 and the bid opening is October 4, 2022. The base IDIQ year term is 12 months with four additional 12-month option periods and a six-month extension period. Offerors must be registered in the System for Award Management to be eligible for award.

View the file

Other files

File Type Posted
FA480922B0001 - Bid Record - 14-Dec-22 (2 pages).pdf PDF
FA480922B0001 Abstract - Bid Opening 14-Dec-22 (4 pages).pdf PDF
Solicitation Amendment - FA480922B00010006 (Conformed) (83 pages) posted 7-December-2022.pdf PDF
Solicitation Amendment FA480922B00010006 SF 30 (4 pages) dated 7-December-22.pdf PDF
25. Min Rqmnt Proj (VKAG 20-1040) SOO (10 pgs) Rev 3 dtd 6-Dec-2022.pdf PDF
FA480922B00010005 Request for Information dated 5-December-2022.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) Statement of Objectives (REVISION 02) (10 pages) dated 1-November-2022.pdf PDF
Solicitation Amendment - FA480922B00010005 (Conformed) (87 pages) dated 28-November-2022.pdf PDF
Solicitation Amendment FA480922B00010005 SF 30 (13 pages) dated 28-November-2022.pdf PDF
2. SABER XI Statement of Work (67 pages) Revision 3 dated 26Oct22.pdf PDF
28. Section 271000 Building Telecommunications Cabling System (13 pages) dated 27-Oct-22.pdf PDF
Solicitation Amendment FA480922B00010004 SF 30 (3 pages) dated 14-October-2022.pdf PDF
Solicitation Amendment FA480922B00010003 SF 30 (10 pages) dated 27-September-2022.pdf PDF
2. SABER XI Statement of Work (66 pages) Revision dated 24-Sept-22.pdf PDF
26. Minimum Requirement Project (VKAG 20-1040) Drawings (Full Set) (8 pages) Revision dated 9-Sept-22.pdf PDF
Solicitation Amendment FA480922B00010002 SF 30 (9 pages) dated 22-September-2022.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) Statement of Objectives (9 pgs) Revision dtd 22-Sept-22.pdf PDF
SABER XI Requests for Information (RFIs) and Responses (19 pages) 20 September 2022.pdf PDF
Solicitation Amendment FA480922B00010001 SF 30 (2 pages) dated 9-September-2022.pdf PDF
12. AF Form 66 Schedule of Material Submittals - VKAG 22-1200 SABER Basic XI (1 page) Revision dated 6-September-22.pdf PDF
SABER XI PreBid Conference and Site Visit Meeting Minutes with Attachments (18 pages) dtd 30 Aug 22.pdf PDF
10. SJAFB Standard Engineering Drawing Preparation and Support (CAD Standards) (71 pages) dated 1-Dec-22.pdf PDF
23. SABER XI IDIQ Bid Schedule (2 pages) - BLANK.pdf PDF
18. Request for Information (1 page) - BLANK.pdf PDF
14. AF Form 103 Base Civil Engineering Work Clearance Request (2 pages) - BLANK.pdf PDF
12. AF Form 66 Schedule of Material Submittals - VKAG 22-1200 SABER Basic XI (1 page) dated 24-May-22.pdf PDF
Solicitation - FA480922B0001 - SJAFB SABER (Posted 19-Aug-22).pdf PDF
19. Contractor Production Report (QC Report) (8 pages) - EXAMPLE.pdf PDF
7.Section 02821 Centipede Grass Hydro-Seeding (10 pages) dated 24-May-22.pdf PDF
22. Wage Determinations (51 pages) dated 25-Feb-22.pdf PDF
13. AF Form 66 Schedule of Material Submittals (1 page) - BLANK.pdf PDF
2. SABER XI Statement of Work (65 pages) dated 12-Aug-22.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) - Statement of Objectives (5 pages) dated 9-May-22.pdf PDF
15. AF Form 3000 Material Approval Submittal (2 pages) - BLANK.pdf PDF
27. Pre-Proposal Conference and Site Visit Location Map (2 pages).pdf PDF
4. Section 01560 Environmental Management Supplement SJAFB Contractors (2 pages) dated 5-Jul-22.pdf PDF
26. Minimum Requirement Project (VKAG 20-1040) Drawings (Full Set) (7 pages) dated 1-Nov-20.pdf PDF
20. SJAFB Access Request Application (2 pages) - EDITABLE.pdf PDF
6. Section 02051 Asbestos Removal, Cleanup and Disposal, Facility Demolition (2 pages) dated 24-May-22.pdf PDF
24. Determination of Contractor Responsibility (3 pgs) - BLANK.pdf PDF
21. Climatic Data Summary for SJAFB (2 pages) dated 13-May-22.pdf PDF
11. Installation Development and Design (ID2) SJAFB (90 pages) dated Mar-11.pdf PDF
1. Nonapropriated Fund (NAF) Standard Clauses (21 pages) dated 2-Jun-22.pdf PDF
17. AF Form 3064 Contract Progress Schedule (3 pages) - EXAMPLE.pdf PDF
9. Seymour Johnson Mass Notification System Message Script (2 pages) dated 24-May-22.pdf PDF
8. Section 02938 Sod (2 pages) dated 24-May-22.pdf PDF
16. AF Form 3065 Contract Progress Report (1 page) - BLANK.pdf PDF
3. Section 01560 Environmental Protection (8 pages) dated 1-Jul-22.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

S E Y M O U R J O H N S O N A I R F O R C E B A S E , N O R T H C A R O L I N A

P R E P A R E D B Y 4 C E S / C E I E

ENVIRONMENTAL

MANAGEMENT SYSTEM:

SITE-SPECIFIC TRAINING

FA480922B0001

Attachment 5

Current as of April-2022

WHAT IS AN EMS?

An Environmental Management System (EMS) is:

A continual cycle of planning, implementing, reviewing and improving the processes and actions that an organization undertakes to meet its organizational and environmental goals.

A framework that allows an organization to consistently control the effects its operations or processes may have on the environment and to continually improve its operating procedures.

FA480922B0001

Attachment 5

WHY USE AN EMS?

Through the establishment of an EMS, Seymour Johnson AFB will reduce mission impacts on the environment while maintaining a high level of regulatory compliance.

Following an EMS will save time, money and valuable natural resources that can not be easily replaced.

The Department of Defense has mandated that all Air Force installations implement and comply with an EMS.

FA480922B0001

Attachment 5

ISO 14001

The Air Force has adopted ISO 14001 (2015) as the model for the development of an EMS at each installation. ISO 14001 was developed by the International Organization For Standardization, which is a non-profit entity that provides state of the art specifications to make industry more efficient and effective. ISO 14001 is the standard that sets guidelines for environmental management.

The ISO 14001 model utilizes a continual cycle of planning, implementing, checking and reviewing to improve environmental performance.

FA480922B0001

Attachment 5

THE EMS CYCLE

The EMS Cycle occurs in the following order:

Planning Phase - Environmental aspects and impacts are identified and environmental goals are established, based on an organizations mission.

Implementation Phase - Operational controls and written procedures are put in place and training is provided.

Checking Phase - Compliance and management systems are assessed, performance measures are monitored, and corrective actions are taken.

Review Phase - Leadership performs progress reviews and takes the required actions to improve the established EMS Cycle.

FA480922B0001

Attachment 5

KEYS TO A SUCCESSFUL EMS

Top leadership must commit to making the environment an organizational priority

There must be a focus on continual improvement, learning from mistakes, and preventing similar problems in the future

Organizations must remain flexible and maintain the ability to quickly adapt to a dynamic environment

Employees must remain aware and involved in implementing changes for improvement and reducing unwanted environmental impacts

FA480922B0001

Attachment 5

ACTIVITIES

Activities offer the greatest opportunity to impact the environment. They are work processes performed everyday and are more prevalent than services and products. Some examples of activities include:

Driving to work Disposing of waste Changing oil in vehicles Preparing jet engines Training air crews Printing documents

FA480922B0001

Attachment 5

ENVIRONMENTAL ASPECTS

An Environmental Aspect is any element of an organization’s activities, products or services that can interact with and/or impact the environment.

Paper consumption Energy consumption Waste generation Storm water runoff Hazardous materials usage

FA480922B0001

Attachment 5

ENVIRONMENTAL IMPACTS

An environmental impact is defined as any change to the environment, whether adverse or beneficial, resulting from the unit’s functional mission or activities. Examples of environmental impacts include the following:

Health and safety exposure Use of landfill space Use of natural resources Generation of non-hazardous waste Hearing impairment

FA480922B0001

Attachment 5

SJAFB’s HIGH PRIORITY ASPECTS

The environmental programs on Seymour Johnson AFB have been scored and ranked based on the number of aspects and potential for significant impacts.

SJAFB has chosen to Improve the Management of Oil/Water Separators by focusing attention on the need to eliminate unnecessary oil/water separators and repair or replace inadequate oil/water separators that remain in service.

Currently, there are 5 oil/water separators remaining in the improvement plan.

FA480922B0001

Attachment 5

YOUR ROLE IN EMS

Be familiar with the Seymour Johnson AFB Environmental Commitment Statement

Understand the environmental aspects associated with your work activities

Adhere to EMS procedures in your workplace

Comply with applicable federal, state, local, DoD and AF regulations

Identify environmental concerns early in the planning stages of new activities

Report existing or potential problems

Accept accountability for environmental performance

FA480922B0001

Attachment 5

ENVIRONMENTAL POLICY

The Seymour Johnson AFB Environmental Commitment Statement, signed into effect by the Wing Commander, directs that we are committed to regulatory compliance, the prevention of pollution, and a continually improving EMS.

“Environmental stewardship is the responsibility of every member of the Seymour Johnson community in accordance with his or her roles and responsibilities.”

The most current Environmental Commitment Statement is posted on the Seymour Johnson AFB public website.

FA480922B0001

Attachment 5 https://www.seymourjohnson.af.mil/Home/SJAFB-Environmental-Management/

DUTY TO CONFORM

Conformance with EMS is a directive issued from the highest offices of the Air Force and DoD. Because you are working for, or on behalf of, Seymour Johnson AFB, you are mandated to conform with the roles and responsibilities set forth in this training. Potential consequences for non-conformance are:

Adverse effects to human health and the environment Non-compliance with regulatory requirements resulting in possible

Notice(s) of Violation Punitive fines Incarceration

FA480922B0001

Attachment 5

CONGRATULATIONS

You have successfully completed the Seymour Johnson Air Force Base

Site-Specific EMS Awareness Training

Please fill out the attached certificate for your records

Also, please provide a copy of your certificate to your SJAFB Contracting Officer

FA480922B0001

Attachment 5 has satisfactorily completed

Seymour Johnson Air Force Base, North Carolina

Seymour Johnson AFB Site-Specific EMS Awareness Training

This certifies that

Completed on Date _________

FA480922B0001

Attachment 5

ENVIRONMENTAL�MANAGEMENT SYSTEM:�SITE-SPECIFIC TRAINING
WHAT IS AN EMS?
WHY USE AN EMS?
ISO 14001
THE EMS CYCLE
KEYS TO A SUCCESSFUL EMS
ACTIVITIES
ENVIRONMENTAL ASPECTS
ENVIRONMENTAL IMPACTS
SJAFB’s HIGH PRIORITY ASPECTS
YOUR ROLE IN EMS
ENVIRONMENTAL POLICY
DUTY TO CONFORM
CONGRATULATIONS
Slide Number 15