This solicitation notice announces an invitation for bids for a simplified acquisition of base engineer requirements indefinite-delivery indefinite-quantity contract at Seymour Johnson Air Force Base in North Carolina. The contract is set aside for certified 8(a) or 8(a) joint venture small businesses and will encompass a wide variety of individual construction tasks such as concrete, masonry, carpentry, plumbing, heating and air conditioning, electrical, roofing, pavement repair, excavation, welding, painting, site development, landscaping, asbestos and lead abatement and removal, and demolition to support base civil engineer activities. The base year will be for twelve months with four twelve-month option periods and one six-month extension period. Interested parties must register in the System for Award Management and subscribe to receive procurement announcements. The site visit is August 30, 2022 and bids are due October 4, 2022. The place of performance includes Seymour Johnson AFB, Fort Fisher Recreation Area, and Dare County Bomb Range in North Carolina.

View the file

Other files

File Type Posted
FA480922B0001 - Bid Record - 14-Dec-22 (2 pages).pdf PDF
FA480922B0001 Abstract - Bid Opening 14-Dec-22 (4 pages).pdf PDF
Solicitation Amendment - FA480922B00010006 (Conformed) (83 pages) posted 7-December-2022.pdf PDF
Solicitation Amendment FA480922B00010006 SF 30 (4 pages) dated 7-December-22.pdf PDF
25. Min Rqmnt Proj (VKAG 20-1040) SOO (10 pgs) Rev 3 dtd 6-Dec-2022.pdf PDF
FA480922B00010005 Request for Information dated 5-December-2022.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) Statement of Objectives (REVISION 02) (10 pages) dated 1-November-2022.pdf PDF
Solicitation Amendment - FA480922B00010005 (Conformed) (87 pages) dated 28-November-2022.pdf PDF
Solicitation Amendment FA480922B00010005 SF 30 (13 pages) dated 28-November-2022.pdf PDF
2. SABER XI Statement of Work (67 pages) Revision 3 dated 26Oct22.pdf PDF
28. Section 271000 Building Telecommunications Cabling System (13 pages) dated 27-Oct-22.pdf PDF
Solicitation Amendment FA480922B00010004 SF 30 (3 pages) dated 14-October-2022.pdf PDF
Solicitation Amendment FA480922B00010003 SF 30 (10 pages) dated 27-September-2022.pdf PDF
2. SABER XI Statement of Work (66 pages) Revision dated 24-Sept-22.pdf PDF
26. Minimum Requirement Project (VKAG 20-1040) Drawings (Full Set) (8 pages) Revision dated 9-Sept-22.pdf PDF
Solicitation Amendment FA480922B00010002 SF 30 (9 pages) dated 22-September-2022.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) Statement of Objectives (9 pgs) Revision dtd 22-Sept-22.pdf PDF
SABER XI Requests for Information (RFIs) and Responses (19 pages) 20 September 2022.pdf PDF
Solicitation Amendment FA480922B00010001 SF 30 (2 pages) dated 9-September-2022.pdf PDF
12. AF Form 66 Schedule of Material Submittals - VKAG 22-1200 SABER Basic XI (1 page) Revision dated 6-September-22.pdf PDF
SABER XI PreBid Conference and Site Visit Meeting Minutes with Attachments (18 pages) dtd 30 Aug 22.pdf PDF
10. SJAFB Standard Engineering Drawing Preparation and Support (CAD Standards) (71 pages) dated 1-Dec-22.pdf PDF
23. SABER XI IDIQ Bid Schedule (2 pages) - BLANK.pdf PDF
18. Request for Information (1 page) - BLANK.pdf PDF
14. AF Form 103 Base Civil Engineering Work Clearance Request (2 pages) - BLANK.pdf PDF
12. AF Form 66 Schedule of Material Submittals - VKAG 22-1200 SABER Basic XI (1 page) dated 24-May-22.pdf PDF
Solicitation - FA480922B0001 - SJAFB SABER (Posted 19-Aug-22).pdf PDF
19. Contractor Production Report (QC Report) (8 pages) - EXAMPLE.pdf PDF
5. Environmental Management System Site-Specific Training (15 pages) dated April-22.pdf PDF
7.Section 02821 Centipede Grass Hydro-Seeding (10 pages) dated 24-May-22.pdf PDF
22. Wage Determinations (51 pages) dated 25-Feb-22.pdf PDF
13. AF Form 66 Schedule of Material Submittals (1 page) - BLANK.pdf PDF
2. SABER XI Statement of Work (65 pages) dated 12-Aug-22.pdf PDF
25. Minimum Requirement Project (VKAG 20-1040) - Statement of Objectives (5 pages) dated 9-May-22.pdf PDF
15. AF Form 3000 Material Approval Submittal (2 pages) - BLANK.pdf PDF
27. Pre-Proposal Conference and Site Visit Location Map (2 pages).pdf PDF
4. Section 01560 Environmental Management Supplement SJAFB Contractors (2 pages) dated 5-Jul-22.pdf PDF
26. Minimum Requirement Project (VKAG 20-1040) Drawings (Full Set) (7 pages) dated 1-Nov-20.pdf PDF
20. SJAFB Access Request Application (2 pages) - EDITABLE.pdf PDF
24. Determination of Contractor Responsibility (3 pgs) - BLANK.pdf PDF
21. Climatic Data Summary for SJAFB (2 pages) dated 13-May-22.pdf PDF
11. Installation Development and Design (ID2) SJAFB (90 pages) dated Mar-11.pdf PDF
1. Nonapropriated Fund (NAF) Standard Clauses (21 pages) dated 2-Jun-22.pdf PDF
17. AF Form 3064 Contract Progress Schedule (3 pages) - EXAMPLE.pdf PDF
9. Seymour Johnson Mass Notification System Message Script (2 pages) dated 24-May-22.pdf PDF
8. Section 02938 Sod (2 pages) dated 24-May-22.pdf PDF
16. AF Form 3065 Contract Progress Report (1 page) - BLANK.pdf PDF
3. Section 01560 Environmental Protection (8 pages) dated 1-Jul-22.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02051

ASBESTOS REMOVAL, CLEAN-UP AND DISPOSAL AND FACILITY DEMOLITION

The term abate, as used in the plans and specifications, shall mean to remove, clean up, and dispose of asbestos containing materials (ACM). The work covered by this section includes the removal, clean up, and disposal of materials containing asbestos as well as permitted facility demolition.

a. DOCUMENTATION OF PERFORMANCE IN ASBESTOS REMOVAL

(1) Upon completion and acceptance, the Contractor shall furnish to the Contracting Officerdocumentation of successful performance in asbestos removal. This documentation will include names and addresses of purchasers of services and location of work performed.

(2) The Contractor shall have at all times in his possession at his office (one copy) and in view at the job-site (one copy) OSHA Regulation 29 CFR 1926.58; Asbestos and Environmental Protection Agency 40 CFR, Part

61, Sub-part B; National Emission Standard for Asbestos, Asbestos Stripping Work Practices, and Disposal of

Asbestos Waste; N.C. General Statute 130A, Article 19, Asbestos Hazard Management.

b. REGULATORY REQUIREMENTS

(1) All asbestos removal clean-up and disposal shall be made in accordance with:

a. N.C. General Statute 130A, Article 19, 29 CFR 1910.1001(all), 29 CFR 1926.1101, and OSHA

Regulation 1926.58, Asbestos, permissible exposure limits for asbestos shall apply to all air samples.

1. Amosite 0.01 fibers/cc

2. Chrysotile 0.01 fibers/cc

3. Crocidolite 0.01 Fibers/cc

4. All Others 0.01 fibers/cc

(2) EPA 40 CFR, Part 61, all sub areas – National Emission Standard for Asbestos, Asbestos Stripping, Stripping Work Practice and Disposal of Asbestos Waste.

(3) Other State and Local Agency Requirements

c. SUBMITTALS:

(1) Pre-Removal Plan: Submit a draft abatement permit application and detailed plan of the work procedures to be used in the removal and demolition of materials containing asbestos. The pre-removal plan must be approved and signed by an N.C. State accredited Asbestos Abatement Project Designer. Such plan shall include location of asbestos control areas, change rooms, layout of change rooms, interface of trades involved in the construction, sequencing of asbestos related work, disposal plan, type of wetting agent and asbestos sealer to be used, air monitoring, and a detailed description of the method to be employed in order to control pollution. This draft application and plan, along with the final state permit(s), must be approved prior to the start of any asbestos work.

Subsequently, provide Base Contracting copies of all permits and notifications sent to agencies. Include North

Carolina Asbestos Accreditation Certificates for each worker and Accredited Supervisor and Asbestos Removal

Permits/Notifications when removal quantities required by N.C. Statute 130A, Article 19.

(2) Submit personnel and space air monitoring and final clearance reports.

(3) Training: Submit certificates signed by each employee that the employee has received current accredited training within 14 months of scheduled removal work in the proper handling of materials that contain asbestos; understands the health implications and risks involved, including the illnesses possible from exposure to

FA480922B0001

Attachment 6

Current as of 24-May-2022 airborne asbestos fibers; understands the use and limits of the respiratory equipment to be used; and understands the results of monitoring of airborne quantities of asbestos as related to health and respiratory equipment.

(4) Return manifest signed by company or landfill accepting custody of asbestos waste within 24 hours.

Minimum information on the manifest shall include; date of disposal, quantity, sources of asbestos, waste type of insulation (pipe, duct, etc), name of certified/licensed asbestos removal Contractor.

d. REMOVAL, CLEAN-UP AND PREPARATION: The Contractor shall have proper dress and equipment for all personnel. The Contractor shall provide proper decontamination facilities. The method of asbestos removal shall be conducted as required by regulation. Work areas shall be decontaminated prior to resuming other activities.

e. PHASING AND SCOPE: Phasing of asbestos removal will be coordinated by the General Contractor and approved by the Contracting Officer.

f. PERMITTED FACILITY DEMOLITION: Pre-Removal Plan: Submit a draft demolition permit application and plan of the work procedures to be used in the removal and demolition of entire facilities or structures. This draft application and plan, along with the final state permit(s), must be approved prior to the start of any demolition work.

Subsequently, provide Base Contracting copies of all permits and notifications sent to agencies. Include North

Carolina Asbestos Accreditation Certificates for each worker and Accredited Supervisor and Asbestos Removal

Permits/Notifications when removal quantities required by N.C. Statute 130A, Article 19.