This document is Amendment 0003 to Solicitation 140R4024R0020 for the Hyrum Dam Spillway Replacement project. The work includes construction of a new reinforced concrete spillway, riprap outlet channel, mechanical and electrical features, drainage systems, foundation aggregate piers, a roadway bridge, gate hoist structure, radial gates, embankment dike, new inverted siphons, administrative access road, and removal of the existing spillway structure. The period of performance is from March 2025 to January 2029. The contracting agency is the Department of the Interior Bureau of Reclamation. The amendment modifies the construction price schedule and updates the period of performance dates.

View the file

Other files for this federal contract opportunity

Other files attached to Hyrum Dam Spillway Replacement, newest first.
File Type Posted
A0003_Att_6_Updated_Solicitation_Pages_12-14_0003.pdf PDF
A0003_Att_7_Updated_Continuation_of_Section_B_in_Excel_Format_0003.xlsx XLSX spreadsheet
A0003_Att_1_Informational_Page_0003.pdf PDF
A0003_Att_2_140R4024R0020_Additional_Technical_Questions_and_Answers_0003.pdf PDF
A0003_Att_3_(Revised)_188-D-60267_0003.pdf PDF
A0003_Att_4_(Revised)_03_30_00___Cast-In-Place_Concrete_0003.pdf PDF
A0003_Att_5_(Revised)_33_46_36___Drain_Pipes_0003.pdf PDF
A0002_Att_13_(Revised)_188-D-60379_Gate_Hoist_Enclosure_Panel_Schedules_0002.pdf PDF
A0002_Att_15_(New)_40-D-4335_0002.pdf PDF
A0002_Att_17_(New)_40-D-6551_0002.pdf PDF
A0002_Att_20_(New)_40-D-7017_0002.PDF PDF
A0002_Att_1_Informational_Page_0002.pdf PDF
A0002_Att_4_140R4024R0020_Technical_Questions_and_Answers_0002.pdf PDF
A0002_Att_6_(New)_01_46_20_-_Testing_Agency_Services_0002.pdf PDF
A0002_Att_7_(Revised)_02_41_07_-_Removal_and_Disposal_of_Existing_Features_0002.pdf PDF
A0002_Att_11_(Revised)_51_02_82_-_Hazardous_Materials_Survey_and_Analytical_Results_0002.pdf PDF
Sol_140R4024R0020_Amd_0002.pdf PDF
A0002_Att_19_(New)_40-D-6592_0002.PDF PDF
A0002_Att_23_Evaluations_of_Potential_Filter_Sand_and_Drain_Gravel_Sources_for_Hyrum_Dam_Modifications_0002.pdf PDF
A0002_Att_18_(New)_40-D-6552_0002.pdf PDF
A0002_Att_21_(New)_40-D-60001_0002.pdf PDF
A0002_Att_8_(Replacement)_31_03_33_-_Removal_and_Control_of_Water_0002.pdf PDF
A0002_Att_14_(New)_40-D-4334_0002.pdf PDF
A0002_Att_12_(New)_188-D-60215_Existing_Spillway-Dike_Plan_0002.pdf PDF
A0002_Att_2_140R4024R0020_Contracting_Questions_and_Answers_0002.pdf PDF
A0002_Att_3_Updated_Solicitation_Pages_62-67_0002.pdf PDF
A0002_Att_5_(New)_01_14_20_-_Reservoir_Spillway_and_Outlet_Works_Operations_0002.pdf PDF
A0002_Att_9_(New)_35_21_20_-_Stoplog_Guides_0002.pdf PDF
A0002_Att_10_(New)_51_00_20_-_Reservoir_Water_Surface_Elevation_Data_0002.pdf PDF
A0002_Att_22_(New)_40-D-60002_0002.pdf PDF
A0002_Att_16_(New)_40-D-6477_0002.pdf PDF
A0002_Att_25_Hyrum_Spillway_Replacement_Geological_Investigations_2022_0002.pdf PDF
A0002_Att_24_Geologic_Investigations_of_Hyrum_Dam_Spillway_2016-2019_0002.pdf PDF
Sol_140R4024R0020_Amd_0001.pdf PDF
A0001_Att_1_Informational_Page_0001.pdf PDF
A0001_Att_2_Site_Visit_Sign-in_Sheet_0001.pdf PDF
Sol_140R4024R0020.pdf PDF
Attachment_7_SF24_Bid_Bond_Form.pdf PDF
Solicitation_No__140R4024R0020_Hyrum_Dam_Spillway_Replacement.pdf PDF
Attachment_3_Current_Spillway_Drawings_(Info_Only).pdf PDF
Attachment_2_140R4024R0020_Drawings_90_.pdf PDF
Attachment_4_Continuation_of_Section_B_in_Excel_Format.xlsx XLSX spreadsheet
Attachment_5_Construction_Wage_Rate_Requirements_for_Cache_County__UT.pdf PDF
Attachment_6_Subcontracting_Plan_Template.docx DOCX document
Attachment_1_140R4024R0020_Specifications_90_.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140R4024R0020 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Salt Lake City UT 84138

R40

125 South State Street, Room 8100 Regional Office Upper Colorado Region Bureau of Reclamation

11/11/20240003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/14/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

For full Amendment 0003 information, please see Attachment A0003_Att 1 Informational Page.

Period of Performance: 03/07/2025 to 01/26/2029

Change Item 00010 to read as follows(amount shown is the obligated amount):

00010 HYRUM DAM SPILLWAY REPLACEMENT

Please See Updated Continuation of Section B -

Construction Price Schedule

(CLINS 00010-01 through 00010-83)

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Lynette H. Rock

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140R4024R0020/0003

Product/Service Code: Z2KA

Product/Service Description: REPAIR OR ALTERATION

OF DAMS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .