This document is a section of a contract for the removal and disposal of existing features as part of the Hyrum Dam Spillway Replacement project in Utah. The work includes removing and disposing of various elements such as underdrain piping, radial gates, a concrete bridge deck, fencing, and concrete walls. The contractor must submit plans detailing the equipment, transportation methods, and disposal locations for the debris. Specific requirements are provided for draining and recycling oil from the hoist equipment and breaking demolished concrete into pieces with a maximum 3-foot dimension. The contractor is prohibited from using blasting for the removal of existing structures. Removed materials must be disposed of in accordance with the contract requirements. This section is part of the overall Hyrum Dam Spillway Replacement project, which involves constructing a new spillway and removing the existing one, with an anticipated performance period of March 2025 through January 2029.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hyrum Dam Spillway Replacement Hyrum Project, Utah
Removal and Disposal of Existing Features
02 41 07 - 1
SECTION 02 41 07
REMOVAL AND DISPOSAL OF EXISTING FEATURES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Removal and Disposal of Existing Features:
1. Payment: Lump sum price offered in Price Schedule A.
a. Includes removal and disposal of the following features:
1) Existing underdrain piping where necessary and as determined by
COR.
2) Radial gates, hoists, hoist enclosure, and any other hoist equipment.
3) Existing concrete bridge deck.
4) Existing chain link fence along spillway walls.
5) Existing ROW fencing along the county road.
6) Existing parapet wall and curb at new spillway excavation and at excavation for existing spillway removal.
7) Test Section
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 02 41 07-1, Removal and Disposal of Existing Features Plans:
1. Including but not limited to the following:
a. Equipment to be used.
b. Transportation methods for debris.
c. Disposal location of debris.
2. For each sequence of work requiring Removal and Disposal of Existing Features.
C. RSN 02 41 07-2, Used Oil Disposal Verification:
1. Verification from recycling center including name, address, quantity recycled and date of recycling.
02 41 07 - 2
1.03 PROJECT CONDITIONS
A. Existing chain link fence is 7-foot-high, consisting of 6 feet of fabric and 1 foot of 3-strand barbed wire. The fence posts are either top-mounted atop concrete wall or slab, or embedded in concrete footings in soil installation.
B. Existing chain link fence gate is a personnel gate, of same size and materials as chain link fence.
C. Contractor shall determine extents of fence removal as required to accommodate site and structure construction.
D. Oil in hoist equipment does not contain PCBs. See Section 51 02 82 - Hazardous Materials Survey and Analytical Results.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 PREPARATION
A. Verify required items of demolition with the COR prior to preparation of the Removal and Disposal of Existing Features Plan submittal.
3.02 EQUIPMENT REMOVAL
A. Hoist Equipment Oil:
1. Drain and collect oil from hoist equipment.
2. Recycle at Type C or D permitted used oil collection center in accordance with
R315 UAC.
B. Remove equipment with coatings in accordance with Section 02 83 30 - Removal and Disposal of Equipment with Coatings Containing Metals.
3.03 STRUCTURE REMOVAL
A. Blasting will not be permitted for removal of existing structures.
B. Remove materials associated with the features identified on the drawings in accordance with the approved plan.
C. Break demolished concrete into pieces with a maximum dimension of 3 feet in any direction, with steel reinforcement cut off flush with any surface.
02 41 07 - 3
3.04 FENCE REMOVAL AND DISPOSAL
A. Remove and dispose of chain link fence and related materials where needed for removal of the existing spillway and crest structures, only when authorized by the COR.
B. Removal methods and equipment are subject to approval of COR.
C. Assume no salvage value for removed fencing and related materials.
D. ROW fencing along the county road to be removed.
3.05 STRUCTURE DISPOSAL
A. Dispose of concrete features by wasting into stilling basin in accordance with drawings, and Section 01 74 00 - Cleaning and Waste Management.
B. Uncoated rebar, conduit, pipe, wiring, embedded metal work, boxes and racks shall be removed and disposed in accordance with 01 74 00 - Cleaning and Waste Management.
END OF SECTION
02 41 07 - 4
This page intentionally left blank.