This is a specification section (01 14 10 - Use of Site) from a federal construction contract for the Stampede Penstock and Butterfly Valve Rehabilitation project on the Washoe Project in California (Specifications No. 20-C0943).

The specification establishes requirements for the Contractor's use of Government land and site management during construction activities. All costs associated with site use are to be included in prices for other contract line items. The Contractor must submit a Land Use and Landscape Rehabilitation Plan identifying the location and extent of all temporary facilities including buildings, service areas, parking, temporary roads, haul routes, utilities, waste processing areas, and temporary fencing. The plan must describe methods to preserve and protect vegetation and landscape features not scheduled for removal, mark work area limits, protect disturbed areas, prevent erosion, protect existing improvements and utilities, and remove temporary structures and rehabilitate the site upon completion. The Contractor must also submit revised drawings documenting any changes in Government land use made during design and erection stages. Site documentation via color digital video recorded on an approved electronic device must be provided prior to construction start, capturing conditions of land, vegetation, structures, utilities, roads, parking areas, and other existing facilities. All construction equipment must be cleaned before arriving onsite to remove dirt, vegetation, and organic material to prevent introduction of noxious weeds and invasive species, with cleaning procedures meeting or exceeding standards in the Bureau of Reclamation's 2012 Cleaning Manual. The Contractor may not house construction personnel on Government land except for guards or watchmen as approved by the Contracting Officer Representative (COR). Government vehicles must have access to the powerplant at all times, and temporary construction roads must be restored to original contours and made impassable to vehicles when no longer required.

View the file

Other files

File Type Posted
Sol_140R2026R0006_Amd_0005.pdf PDF
Amdt_0005-Attch_1-Questions_and_Answers_0005.pdf PDF
Amdt_0005-Section_J-Attch-6-Yaskawa_650_KW_Generator_Drawings_0005.pdf PDF
Attch_3-Section_00_01_10-Table_of_Contents_0004.pdf PDF
Attch_6-Section_01_35_20-Safety_and_Health_0004.pdf PDF
Attch_14-Questions_and_Answers_0004.pdf PDF
Attch_13-New_For_Information_Only_(FIO)_Drawings_0004.pdf PDF
Attch_7-Section_01_35_50-Site_Security_0004.pdf PDF
Attch_8-Section_01_57_30-Water_Pollution_Control_0004.pdf PDF
Attch_1_-_Revised_Specifications_0004.pdf PDF
Attch_5-Section_01_33_00-Submittals_0004.pdf PDF
Attch_11-Section_31_03_33-Removal_and_Control_of_Water_0004.pdf PDF
Attch_12-Section_52_00_00-Drawings_0004.pdf PDF
Sol_140R2026R0006_Amd_0004.pdf PDF
Attch_2-Section_00_00_50-Section_B___0004.pdf PDF
Attch_9-Section_01_57_70-Fire_Protection_and_Prevention_0004.pdf PDF
Attch_10-Section_26_05_20-Grounding_and_Bonding_0004.pdf PDF
Att__1_Site_Visit_Attendance_Record_0003.pdf PDF
Sol_140R2026R0006_Amd_0003.pdf PDF
Sol_140R2026R0006_Amd_0002.pdf PDF
C05_04_Solicitation_140R2026R00006_0002.pdf PDF
Non-Disclosure_Agreement_(NDA_-_Stampede_Penstock_and_Butterfly_Valve_Rehab_0001.pdf PDF
Sol_140R2026R0006_Amd_0001.pdf PDF
Section_L_Amendment_0001_0001.pdf PDF
General_Decision_Number_CA20260007_Dated_01232026.pdf PDF
Past_Performance_Questionnaire.pdf PDF
Offeror_Responsibility_Information.pdf PDF
Release_of_Claims.pdf PDF
Sol_140R2026R0006.pdf PDF
Solicitation_140R2026R00006.pdf PDF
Notice_to_Contractors.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stampede Penstock and Butterfly Valve Rehab

Washoe Project, California Specifications No. 20-C0943

Use of Site

01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (Reclamation)

1. Cleaning Manual-2012 Inspection and Cleaning Manual for

Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012

Edition Available online at:

https://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, stockpile areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences including location of access points and gates.

b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to

01 14 10 - 2 jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

C. RSN 01 14 10-2, Site Documentation:

1. Specified site documentation on electronic device approved by the Government:

a. Label each device with contract number and title, Contractor’s name, and date video was made.

1.04 PROJECT CONDITIONS

A. Deleted Work hours: Refer to Section 01 14 12 – Work Restrictions.

B. Government land as shown on drawings as Contractor use areas may be used for required construction facilities.

C. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

D. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.

E. Do not interfere with work of other contractors or the Government.

F. Government Vehicles:

1. Government vehicles require access to the powerplant at all times.

G. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.

PART 2 PRODUCTS

Not Used

01 14 10 - 3

PART 3 EXECUTION

3.01 EXAMINATION

A. Site Documentation:

1. Document site conditions with color digital video prior to start of onsite construction operations.

2. Document condition of land, vegetation, structures, utilities, roads, parking lots, and other features of existing facilities at jobsite.

3. Obtain directions on required documentation from COR.

3.02 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in the Cleaning Manual.

3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.

3.03 RESTORATION

A. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.

END OF SECTION