This document is a Table of Contents for Section C (Description/Specifications) of a federal solicitation for the Stampede Penstock and Butterfly Valve Rehabilitation project at the Washoe Project in California (Solicitation No. 20-C0943).
The specifications are organized into nine divisions covering the full scope of rehabilitation work. Division 01 (General Requirements) addresses site management, safety protocols, submittals, environmental controls, and quality procedures. Division 02 (Existing Conditions) covers equipment removal, disposal, and hazardous materials abatement, including removal of coatings with regulated metals. Division 09 (Finishes) specifies coating requirements. Division 26 (Electrical) details electrical materials, conductors, grounding, raceways, and wiring checkout procedures. Division 31 (Earthwork) addresses water removal and control. Division 35 (Waterway and Marine Construction) covers valves and equipment installation. Division 48 (Electrical Power Generation) encompasses disassembly, reassembly, alignment, commissioning, packing box refurbishment, and wicket gate mechanism work. Division 51 (Information Available to Offerors) provides photographs, reservoir elevation records, and hazardous material survey results. Division 52 addresses contract drawings. The specifications emphasize contractor safety responsibilities, coordination meetings, product testing, protection of existing installations, environmental controls, and water pollution control measures required for this hydroelectric facility rehabilitation project.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stampede Penstock and Butterfly Valve Rehab
Washoe Project, California Solicitation No. 20-C0943
Table of Contents
00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 14 10 Use of Site 01 14 12 Work Restrictions
01 14 30 Interruption of Service 01 31 22 Coordination Meetings 01 31 30 Contract Document Management System
01 32 10 Construction Program 01 33 00 Submittals
01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health
01 35 30 Contractor’s Onsite Safety Personnel 01 35 50 Site Security
01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services
01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking
01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 32 Temporary Fencing
01 57 20 Environmental Controls 01 57 30 Water Pollution Control
01 57 70 Fire Protection and Prevention 01 60 00 Product Requirements 01 64 40 Government Furnished Products
01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Equipment Removal and Disposal 02 80 10 General Requirements for Hazardous Materials Abatement
02 83 35 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
DIVISION 09 – FINISHES
09 96 20 Coatings
Stampede Penstock and Butterfly Valve Rehab
Washoe Project, California Solicitation No. 20-C0943
Table of Contents
00 01 10 - 2
DIVISION 26 – ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 20 Grounding and Bonding
26 05 33 Raceways and Boxes 26 05 90 Wiring Checkout and Tests
DIVISION 31 – EARTHWORK
31 03 33 Removal and Control of Water
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 22 14 Valves and Equipment
DIVISION 48 – ELECTRICAL POWER GENERATION
48 13 04 Disassembly and As-Found Readings 48 13 07 Reassembly and Alignment
48 13 08 Commissioning 48 13 15 Packing Box Refurbishment
48 13 26 Wicket Gate Mechanism
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors
51 00 10 Photographs 51 00 20 Reservoir Elevation Records 51 00 50 Electronic Media Release
51 02 83 Hazardous Material Survey and Analytical Results
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF SECTION