Attch_2-Section_00_00_50-Section_B___0004.pdf
PDF 152 KB Posted
- Attached to
- Stampede Penstock and Butterfly Valve Rehab
- Solicitation number
- 140R2026R0006
About this file
This is a Price Schedule document for Solicitation No. 140R2026R0006, a Bureau of Reclamation contract for Stampede Penstock and Butterfly Valve Rehabilitation work.
The solicitation contains 11 Contract Line Item Numbers (CLINs) with specific supplies and services required. CLIN 1 covers Mobilization and Preparatory Work as a lump sum, with an estimated maximum of 10 percent of the total bid price per WBR 1452.232-81. CLIN 2 addresses Contract Document Management System (CDMS) as a lump sum. CLINs 3 through 6 involve surface preparation and coating work measured in square feet: blast and recoat services for interior surfaces of various penstock and valve components (3,100 sq ft); blast and recoat for butterfly valve components (80 sq ft); waterjet and recoat for air-vac pipes (160 sq ft); and coatings spot repair work (150 sq ft). CLIN 7 covers removal and control of water for the 90-inch outlet works as a lump sum. CLIN 8 requires delivery and control of water for down river minimum flow requirements at 1,460 million gallons. CLINs 9, 10, and 11 address equipment work: 24-inch valve replacement, 42-inch valve refurbishment, and wicket gate mechanism work, all as lump sum line items. All offers must be submitted for the complete Price Schedule with no partial bids accepted, and all pricing is subject to the terms and conditions of the solicitation.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 140R2026R0006 – Stampede Penstock and Butterfly Valve Rehab
Price Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
STAMPEDE PENSTOCK AND BUTTERFLY VALVE REHAB
B.1 WBR 1452.236-85 INSTRUCTION FOR MOBILIZATION MAR 2022
AND PREPARATORY WORK SCHEDULE
LINE ITEM – BUREAU OF RECLAMATION
The contracting officer estimates that the Section B Mobilization and Preparatory Work schedule line item should not exceed 10 percent of the total bid price. Your attention is directed to contract clause WBR 1452.232-81 Payment for Mobilization and Preparatory
Work, which reflects how the Government will pay for this line item, including how payment will be made when the price bid for this schedule line item is higher than the percentage stated herein.
(End of provision)
B.2 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory
Work, for CLIN 1.
(d) Definitions:
(1) CLIN – Contract Line Item Number
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1 1 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
2 01 31 30 Contract Document
Management System
(CDMS)
For the lump sum of $
B - 2
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
3 09 96 20 Blast and Recoat: Interior surfaces of 54-inch reducer, 42-inch penstock, 24-inch penstock, and 42-inch butterfly valve body
3100 sq ft $ $
4 09 96 20 Blast and Recoat: 42-inch butterfly valve leaf, inner headcover and air admission pipe, outer head cover, and operating ring
80 sq ft $ $
5 09 96 20 Waterjet and Recoat: 12-inch air-vac pipe and 14-inch air-vac pipe
160 sq ft $ $
6 09 96 20 Coatings Spot Repair:
90-inch outlet work head gate, exterior surface of
90-inch outlet work, interior surface of Unit 1 scroll case and stay vanes, exterior surfaces of 12-inch and 14-inch air-vac assembly
150 sq ft $ $
7 31 03 33 Removal and Control of
Water for 90 inch Outlet
Works
For the lump sum of $
8 31 03 33 Delivery and Control of
Water for Down River Minimum Flow
Requirements
1460 Mgal $ $
9 35 22 14 24-inch Valve
Replacement
For the lump sum of $
10 35 22 14 42-inch Valve Refurbishment
For the lump sum of $
11 48 13 26 Wicket Gate Mechanism For the lump sum of $
TOTAL FOR PRICE SCHEDULE $_________________
B - 3
END OF SUPPLIES OR SERVICES AND PRICES/COSTS