This document contains details for a federal contract solicitation to stabilize an administration building and construct a new visitor center at Pullman National Monument in Chicago, Illinois. The National Park Service is seeking proposals on a small business set-aside basis for a firm-fixed price contract with an estimated value between $5-10 million. The selected contractor will stabilize the existing three-story administration building, including exterior and interior masonry work, and construct a new 10,000 square foot visitor center on the first floor. The project also involves minimal build-out of the second and third floors, along with common areas and new mechanical, electrical and plumbing systems. Proposals are due on an unspecified date in July 2019, with an anticipated period of performance from September 2019 through August 2020. Coordination will be required with other concurrent construction and preservation projects at the site.

PSP Volume I

View the file

Other files for this federal contract opportunity

Other files attached to Pullman National Monument, PULL 223195-253045, newest first.
File Type Posted
191024_RFI_Response_WSP_009-010_MEP_detail.pdf PDF
11-S1.0_01STRPLN_S1-Addendum_191024.pdf PDF
5-084413_Glazed_Aluminum_Curtain_Walls.pdf PDF
4-10.22.19_-_Pullman_Visitor_Center_Camera_Changes.pdf PDF
8-A2.4B_INT_ELEV_A2-Addendum_191022.pdf PDF
10-ED1.0_POWER_1ST_FLOOR_DEMOLITION.PDF PDF
3-PULL_Visitor_Center,_Bidding_Questions_as_of_10-22-2019.pdf PDF
2-Amendment_Number_0006_Narrative.pdf PDF
1-140P2019R0048,_Amendment_No._0006.pdf PDF
9-A6.4_WINDDTLS_A6-Addendum_191022.pdf PDF
PULL_VC_Contractor_Site_Visit_Attendees_191017.pdf PDF
North_Bay_Electrical_Equipment.pdf PDF
PULL_223195_Sustainability_Checklist_2019-0619.pdf PDF
SF_30_-_140P2019R0048-Amendment_0005.pdf PDF
PULL_223195_ARCH_Submittal_List_2019-0820.pdf PDF
2-Amend__4,_Vol_II,_Instructions_.pdf PDF
B11_PULL_223195-253045_VC_prebid_attendees_191009.pdf PDF
1-Amendment__4_Narrative.pdf PDF
SF_30_Amendment___4_140P2019R0048.pdf PDF
PULL_Prebid_Notes.pptx PPTX presentation
PULL_Visitor_Center,_Bidding_Questions,_10-1-2019.xlsx XLSX spreadsheet
Amendment_0003_140P2019R0048.pdf PDF
B02_SF_30,_Amend_No._002.pdf PDF
E2.4_-_VC_Exhibit_Design_Part4.pdf PDF
E2.3_-_VC_Exhibit_Design_Part3.pdf PDF
_B08_PULL_223195-253045_Amend__1,_page_175_of_180,_preproposal.pdf PDF
B01_PULL_223195-253045_140P2019R0048_SF_1442,_Amend__1.pdf PDF
B08_PULL_223195-253045_Amend__1,_Narrative.pdf PDF
B08_PULL_223195-253045_Amend__1,_SF_30.pdf PDF
PULL_223195_ARCH_ContractPriceSchedule_rfp-6-18-19.xls XLS spreadsheet
D1_-_Pullman_Stabilization_Drawings.pdf PDF
1-PULL_223195_FINAL_Spec_BOOK_1_2019-0913.pdf PDF
2-PULL_223195_FINAL_Spec_BOOK_2_2019-0913.pdf PDF
B08_PULL_223195-153045_140P2019R0048_Binder1.pdf PDF
E1.3_-_Site_Development_Drawings_DRAFT_2019-0719_Part3.pdf PDF
B08_Solit_PSP_Vol_II_SubKPlanForm_REQD.doc DOC document
B_-_VC_Building_Soil_Sampling_Report_DAI.pdf PDF
D2_-_Pullman_Stabilization_Project_Manual.pdf PDF
E1.1_-_Site_Development_Drawings_DRAFT_2019-0719_Part1.pdf PDF
4-B03_PULL_223195-253045_General_Decision,_IL20190009_.pdf PDF
B08_Solit_PSP_Vol_II_SBSubKCalc.xlsx XLSX spreadsheet
C_-_Limited_Hazardous_Materials_Report_GSG.pdf PDF
A_-_Soils_Investigation_Report_TSC.pdf PDF
E2.1_-_VC_Exhibit_Design_Part1.pdf PDF
E2.3_-_VC_Exhibit_Design_Part3.pdf PDF
E2.4_-_VC_Exhibit_Design_Part4.pdf PDF
3-PULL_223195_FINAL_Drawings_2019-0913.pdf PDF
E1.2_-_Site_Development_Drawings_DRAFT_2019-0719_Part2.pdf PDF
6-PSP_Vol_II,_pkg.pdf PDF
E2.2_-_VC_Exhibit_Design_Part2.pdf PDF
Show all 50

Pullman National Monument, PULL 223195-253045 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pullman National Monument

Solicitation #: 140P2018R0048

PROJECT TITLE: Stabilize Administration Building and Construct New Visitor Center

PULL 223195-253045

REQUEST FOR PROPOSAL

(RFP)

Proposal Submission Package

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

For Technical Volume I:

1. Experience Questionnaire

2. Subcontractor Reference

3. Past Performance Questionnaire

For Business & Price Volume II:

1. SF 24 Bid Bond

2. Contract Price Schedule

3. General References

4. Proposed Equals

5. Hazardous Materials Identification Listing

6. Small Business Subcontracting Plan

7. Subcontracting Calculations

Project Experience Questionnaire Solicitation: 140P2019R0048

Submit responses to the questions below that address experience relative to the elements noted under the Project Experience evaluation subfactor in solicitation section L. Limit submittals to the quantity of projects and timeframes required in the solicitation. Expand the response sections shown below as needed to adequately address each question (this questionnaire may be expanded to multiple pages if needed).

Offeror Company Name

REFERENCED PROJECT INFORMATION

Project Title Title

Project Location City, State

Brief Project Description

Description

Project Owner Company Name POC: First & Last Name Phone: (XXX) XXX-XXXX

CONTRACTOR LIST

List Contractor(s) whose experience on the referenced project is being submitted for evaluation on this proposed project. If more than one contractor is listed (i.e. prime and subcontractors), provide information specific to that contractor.

Contractor Name

Role on Referenced

Project (Prime or Sub)

Trade

Price (list for each contractor’s specific work)

Performance Period

(calendar days) (list for each contractor’s specific work)

Original Final Original Final

Sparky’s Electrical Company Prime Prime $XXX,XXX $X,XXX,XXX XX XX

ABC Plumbing & Heating, Co Subcontractor Plumbing & Mechanical

$X,XXX,XXX $X,XXX,XXX XXX XXX

Subcontractor

PROJECT EXPERIENCE QUESTIONS

1. Describe the project work performed by all contractors listed above.

Response

2. Identify which Project Experience elements listed in section L of the solicitation each contractor’s work addresses.

3. Describe & provide reasons for any changes to the original price for the work described in question 2 above.

4. Describe and provide reasons for any changes to the original schedule for the work described in question 2 above.

5. Describe problems, associated with the work described in question 2 above, which were encountered and how they were resolved. Describe how the offeror’s proposal accounts for similar issues.

6. Describe the means and methods, associated with the work described in question 2 above, which were successful. Would you implement the same means and methods on the proposed project? Why or why not?

7. Provide any other additional project information you believe should be presented.

Subcontractor Reference READ CAREFULLY: The purpose of this form is for the offeror to list certain subcontractors identified in the Instructions, Conditions, and Notices to Offerors (Section L) who are considered critical to the successful accomplishment of the project. Use as many sheets as necessary. These subcontractor references should include additional relevant projects similar to the work described in the plans and specifications. Include Area Codes with all telephone numbers. Fill in the information by typing or printing legibly.

SUB CONTRACTOR (PROPOSED):

ADDRESS:

TELEPHONE NUMBER: ( )

# PROJECT NAME:

Name of Owner:

Location:

Prime Contractor

Telephone Number:

Subcontract $ Value:

Dates of Construction:

Reference Name and Telephone Number: ( ) .

Dates of Construction:

DESCRIPTION & SCOPE OF WORK

SPECIFIC AREAS OF EXPERIENCE (SEE INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER

INFORMATION – CAPABILITY CRITERIA):

PAST PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS: Offeror to complete Sections A and B and transmit questionnaire to reference.

Reference to complete Sections C and D and transmit back to Contracting Officer listed in section E.

A. CONTRACTOR INFORMATION

Company Name Company

Street Address Address

City City

State State

Zip Code XXXXX

DUNS Number XXXXXXX

Point of Contact Name, Email, Phone

B. CONTRACT INFORMATION

Project Title Title

Contract Number XXXXXXXXXX

Contract Type Firm Fixed Price / Time & Materials / Cost Reimbursable / Other

Awarded Contract Price $X,XXX,XXX

Current / Final Price $X,XXX,XXX

Contract Award Date XX/XX/XXXX

Contract Completion Date XX/XX/XXXX

Period of Performance XX/XX/XXX – XX/XX/XXX

Project Location Park or Street address, City, State

Client / Owner Company

Brief description of the contract & work effort:

Scope of work description

C. REFERENCE:

Name First, Last

Position / Title Title

Organization Agency or Company

Phone Number XXX-XXX-XXXX

Email Address Email

Signature Signature

Date XX/XX/XXXX

D. EVALUATION

Rating Definition

Exceptional

Performance met contractual requirements and exceeded many to the owner’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good

Performance met contractual requirements and exceeded some to the owner’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory Performance met contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal Performance did not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.

Unsatisfactory

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Evaluation Area Rating

Quality

Quality of workmanship (including subcontractors)? Choose an item.

Quality of and adherence to quality control plan? Choose an item.

Quality of informational and technical submittals? Choose an item.

Overall Quality Rating Choose an item.

Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Schedule (& Time Management)

Met project schedule milestones? Choose an item.

Responded to owner requests in a timely manner? Choose an item.

Informational and technical submittals submitted timely? Choose an item.

Promptly addressed scheduling issues? Choose an item.

Overall Schedule (& Time Management) Rating Choose an item.

Cost Control

Addressed differing & unforeseen site conditions so as to minimize additional costs? Choose an item.

Provided fair and reasonable pricing for contract modifications? Choose an item.

Submitted accurate and complete invoices? Choose an item.

Promptly paid subcontractors and suppliers? Choose an item.

Overall Cost Control Rating Choose an item.

Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Management

General oversight by project manager and superintendent? Choose an item.

Coordination with and control of subcontractors? Choose an item.

Avoidance of accidents & safety violations? Choose an item.

Addressed location factors (especially remote locations)? Choose an item.

Maintained good working relationship with owner representatives? Choose an item.

Demonstrated flexibility, innovativeness and cooperation in resolving potential problems? Choose an item.

Overall Management Rating Choose an item.

Small Business Subcontracting (& Labor Standards)

Met regulatory and contractual labor standards? Choose an item.

Successfully contracted with small and socio-economically disadvantaged businesses? Choose an item.

Quality and adherence to applicable subcontracting plans? Choose an item.

Overall Small Business Subcontracting (& Labor Standards) Rating Choose an item.

Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Regulatory Compliance

Met building and life safety codes? Choose an item.

Overall Regulatory Compliance Rating Choose an item.

Overall Recommendation:

Given what I know today about the contractor's ability to perform in accordance with the contract’s most significant requirements, I would recommend them for similar contracts: Choose an item.

Overall Comments:

E. RETURN:

Return by 2:00pm, MT / Date, October 22, 2019

Name Daryl Hawkins

Title Contract Specialist

Organization National Park Service – Denver Service Center

Email daryl_hawkins@contractor.nps.gov

B08_Solit_PSP_Vol I
B08_Solit_PSP_Vol_I_Exp_REQD
B08_Solit_PSP_Vol_I_SubRef
B08_Solit_PSP_Vol_I_PastPerf_REQD

File details come from the government source that posted it. Updated .