3-PULL_Visitor_Center,_Bidding_Questions_as_of_10-22-2019.pdf

PDF 126 KB Posted

Attached to
Pullman National Monument, PULL 223195-253045
Solicitation number
140P2019R0048
Issued by

About this file

This pre-solicitation notice provides details for a small business set-aside solicitation seeking a contractor to stabilize an administration building and construct a new visitor center at Pullman National Monument in Chicago, Illinois.

The scope of work involves tenant improvements to convert approximately 10,000 square feet of the first floor into a visitor center housing exhibits, retail, and staff spaces. It also includes repairs to the entire three-story administration building including masonry work, structural reinforcement, and light finish work on the upper floors. A single award firm-fixed price contract is anticipated for a period of performance from September 2019 to August 2020. The estimated price range is $5-10 million. The NAICS code is 236220 with a $36.5 million small business size standard. Responsible small businesses may submit offers which will be considered. The solicitation is expected to issue on or around July 18, 2019 through www.fedbizopps.gov.

Questions and Answers as of 10-25-2019

View the file

Other files

File Type Posted
Amendment_Number_0007_Narrative.pdf PDF
191024_RFI_Response_WSP_009-010_MEP_detail.pdf PDF
SF_30-Amendment_0007-140P2019R0048_10.28.19.pdf PDF
2-Amendment_Number_0006_Narrative.pdf PDF
8-A2.4B_INT_ELEV_A2-Addendum_191022.pdf PDF
11-S1.0_01STRPLN_S1-Addendum_191024.pdf PDF
4-10.22.19_-_Pullman_Visitor_Center_Camera_Changes.pdf PDF
5-084413_Glazed_Aluminum_Curtain_Walls.pdf PDF
9-A6.4_WINDDTLS_A6-Addendum_191022.pdf PDF
10-ED1.0_POWER_1ST_FLOOR_DEMOLITION.PDF PDF
1-140P2019R0048,_Amendment_No._0006.pdf PDF
7-282000_FL_-_Video_Surveillance.pdf PDF
PULL_223195_Sustainability_Checklist_2019-0619.pdf PDF
SF_30_-_140P2019R0048-Amendment_0005.pdf PDF
North_Bay_Electrical_Equipment.pdf PDF
PULL_VC_Contractor_Site_Visit_Attendees_191017.pdf PDF
PULL_Visitor_Center,_Bidding_Questions_as_of_10-21-2019-FINAL.pdf PDF
PULL_223195_ARCH_Submittal_List_2019-0820.pdf PDF
1-Amendment__4_Narrative.pdf PDF
B11_PULL_223195-253045_VC_prebid_attendees_191009.pdf PDF
SF_30_Amendment___4_140P2019R0048.pdf PDF
2-Amend__4,_Vol_II,_Instructions_.pdf PDF
PULL_Prebid_Notes.pptx PPTX presentation
PULL_Visitor_Center,_Bidding_Questions,_10-1-2019.xlsx XLSX spreadsheet
Amendment_0003_140P2019R0048.pdf PDF
E2.4_-_VC_Exhibit_Design_Part4.pdf PDF
B02_SF_30,_Amend_No._002.pdf PDF
E2.3_-_VC_Exhibit_Design_Part3.pdf PDF
_B08_PULL_223195-253045_Amend__1,_page_175_of_180,_preproposal.pdf PDF
B08_PULL_223195-253045_Amend__1,_Narrative.pdf PDF
B01_PULL_223195-253045_140P2019R0048_SF_1442,_Amend__1.pdf PDF
B08_PULL_223195-253045_Amend__1,_SF_30.pdf PDF
PULL_223195_ARCH_ContractPriceSchedule_rfp-6-18-19.xls XLS spreadsheet
E2.1_-_VC_Exhibit_Design_Part1.pdf PDF
E1.1_-_Site_Development_Drawings_DRAFT_2019-0719_Part1.pdf PDF
2-PULL_223195_FINAL_Spec_BOOK_2_2019-0913.pdf PDF
C_-_Limited_Hazardous_Materials_Report_GSG.pdf PDF
B_-_VC_Building_Soil_Sampling_Report_DAI.pdf PDF
4-B03_PULL_223195-253045_General_Decision,_IL20190009_.pdf PDF
D1_-_Pullman_Stabilization_Drawings.pdf PDF
B08_PULL_223195-153045_140P2019R0048_Binder1.pdf PDF
5-PSP_Vol_I,_pkg.pdf PDF
1-PULL_223195_FINAL_Spec_BOOK_1_2019-0913.pdf PDF
B08_Solit_PSP_Vol_II_SBSubKCalc.xlsx XLSX spreadsheet
E1.3_-_Site_Development_Drawings_DRAFT_2019-0719_Part3.pdf PDF
D2_-_Pullman_Stabilization_Project_Manual.pdf PDF
A_-_Soils_Investigation_Report_TSC.pdf PDF
B08_Solit_PSP_Vol_II_SubKPlanForm_REQD.doc DOC document
E2.3_-_VC_Exhibit_Design_Part3.pdf PDF
E2.2_-_VC_Exhibit_Design_Part2.pdf PDF
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

No. Date of Question

Question Response Response Issued

9/23/2019 Transoms of this size cannot be provided without vertical mullion, deadload of glass on horizontal is about 475 lbs., not sure if this is feasible.

Extrusions detailed appear to be low profile with no clear specification back-up other than CR Laurence or others as listed. Please advise.

Attached please find the following revised documents:

ꞏ Sheet A2.4B – changes bubbled

ꞏ Sheet A6.4 – changes bubbled

ꞏ Section 084413 – this should replace the previous section 084113 Aluminum Framed Entrances and Storefronts.

10/25/2019

9/24/2019 While there is irrigation called out on the plans, there is no direction as to acceptable products or manufacturers. I would like to verify that Rain Bird is an acceptable manufacturer for the project.

Could you confirm that Rain Bird is an acceptable manufacturer?

There is no irrigation on this project. 10/1/2019

9/25/2019 Robbins Lightning, Inc. received this project today and we are not listed as an Approved Lightning Protection Manufacturer. I have attached an approval letter about our company. Our websites are listed in the letter where you may view our products and services. We would like to be listed as an Approved Lightning Protection Manufacturer on this project and future projects.

Section 21 41 13 should be deleted from the project manual. It seems to have been inadvertently included from a very early design submission. The current Table of Contents is correct as it does not include that section.

There is no lightning protection scope of work in this project beyond protection of the existing.

10/1/2019

9/23/2019 We would like to request your consideration of our Spray Foam Insulation Product as an alternate for this project:

QUIK-SHIELD® 118 is the first Ultra-Efficient closed-cell, spray foam on the market today. It is specially formulated to increase jobsite efficiency, decrease labor and overhead costs, reduce jobsite risk, and deliver the lowest cost installed.

Key features of Quik-Shield 118

Core Density: nominal, 1.8-2.0 lb/ft3.

R-value at 1”: 6.6.

9% total renewable/recycle content.

Meets GREENGUARD Gold standard for low VOC’s.

12 hr. commercial project re-entry (vs. 24 hr. for the specified product).

Limited Lifetime Warranty QS118 has been approved with DC315

Spec Sedtion: 072119: This item is acceptible as an equal. 10/1/2019

10/1/2019 We respectfully submit for your consideration a request to approve products as an accepted substitute on Pullman National Monument Visitor Center (17-641872); please find substitution request form attached.

With over 30 years of experience, Scranton Products is the industry leader in plastic (HDPE) bathroom partitions and lockers. Constructed from premium, American-made solid plastic, our products resist dents, scratches, corrosion, graffiti and mildew. More information regarding the benefits of our products as well as technical data sheets and MSDS forms for the appropriate product(s), confirming performance as specified, can be reviewed via the links below:

Warranty LEED Points 2019 Color Texture Brochure Love the Look of Stainless Steel Hiny Hiders Partitions Specifications Engraving Brochure Hiny Hiders Brochure Health Product Declaration - Hiny Hiders HDPE vs Other Materials Comparison SP Artisan Woodgrain Collection

The HDPE partitions proposed in this substitution request are NOT equivalent in performance to the phenolic-core partitions specified.

10/21/2019

10/4/2019 Product substiution request, the Tormax TX1201, request to be approved as an “equal” in Section 087113 Automatic Door Operators. As the attached literature and specifications confirm, this product meets/exceeds all project requirements:

UL325

BHMA A.156.19

Rated for door leafs up to 550lbs Programmable to overcome wind conditions and stack pressure Additional safety features are standard, such as “reverse on obstruction” in both opening and closing

Tormax product meets the performance requirements of the specifications. Additionally though, the door operators in this project have to be fully compatible to operate with the all-glass entrance doors – thus the product should be coordinated with the GC and their entrance door manufactuer.

10/25/2019

10/8/2019 Would like to submit two Approved equal/Substitution requests.

The first request is for the hand dryers with our model; The Speedflow Plus, which includes a HEPA filter media to trap allergens and is also surface-mounted ADA compliant. The second request we are submitting is for the baby changing station with our model: the Babymedi. The Babymedi is ADA Compliant and includes a Biocote antimicrobial additive embedded onto its surface. Please note, our Speedflow Plus and Babymedi are more cost-effective to what is specified. Would you please consider it and advise?

Both of these products: Speedflow Plus (hand dryer) and Babymedi (diaper changing station) appear to meet or exceed the performance requirements of the specifications. They are acceptable equal products.

10/21/2019

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

10/9/2019 Product substitution request:

The Lapolla 4G is a high lift, high yield and low v.o.c. foam. It has a 1 hour re-entry for trades and a 2 hour re-occupancy for homeowners with 10 ACHs. This foam is also Green Guard Gold Certified.

This product appears to meet/exceed the performance requirements. It is compliant with the specifications and equal to the named manufacturers. However, it is not immediately clear from the available product data if their proprietary ignition barrier product can be tinted black. If it can, than it seems to meet the design requirements as well. If it con not, it does not meet the design requirements.

10/21/2019

10/11/2019 5) Drawing A5.4 Wall Details, Is Wall Type A1 used on the project?

6) Section L, Subfactor 2B – Schedule requires to submit the schedule in “MS Project Gantt Chart format”. Is Primavera Gantt Chart format acceptable?

7) Section L, Subfactor 2B – Schedule, requires the proposed schedule Notice to Proceed to be 12/01/2019. Given the requirements of Section 01 31 00, 1.3 A and B, as well as the moving bid due date, is this Notice to Proceed date still realistic?

8) Section 01 50 00, 3.3, B & C, Confirm that Site Project Contract will provide access roads and environmental controls including erosion protection and Traffic Controls.

9) Since the NPS contract will not be performing much, if any, soil disturbance; which Contract is responsible to obtain the Temporary Storm Water Pollution Prevention or the UPPP Permit?

10) Section 01 81 13, 1.1C, 2. Please Provide NPS Project Sustainability Checklist

5) Drawing A5.4 Wall Details, Is Wall Type A1 used on the project?

No

6) Section L, Subfactor 2B – Schedule requires to submit the schedule in “MS Project Gantt Chart format”. Is Primavera Gantt Chart format acceptable? Yes, Primavera is and acceptable format.

7) Section L, Subfactor 2B – Schedule, requires the proposed schedule Notice to Proceed to be 12/01/2019. Given the requirements of Section 01 31 00, 1.3 A and B, as well as the moving bid due date, is this Notice to Proceed date still realistic? January 6, 2020 is the anticipated NTP date.

8) Section 01 50 00, 3.3, B & C, Confirm that Site Project Contract will provide access roads and environmental controls including erosion protection and Traffic Controls.

The VC contractor (this contract) is responsible to coordinate traffic control with the site contractor, and be responsible for traffic control related to the VC construction.

9) Since the NPS contract will not be performing much, if any, soil disturbance; which Contract is responsible to obtain the Temporary Storm Water Pollution Prevention or the UPPP Permit?

Storm water PERMIT will be obtained by others, but the VC Contractor will still need to provide a Polution Prevention PLAN for their work.

10) Section 01 81 13, 1.1C, 2. Please Provide NPS Project Sustainability Checklist The Sustainability Checklist is provided herein; it includes the site work which is NIC.

10/21/2019

1) Drawing A5.3 detail 8 – Please provide material specifications including Finish color regarding the new cast stone cap with coating.

“with coating” should be removed from the note.

Cast stone specifications: A combination of white and/or gray Portland Cement, natural sand, marble and/or quartz aggregate and natural and synthetic pigments cast to produce a unit with a minimum compressive strength of 6,000 psi and a maximum 5 percent absorption and reinforced as required for stresses of transportation, handling and loads imposed by construction where used as lintels. Comply with ASTM C 1364. Provide cast stone by a manufacturer having at least 5 years’ experience and complies with standards of Cast Stone Institute. Finish of cast stone to meet appearance of existing limestone on building.

Acceptable manufacturers:

a. American Art Stone.

b. Continental Cast Stone.

c. Dallas Cast Stone.

d. Edwards.

e. Russell.

2) Is 3” spray insulation required for the underside of the floor slab of level 3 (2nd floor Ceiling)?

No

3) Drawing A1.2B, Wall Type B is shown along perimeter walls; however, the wall layers are not shown. Is Wall Type B to be installed?

Wall Type B is to be installed at all exterior wall at the second and third floors

4) Drawing A1.3B, Wall Type B is shown along perimeter walls; however, the wall layers are not shown. Is Wall Type B to be installed?

Wall Type B is to be installed at all exterior wall at the second and third floors

1) Drawing A5.3 detail 8 – Please provide material specifications including Finish color regarding the new cast stone cap with coating.

2) Is 3” spray insulation required for the underside of the floor slab of level 3 (2nd floor Ceiling)?

3) Drawing A1.2B, Wall Type B is shown along perimeter walls; however, the wall layers are not shown. Is Wall Type B to be installed?

4) Drawing A1.3B, Wall Type B is shown along perimeter walls; however, the wall layers are not shown. Is Wall Type B to be installed?

10/11/2019 10/21/2019

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

11) Section F, 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK. For scheduling purposes, will the Notice to Proceed be issued immediately after submission of bonding and insurance or will there be a Limited Notice to Proceed issued for submittals and preconstruction activities?

12) Section 013100, 1.8B, has the Government secured any General Permits with the municipality?

13) Section 013100, 1.8B lists potential permits required for this project. Since the NPS project is responsible up to 5 feet from the face of the building, please clarify permit/fees responsibility between Site and NPS projects.

14) Drawing T1.0, Will the NPS contract include the installation of the Six (6) underground conduits servicing cameras C18-C23 beyond the five feet (5’) from the outside face of building?

11) Section F, 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK. For scheduling purposes, will the Notice to Proceed be issued immediately after submission of bonding and insurance or will there be a Limited Notice to Proceed issued for submittals and preconstruction activities? NTP will be provided with the successful completion of the preconstruction submittals identified in Division 1.

12) Section 013100, 1.8B, has the Government secured any General Permits with the municipality?

We do not expect any municipal permits associated with the VC project.

13) Section 013100, 1.8B lists potential permits required for this project. Since the NPS project is responsible up to 5 feet from the face of the building, please clarify permit/fees responsibility between Site and NPS projects.

VC Contractor would be responsible for any permits associated with acquisition of temporary utilities. We do not expect any municipal permits associated with the building construction.

14) Drawing T1.0, Will the NPS contract include the installation of the Six (6) underground conduits servicing cameras C18-C23 beyond the five feet (5’) from the outside face of building?

YES. Conduits and cameras indicated on T1.0 are to be installed under this contract.

Cameras will be mounted on poles provided and installed by others.

10/21/2019

15) Drawing A6.0 Finish Legend Description: Carpet 1, 2 and 3. Please provide the style, color, sizes for all three carpet tiles described in the finish legend.

16) Drawing A6.0 Finish Legend Description: LVT. Please provide the color and size for this Tarkett LVT flooring?

17) Drawing A6.0 Finish Legend Description: Wood. Per manufacture Boen, additional information is needed engineered wood flooring. Please provide the size of flooring.

15) Drawing A6.0 Finish Legend Description: Carpet 1, 2 and 3. Please provide the style, color, sizes for all three carpet tiles described in the finish legend.

Specific finish Basis of Design products are indicated in the FINISH LEGEND at the top right of sheet A6.0

16) Drawing A6.0 Finish Legend Description: LVT. Please provide the color and size for this Tarkett LVT flooring?

Specific finish Basis of Design products are indicated in the FINISH LEGEND at the top right of sheet A6.0

17) Drawing A6.0 Finish Legend Description: Wood. Per manufacture Boen, additional information is needed engineered wood flooring. Please provide the size of flooring.

Specific finish Basis of Design products are indicated in the FINISH LEGEND at the top right of sheet A6.0. The wood is indicated to be 100mm.

10/21/2019

10/10/2019 In regards to the fire alarm system. I saw that there was an existing EST Fire Alarm system existing. The specifications do not list a manufacture of the new Fire Alarm System. Can I propose/quote a Notifier System? Or do you need an EST fire alarm system?

Refer to specification 264001 section 1.5.B for acceptable manufacturers. Notifier by Honeywell is listed in acceptable manufacturer list. Follow book one front end specifications for substitution requests.

10/25/2019

10/3/2019 Clarification request:.

There is an existing zoned fire detection system in the NPS admin building that covers our structure as well as the state owned north wing. The panel is in the same location as the proposed new FACP.

The construction documents do not seem to acknowledge its existence nor the need for removal. There are general notes on sheets E 3.2 and E3.3 that talk about connecting existing devices, but that note does not exist on sheet E3.1. This could potentially be a problem as the way I'm reading now we could be inadvertently demo'ing the state's fire alarm system for the north wing with no provision to reconnect.

Is this something that was overlooked, or did I miss something noted elsewhere in the documents?

Existing Fire Alarm Annunicator Panel found at entrance to Visitor Center / Administration building will be removed, modified, and relocated to North Factory Wing first responder entrance. Refer to re-issued drawing ED1.0.

Existing fire alarm control panel for North Factory Wing, bays, is to remain in main electrical room 108 in North Factory Wing. Existing notification and detection devices found within administration building shall be disconnected from existing FA system and connected to new FACP dedicated to just visitor center. Refer to ED and E3 series drawings.

10/25/2019

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

10/15/2019 I wanted to follow up from my calls and touch base with you regarding the design of this project. I want to make sure that you are getting the most out of the design at the best value. The two possible issues that I see are as follows:

1 - The appliance that you have requested (PN VMA-AS3-24P18-NA - this is the updated version of the AS2) will not provide the days of retention and does not have sufficient throughput for the cameras that you are requesting. You would only get 19 days and 7 hours of storage at only 10FPS. (See calculation below)

2 - You have 8 180 deg. multi-head cameras at the 4 corners of the building. As we are more than willing to provide the cameras that you have requested, I have to let you know that there is a cheaper and simpler way to achieve the same amount of coverage. In addition to the 180 deg configuration, our multi-head cameras can be set to a 270 deg configuration. That would eliminate having 8 cameras at the corners of the building and cut that down to 3. And the one at the NE corner could remain a 180 deg. (See current camera locations below).

If eliminating the additional multi-sensor cameras from the design you would get the same coverage and still be able to use the appliance that you used on the spec. (See adjusted calculation below)

Please let me know how you would like me to proceed and I will get the information to the integrators that are bidding on this opportunity.

And please feel free to contact me with any questions or concerns.

270 degree cameras are acceptable. Subject to approval via the submittal process after contract award.

1. In the video surveillance section> 2.3: add the wording that the cameras must be compatible with the milestone recording system.

2: In the video surveillance section> 2.8: REMOVE manufacture and storage information and insert that NPS will supply the required power over ethernet switch and the Network Video Recorder.

Please find attached reissued drawings T0.1, T1.0, T1.1, T4.0, T5.0, T6.0, T7.1 and resissued specification 232000 Video Survelliance

10/21/2019

10/15/2019 The specs do not call out for any acceptable controls contractor for the Pullman National Monument project. I would like to know if there are any preferred temperature controls contractor for this project.

The specs call out products and performance, and do not indicate contractors or installers.

That would be up to the bidding GCs to determine who they believe can meet the requirements of the documents.

10/21/2019

10/17/2019 1. There is no spec for HVAC controls (typically 23 09 23), please provide as well as any acceptable manufacturers for devices, etc.

2.Fire dampers are only shown at deck penetrations at the first floor, please confirm if fire dampers will be required at other deck penetrations and/or penetrations through rated walls.

3.Specification 23 07 00 calls for boilers to be insulated, please confirm if this is applicable.

4.Specification 23 07 00 calls for board insulation on exhaust ductwork. Is this for sound attenuation? Please confirm.

1. All controls equipment and devices shall be those recommended by the equipment manufacturer. All controls shall be standalone, programmable electronic ddc.

Controls for the air handlers with associated condensing units and VAV boxes will be provided with Carrier i-Vu open controls as indicated on the air handling schedule keyed note #11 sheet M6-0. The two heating hot water boilers and associated primary-secondary hot water pumps to be controlled by boilers packaged controls.

2. Fire dampers shall be provided on all ductwork penetrating fire rated partitions. Currently in our project the majority required fire dampers are located on duct entering rated shafts at the first floor extending to the roof.

3. Boilers will not be insulated.

4. This section refers to exhaust or relief ductwork downstream the isolation motorized dampers and end exterior terminations like a gooseneck Sound insulation shall will be

10/25/2019

10/15/2019 Will there be a roofing report the composition of the existing roof? We would need to know for the amount dumpsters needed when quoting this.

Please let me know.

Please see the drawings in the D1 appendix (the Stabilization Drawings), Sheet’s A6.1 – A6.6. The roofing system shown in these details is the only one that is installed.

10/21/2019

10/18/2019 1. Just to confirm: Proposals Must be hard copied and mailed/messengered?

2. This bid is for only work covered in “Final” drawings. All other included drawings are for record/reference only?

3. There are only fire dampers shown at deck penetrations at the first floor.

4. Can we get confirmation that there will not need to be fire dampers at all deck penetrations and/or other fire rated walls on the plans?

5. I am not finding any spec sections for the controls. We will need that (typ. 23 09 23)

6. Also - need to know who the acceptable controls contractors are to get controls pricing.

1. Hard copies of the proposals must be received at the location provided by the due date and time.

2. FedBiz Ops Items 1, 2, and 3 are the drawings and specifications that outline the scope of work for this project. Items A, B, C, D, and E include supplemental information for the contractors understanding, consideration, and coordination when executing the scope of items 1, 2, and 3. All other items are contractual project requirements. Amendments may change any of the above items.

3-4. Fire dampers shall be provided on all ductwork penetrating fire rated partitions.

Currently in our project the majority required fire dampers are located on duct entering rated shafts at the first floor extending to the roof.

5. - 6. Controls for the air handlers with associated condensing units and VAV boxes will be provided with Carrier i-Vu open controls as indicated on the air handling schedule keyed note #11 sheet M6-0. The two heating hot water boilers and associated primary-secondary hot water pumps to be controlled by boilers packaged controls.

10/25/2019

10/17/2019 Can you provide information about the existing electrical system in the are ato the north of the Administration Building, in the factory bay owned by the State of Illinois?

Please see the attached photographs keyed to plan locations. 10/21/2019

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

10/21/2019 1. Specification 040120-2.4 Cleaning Materials – With regards to masonry cleaning, both interior and exterior, please confirm if cleaning materials listed in this section are the only ones allowed for use on the project.

2. Sheet A2.4A – Gen. Note 2. – Please confirm typical water spray methods for cleaning masonry will be allowed when cleaning the interior masonry walls.

1. Specification 040120-2.4 Cleaning Materials – With regards to masonry cleaning, both interior and exterior, please confirm if cleaning materials listed in this section are the only ones allowed for use on the project.

The expectation of masonry cleaning for this project is ONLY to gently remove existing biological growth on the north elevation, and provide a detergent cleaning of the masonry as a whole. A specific masonry cleaning program with chemical based cleaning products is not intended. It is understood and expected that the building will retain some of the patina of its age.

Substitutions to the specific cleaning products specified would be considered through the standard substitution procedure based on equivalent performance and/or benefit to the Government.

2. Sheet A2.4A – Gen. Note 2. – Please confirm typical water spray methods for cleaning masonry will be allowed when cleaning the interior masonry walls.

Any methods proposed are subject to approval via the pre-cleaning test procedure as described in 0401020/1.4/C

10/25/2019

10/22/2019 For stand sprinkler pipe through the roof, that should be a control valve in heated area , pleas provide details Who is the approved controls contractor for this project?

Plans call for PVC for all storm piping and sanitary and vents. Chicago doesn’t allow that in commercial. Are they anticipating getting the special permit that will allow it?

No rail around the 2 mezzanine area Are we to install all Exterior storm windows , as per detail 2/A6.7 provided by the government ? if yes is it all levels or just first floor Please clarify the attachment documents to addendum # 5 are not to be label as aluminum 6,7 and 8

For stand sprinkler pipe through the roof, that should be a control valve in heated area , pleas provide details Who is the approved controls contractor for this project?

Plans call for PVC for all storm piping and sanitary and vents. Chicago doesn’t allow that in commercial. Are they anticipating getting the special permit that will allow it?

This project is on Federal property and as such is designed to comply with IBC 2015. City of Chicago Building Code is not applicable to this project.

No rail around the 2 mezzanine area The mezzanine is fully enclosed with full height partitions.

Are we to install all Exterior storm windows , as per detail 2/A6.7 provided by the government ? if yes is it all levels or just first floor Storm windows (provided by the government) are to be installed at windows indicated with keynote A40 on sheets A2.0, A2.1 and A2.3. There are 12 first floor windows to which this note applies.

Please clarify the attachment documents to addendum # 5 are not to be label as aluminum 6,7 and 8 Addendums 6, 7, 8 are attachments related to addendum #5. This will be clarified in an upcoming amendment.

10/25/20119

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

10/22/2019

1. There is no spec for HVAC controls (typically 23 09 23), please provide as well as any acceptable manufacturers for devices, etc.

2. Fire dampers are only shown at deck penetrations at the first floor, please confirm if fire dampers will be required at other deck penetrations and/or penetrations through rated walls.

3. Specification 23 07 00 calls for boilers to be insulated, please confirm if this is applicable.

4. Specification 23 07 00 calls for board insulation on exhaust ductwork. Is this for sound attenuation? Please confirm.

5. On first floor core plan, there are no C1 walls north of Stair "S" (below the mezzanine), yet on the first floor build out plan there are F1 walls shown in the same location under the mezzanine. Please verify that C1 walls should be present on the first floor core plan north of Stair "S".

6. Opening 9 is shown on the door schedule as a type "K" casing with no door, however the interior elevations show this as a type E door/frame (assumed). Please verify if opening 9 is type E and provide hardware set.

7. New wood door frames, window trim and wood base are called out to be stained. Please verify if these items are to be field finished.

8. What are the finishing requirements of the furred walls on the third floor? Tape and level 4 finish? Are these walls painted?

9. Can you provide structural details where wall footings (2/S3.0) meet existing 5'-6" x 5'-6" footings?

1. All controls equipment and devices shall be those recommended by the equipment manufacturer. All controls shall be standalone, programmable electronic ddc. Controls for the air handlers with associated condensing units and VAV boxes will be provided with Carrier i-Vu open controls as indicated on the air handling schedule keyed note #11 sheet M6-0. The two heating hot water boilers and associated primary-secondary hot water pumps to be controlled by boilers packaged controls.

2. Fire dampers shall be provided on all ductwork penetrating fire rated partitions. Currently in our project the majority required fire dampers are located on duct entering rated shafts t the first floor extending to the roof.

3. Boilers will not be insulated.

4. This section refers to exhaust or relief ductwork downstream the isolation motorized dampers and end exterior terminations like a gooseneck. Sound insulation shall will be provided 10’ up & down the stream of any fan.

5.The partitions around the perimeter of the mezzanine are intended to be Type A/A1/A2 walls as indicated on the build-out plans. And furring (type F/F1) is intended to be provided on the bathroom side of the north wall of Stair S.

6. Opening 9 is to be a casing with no door as per the door schedule. Clarification:

overhead coiling security grilles per Specification 083113 are to be provided at the north side of the opening for Openings 8, 9, and 33.

7.Yes, field finished to match existing wood window finishes on site.

8. New walls to be primed and painted as indicated on the wall details A5.4. Finish for exposed walls to be level 4 per 092900 (except at the exhibit area where level 5 is specified).

9. Please see detail and note on re-issued Sheet S1.0

10/25/2019

10/22/2019 Per Amendment #00004, SUBCONTRACTING PLAN (only required for large businesses) - Please confirm that this requirement is still ONLY for Large Business.

When submitting a response as a JV, would the "up to three relevant project" be cumulative of the JV or can EACH JV partner submit up to three projects?

Please provide examples of three projects where the JV has worked together. Lacking that, provide no more than three projects in total, with at least one from each firm.

10/25/2019

10/23/2019 1. Are we requiring an elevator or just an opening? Did not see the specs for the elevator.

2. Is there a gas line to the building? Needed to determine if they can tap into it for heat or provide another heat source. They could find this information if they knew the exact address of the building. Apparently, the address we used is not exact address.

There is not an elevator included in the scope of this project.

There is not currently gas service to the building. The gas service line will be installed as part of the Site Development Project, by a different contract.

10/25/2019

22 10/22/2019 Binder 1 – Section H – Special Clause 3 (b): Small Business Participation is identified as “a minimum 20% of the total contract value is performed by Small Business.” However, in the attachment “Small Business Contracting Plan” as part 6-PSP_Vol II identified 43% as the goal for Small Business Concerns, 3% for HUBZone Small Business concerns and 5% for both Small Disadvantaged Business Concerns and Small Women Owned Business Concerns. Please confirm that the Small Business Contracting Plan is defined as “goals,” whereas the 20% Small Business Participation is a mandatory requirement for the proposal.

The Small Business Participation Plan is a separate requirement than the Small Business Subcontracting Plan.

All companies, large and small must submit a Small Business Participation Plan which guarantees 20 percent of the total contract value will go to small businesses.

All Large Businesses must submit a Small Business Subcontracting Plan with a goal of: Small Businesses (43%), Small Disadvantaged Businesses (5%), Women-Owned Businesses (5%), HUBZone (3%), and Service Disabled Veteran-Owned Businesses (3%), of the total dollars planned to be subcontracted. 10/25/2019

23 10/22/2019 Please confirm offer period is 90 Days as stated in Section 13.d of the SF1442. Confirmed 10/25/2019 24 10/22/2019 Please confirm that both Fabricator and Erector must be designated AISC Certified per 05 12 00 1.5 A-C. Confirmed 10/25/2019 25 10/22/2019 Please confirm that there will be single contract award for the sum of CLIN1 and CLIN 2 and that no scenario exists where separate contracts may be awarded to separate contractors where CLIN 1 as associated with 22253045 & CLIN 2 as associated with 223195 Confirmed 10/25/2019 26 10/22/2019 On drawing E1.4, the “A/B” note in the title block is shown indicating work in both CLIN1 and 2. Can you clarify what scope will be for A and B? On sheets E1.3 and E1.4 the following work is part of CLIN1(A): wall outlets and EHU's.

All other work is part of CLIN2 (B). 10/25/2019 27 10/22/2019 In specification 078100 Applied Fireproofing & 078123 Intumescent Fire Protection, for application of the products it says to assume all “Steel members are to be considered unrestrained unless specifically noted otherwise.” Can you confirm which new beams are to receive Intumescence and which are to receive Fire Proofing?

Intumescent fire protection is intended for exposed columns as indicated in the column details at A4.2. Applied fireproofing is intended for all other locations requiring protection. 10/25/2019

28 10/22/2019 On A4.6 there are callouts in the stair wells for “EXISTING STEEL BEAM SPRAY FIREPROOF BEAM AND METAL DECK.” Can you confirm the extent of spray fireproofing at the existing beam and the required spray fireproofing of the existing metal deck?

steel beam: entirely steel deck: within the stair enclosure 10/25/2019

29 10/22/2019 The table in section 2.2-C of specification 23 07 00 appears to indicate that the Exhaust Duct is to be insulated with glass fiber rigid board. Please confirm this is correct.

This section refers to exhaust or relief ductwork downstream the isolation motorized dampers and end exterior terminations like a gooseneck. Sound insulation shall will be provided 10’ up & down the stream of any fan. 10/25/2019

Pullman Visitor Center and Administration Building Stabilization Responses to Offerers Questions 10/25/2019

30 10/22/2019 The table in section 2.3-A of specification 23 07 00 appears to indicate that the Boilers are to be insulated with glass fiber board. Please confirm this is correct. Boilers will not be insulated 10/25/2019

31 10/22/2019 Please confirm if there are any alternate manufacturers allowed for the condensing boilers as none are identified in the specification. Additionally, please confirm that the basis of design manufacturer for the boilers is HTP as listed in the Mechanical Schedule on M6.2 Substitutions would be considered in accordance with front end requirements. 10/25/2019

32 10/22/2019 Number Notes #2 on drawing P1.0 appears at several instances where there is a 3" p-trap shown in the underground plumbing plan. There is a minimum 4" underground plumbing requirement in the City of Chicago. Please advise if we are to follow Chicago Building Code or the drawings.

This project is on Federal property and as such is designed to comply with IBC 2015. City of Chicago Building Code is not applicable to this project. 10/25/2019

33 10/22/2019 The first-floor build-out plan A1.0B shows what appears to be a chase at column line A8. Drawing F1.0, Sheet Note #7 calls for a new chase to accommodate the incoming 6” fire protection service near the same location as shown on the architectural plans, however the pipe is shown outside the chase wall. Please advise if this pipe should be located within the new chase wall depicted on A1.0B or if an additional chase wall is required

Pipe is intended to be within the chase wall.

10/25/2019 34 10/22/2019 Book 1 of the Construction Documents Specifications identify Division 31 Earthwork specifically 31 200 00 Earth Moving however the plan set does not indicate activities. Are we to assume that Earth Moving 21 20 00 is applicable to the immediate restoration of disturbed areas around the building, including construction and laydown areas?

As indicated in the specification, it is intended for: Preparing subgrades for slabs-on-grade;

Drainage course for concrete slabs-on-grade; Subsurface drainage backfill for walls and trenches; Excavating and backfilling trenches for utilities and pits for buried utility structures (within 5 feet of the building perimeter).

10/25/2019 35 10/22/2019 Please confirm Volume II, Business and Price Proposal submission format is (1) hard copy and (1) one electronic copy. Confirmed 10/25/2019 36 10/22/2019 We would like to request your consideration of TimberBlind MetroShade as a motorized window shade manufacturer. The product substitution request form is attached. TimberBlind MetroShade is acceptable. 10/25/2019

37 10/22/2019 Please confirm if window & shade blocking shown in Details1, 2, 3, 4 on A6.3 are existing to remain or new. Blocking indicated is to be provided under this contract. 10/25/2019 38 10/22/2019 Window trim on A6.3 is called out to be new and to match existing. On the walk-thru, we noticed that some windows are stained wood, and some are metal. Can you provide information on which windows will require trim to be painted to match the metal and which will be required to be stained to match the wood windows?

All new wood trim at windows under this contract is intended to be stained.

10/25/2019

39 10/22/2019 Can you please define the sizes and locations of rolling grilles/security gates? Currently, they are not in the door schedule and are only shown in some cut throughs.

Rolling grilles/security gates are to be provided on the north side of the opening at openings 8, 9, and 33. Fire shutter to be provided on the south side of the opening at opening 32.

10/25/2019

40 10/22/2019 Can a copy of a CPARS evaluation be included in addition to the PPQ form for projects completed under a joint venture and DUNS number different than proposing entity for this submission?

Yes, if it demonstrates the company’s role in completing the requirement is relevant to this requirement.

10/25/2019

41 10/22/2019 Please clarify the number of hard and electronic copies required for Volume 2 Business and Price Proposal submission. There is a discrepancy between the requirements issued in Amendment 4 and the PowerPoint presentation included in the Amendment 4 attached documents. FORMAT: Submit (1) hard copy and (1) one electronic copy.

10/25/2019

10/22/2019 Per Amendment #00004, SUBCONTRACTING PLAN (only required for large businesses) - Please confirm that this requirement is still ONLY for Large Business.

he Small Business Participation Plan is a separate requirement than the Small Business Subcontracting Plan.

All companies, large and small must submit a Small Business Participation Plan which guarantees 20 percent of the total contract value will go to small businesses.

10/25/2019

10/22/2019 When submitting a response as a JV, would the "up to three relevant project" be cumulative of the JV or can EACH JV partner submit up to three projects?

A total of up to three 1025/2019

10/22/2019 Clarification regarding scaffolding on north wing roof Add to Note 11, Sheet G1.0: The scaffold shall not rquire structural support of the north wing roof.

10/25/2019

END OF QUESTIONS