10-Exhibit I_NFPA 110 EPSS Maintenance and Operation Testing Log_04012026_BA.pdf
NFPA Standard PDF 321 KB Posted
- Attached to
- Generator IDIQ
- Solicitation number
- 1232SA26Q1346
About this file
This document is an NFPA 110 Maintenance and Operational Testing Log template for emergency power supply systems (EPSS) at the Beltsville Agricultural Research Center (BARC), a USDA-ARS facility in Beltsville, Maryland. The log is designed to document routine maintenance and operational testing of generators, automatic transfer switches (ATS), and manual transfer switches (MTS) under an Indefinite Delivery/Indefinite Quantity (IDIQ) contract for maintenance and repair services.
The template captures essential generator specifications including make/model, engine model, fuel type, serial number, standby kilowatt rating, normal operating temperature, normal oil pressure, and 30% of standby rating capacity. The testing log contains fourteen sequential steps that contractors must perform and document during each maintenance and operational test cycle. These steps include performing scheduled maintenance, recording running time meter readings at test start and end, simulating power failure from cold start, documenting time delays for startup and transfer operations, recording AC voltage/frequency/amperage measurements, monitoring oil pressure and battery charging rates at multiple intervals (initial, after 15 minutes of running, and prior to re-transfer), running the unit under load for a minimum of 30 minutes, recording re-transfer and shutdown time delays, and returning the unit to automatic operation mode. The log provides columns for multiple test dates to enable ongoing tracking and compliance documentation with NFPA 110 standards throughout the contract period.
View the file
Other versions and copies of NFPA 110
Show all 20
Who attaches NFPA 110
| State | Files |
|---|---|
| Massachusetts | 1 |
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BARC EPSS (Generator/ATS/MTS) Maintenance and Repair IDIQ Beltsville Agricultural Research Center (BARC) USDA-ARS, Beltsville, MD
Exhibit I NFPA 110 EPSS Maintenance and Operation Testing Log
NFPA 110 Maintenance and Operational Testing Log
Site/Location:
Generator Make/Model: Fuel Type:
Engine Model: Normal Operating Temp: Standby kW Rating: kW
Serial #: Normal Oil Pressure: 30% of Standby Rating: kW
Date Tested
1) Perform maintenance per Maintenance Schedule Test Specific Gravity Complete Checklist General Condition
2) Record running time meter (RTM) at start and end of test.
Start (Hrs.)
End (Hrs.)
3) Simulate power failure from a cold start using test switch or opening normal power supply.
4) Observe and record time delay (T/D) on start.
T/D Start (sec)
5) Record cranking time (terminates when engine starts).
Crank time (sec)
6) Transfer load to EPS Generator.
T/D Transfer (sec)
7) Record AC voltage, frequency, amperage.
AC Voltage Hz AC Amps AC kW
8) Record initial oil pressure and battery charging rate.
Oil pressure (psi) DC Amps
9) Record oil pressure, battery charging rate, and water or air temp after 15-min running time.
Oil pressure (psi) DC Amps Water/Air Temp
10) Re-transfer back to normal power after running under load for a minimum of 30 minutes.
11) Record engine and AC instruments just prior to re-transfer.
Oil pressure (psi) DC Amps Water/Air Temp AC Voltage Hz AC Amps AC kW
12) Record time delay on re-transfer.
T/D re-transfer (min)
13) Record time delay on shutdown for units so equipped.
T/D Stop (min)
14) Place unit in automatic operation mode.
Operator Initials