Main Ring Electrical P-F3 to P-F4 15KV Cable Installation, FESS Project 3-7-103B

Closed Solicitation Posted

Solicitation number
375108-CD
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Illinois 60510, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Energy's Fermi National Accelerator Laboratory is soliciting proposals for the installation of a 15KV medium voltage electrical cable system between P-F3 and P-F4 as part of the FESS Project 3-7-103B. The work encompasses furnishing all labor, materials, transportation, equipment, supervision, quality control, and safety oversight necessary to install approximately 15,000 feet of 15KV power cables and 5,800 feet of communication cables into an existing underground duct bank system. Qualifying offerors must demonstrate at least 10 years of construction industry experience in medium voltage cable installation, possess NFPA 70E compliance certification, and provide four past project examples with qualified key personnel including a Project Manager with 5 years of experience, a Project Superintendent with 10 years of experience, and a Safety Engineer with 5 years of experience. The procurement will be evaluated using a Lowest Price Technically Acceptable (LPTA) methodology, and all proposals must be submitted electronically by 4:00 PM Central Time on December 17, 2025, as extended by Amendment 03 issued on December 11, 2025.

This is a Total Small Business set-aside opportunity with a small business size standard of $45.0 Million under NAICS code 237130. The project timeline requires completion within 90 calendar days from the Notice to Proceed, with specific milestones including submission of all material submittals and commencement of work by day 15, completion of work on feeders requiring manhole entry by day 45, and final project completion by day 90. Fermi Forward Discovery Group, LLC will furnish specified materials including 750 MCM 15KV cable, 15KV splice kits, cable supports, communications cables, and 15KV air switches, while the subcontractor bears responsibility for all remaining materials and equipment. The work will be performed in Batavia, Illinois at the Fermi National Accelerator Laboratory site, and successful offerors must provide performance and payment bonds, comprehensive insurance coverage meeting specified minimums, Davis-Bacon Act wage compliance documentation, and detailed safety and quality assurance plans prior to contract award.

Notice text

4 versions

Update #4 · Latest ·

On 12/11/2025, Amendment 03 was issued to extend the proposal due date to 4pm CT on December 17, 2025. See atatched file for more information.

On 12/4/2025, Amendment 02 was issued to provide REVISED responses to some questions issued in Amendment 01, replaced the Revised Exhibit R- Proposal Form issued with Amenment 01, and Replaced Revised Drawing No.'s 3-7-103-B_E-5 and 3-7-103-B_E-10 issued in Amenment 01 with new revised drawings. See attached files for more information.

On 12/4/2025, Amendment 01 was issued to Replace Exhibit R- Proposal form, Replace Drawing No.'s 3-7-103-B_E-1A, 3-7-103-B_E-5, and 3-7-103-B_E-10 with Revised drawings, and to provide responses to questions from prospective offerors. See atatched files for more information.

The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to perform the work described in the Statement of Work entitled, “P-F3 to P-F4 15 KV Cable Install, Project 3-7-103B” dated November 3, 2025 and Drawing Set entitled “P-F3 to P-F4, 15KV Cable Installation, Project No. 3-7-103B, dated October 2025, Specification Sections 010010 – General Requirements (March 2025), Section 013100 FRA Environment, Safety, and Health Requirements (April 2025), Section 013300 – Submittals (January 2025), Section 014100 – Quality Requirements (October 2025),  mentioned therein, which the specifications, drawings, and other documents are attached to and hereby made a part of this Solicitation.

Update #3 ·

On 12/4/2025, Amendment 02 was issued to provide REVISED responses to some questions issued in Amendment 01, replaced the Revised Exhibit R- Proposal Form issued with Amenment 01, and Replaced Revised Drawing No.'s 3-7-103-B_E-5 and 3-7-103-B_E-10 issued in Amenment 01 with new revised drawings. See attached files for more information.

On 12/4/2025, Amendment 01 was issued to Replace Exhibit R- Proposal form, Replace Drawing No.'s 3-7-103-B_E-1A, 3-7-103-B_E-5, and 3-7-103-B_E-10 with Revised drawings, and to provide responses to questions from prospective offerors. See atatched files for more information.

The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to perform the work described in the Statement of Work entitled, “P-F3 to P-F4 15 KV Cable Install, Project 3-7-103B” dated November 3, 2025 and Drawing Set entitled “P-F3 to P-F4, 15KV Cable Installation, Project No. 3-7-103B, dated October 2025, Specification Sections 010010 – General Requirements (March 2025), Section 013100 FRA Environment, Safety, and Health Requirements (April 2025), Section 013300 – Submittals (January 2025), Section 014100 – Quality Requirements (October 2025),  mentioned therein, which the specifications, drawings, and other documents are attached to and hereby made a part of this Solicitation.

Update #2 ·

On 12/4/2025, Amendment 01 was issued to Replace Exhibit R- Proposal form, Repalce Drawing No.'s 3-7-103-B_E-1A, 3-7-103-B_E-5, and 3-7-103-B_E-10 with Revised drawings, and to providfe respones to questions from prospective offerors. See atatched files for more information.

The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to perform the work described in the Statement of Work entitled, “P-F3 to P-F4 15 KV Cable Install, Project 3-7-103B” dated November 3, 2025 and Drawing Set entitled “P-F3 to P-F4, 15KV Cable Installation, Project No. 3-7-103B, dated October 2025, Specification Sections 010010 – General Requirements (March 2025), Section 013100 FRA Environment, Safety, and Health Requirements (April 2025), Section 013300 – Submittals (January 2025), Section 014100 – Quality Requirements (October 2025),  mentioned therein, which the specifications, drawings, and other documents are attached to and hereby made a part of this Solicitation.

Update #1 ·

The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to perform the work described in the Statement of Work entitled, “P-F3 to P-F4 15 KV Cable Install, Project 3-7-103B” dated November 3, 2025 and Drawing Set entitled “P-F3 to P-F4, 15KV Cable Installation, Project No. 3-7-103B, dated October 2025, Specification Sections 010010 – General Requirements (March 2025), Section 013100 FRA Environment, Safety, and Health Requirements (April 2025), Section 013300 – Submittals (January 2025), Section 014100 – Quality Requirements (October 2025),  mentioned therein, which the specifications, drawings, and other documents are attached to and hereby made a part of this Solicitation.

Files

File Type Posted
Amend 03 to RFP 375018-CD.pdf PDF
375108-CD Amendmant 2 Revised Response to Questions.pdf PDF
375108-CD Amendment 2 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 2 Revised Drawings.pdf PDF
Amend 02 to RFP 375108-CD.pdf PDF
375108-CD Amendment 1 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 1 Revised Drawings.pdf PDF
375108-CD Amendmant 1 Response to Questions.pdf PDF
Amend 01 to RFP 375108-CD.pdf PDF
1.0 RFP 375108-CD.pdf PDF
Exhibit B1- Section 16010 General Electrical Requirements.pdf PDF
Exhibit B3- Section 16125 15KV Cable Installation.pdf PDF
Exhibit C- 010010 General Requirements.pdf PDF
Exhibit G- FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit J - Bond Payment FL-42.pdf PDF
Exhibit K- Bond Performance FL-40.pdf PDF
Exhibit L - Statement of Acknowledgment (SF-1413).pdf PDF
Exhibit Q- Summary of Required RFP Submittal Documents.pdf PDF
Exhibit B2- Section 16121 Medium Voltgage Cable.pdf PDF
Exhibit H - 2025 Construction Insurance Requirements.pdf PDF
Exhibit I - Bond Bid FL-41.pdf PDF
Exhibit M - Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit P- Davis Bacon Wage Rates.pdf PDF
Exhibit A- P-F3 TO P-F4 15KV Cable Installation SOW.pdf PDF
Exhibit E- 013300 Submittals.pdf PDF
Exhibit N - SARC_Subcontractor Annual RepsCerts Rev 4_FFDG.pdf PDF
Exhibit O - Proposal Certifications Form PUR-466_FFDG.pdf PDF
Exhibit S- Sample Firm-Fixed-Price Subcontract.pdf PDF
Exhibit B Drawings.pdf PDF
Exhibit B4- Section 16450 Grounding and Bonding.pdf PDF
Exhibit B5- Section 16950 Testing Electrical Systems.pdf PDF
Exhibit D- 013100 ESH Requirements.pdf PDF
Exhibit F- 014100 Quality Requirements.pdf PDF
Exhibit R - Proposal Form 375018-CD F3 to F4 15KV Cable Installation.pdf PDF
Show all 34

Similar open opportunities

Opportunity Agency Set-aside Responses due
Kautz road substation construcion, UIP subproject 2- KRS Batavia, Illinois 60510, United States · NAICS 237130 Fermi National Accelerator Laboratory No set-aside
Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB Batavia, Illinois 60510, United States · NAICS 236210 Fermi National Accelerator Laboratory No set-aside
PIP-II F-37 building LWC pump room piping system installation Batavia, Illinois 60510, United States · NAICS 23822 Fermi National Accelerator Laboratory No set-aside
Wilson Hall Floor 16 Electric and Elevator Machine Rooms Fire Rating and Mechanical Upgrade Illinois 60510, United States · NAICS 236220 Fermi National Accelerator Laboratory Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors